TABLE 1-List of Activities, Durations, and Precedences For A Mobile Office Installation Project
TABLE 1-List of Activities, Durations, and Precedences For A Mobile Office Installation Project
44
A Site layout
40
B Slab excavation
36
C Slab forms
32
D Place blocks
28
E Rough Plumbing
24
F Rough electrical
20
G Place concrete
16
H Place home
Remove forms 12
I
8
J Cure concrete
4
K Hookup home
0
L Cleanup
Daily Accomplishment 1 2 5 5 5 7 7 5 5 1 1 1 1 1 1
Accumulative Accomplishment 1 3 8 13 18 25 32 37 42 43 44 45 46 47 48 2