Critical Path Method: Farrokh Alemi, PH.D

The document discusses the critical path method (CPM) for project scheduling. CPM involves identifying all tasks, determining their duration and precedence relationships, and calculating the earliest and latest start and finish dates to find the critical path - the longest sequence of dependent tasks that determines the project's minimum completion time. CPM aims to finish projects as fast as possible while quantifying progress and enabling effective communication through formal schedules.

Uploaded by

Ali Kamel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
297 views40 pages

Critical Path Method: Farrokh Alemi, PH.D

The document discusses the critical path method (CPM) for project scheduling. CPM involves identifying all tasks, determining their duration and precedence relationships, and calculating the earliest and latest start and finish dates to find the critical path - the longest sequence of dependent tasks that determines the project's minimum completion time. CPM aims to finish projects as fast as possible while quantifying progress and enabling effective communication through formal schedules.

Uploaded by

Ali Kamel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 40

Critical Path Method

Farrokh Alemi, Ph.D.


Purpose of CPM

 Finish fast
 Quantify progress
 Communicate effectively

Course on Project Management


Advantages and Disadvantages of
Formal Schedules
 Saves time and money on large
complex projects
 Effective communication tool
 Too much work
 Assessment of duration of tasks
 Assessment of interdependencies

Course on Project Management


Resource Oriented and Time
Oriented Schedules
 Resource oriented
 Time oriented

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Obtaining list of patients
D Sample from list
E Mail surveys to selected patients
F Collect responses
G Analyze data

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost
Activity Description Precedents
A Select satisfaction survey tool
B Print survey tool A
C Select list of patients
D Sample from list C
E Mail surveys to selected patients D
F Collect responses E
G Analyze data F

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Activity Description Precedents Duration


A Select satisfaction survey tool 2 weeks
B Print survey tool A 3 weeks
C Select list of patients 1 week
D Sample from list C 1 week
E Mail surveys to selected patients D 2 weeks
F Collect responses E 4 weeks
G Analyze data F 3 weeks

Course on Project Management


Branch and Node Charts

 Activity on branch
 Activity on node

Course on Project Management


Activity In Node
A B E F G

C D

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Activity On Branches
A B E F G
1 3 5 6 7 End
Start
C D
2 4

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Earliest and Latest Start and
Finish Times

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Forward pass calculates early start and finish

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Backward pass calculates latest start and end times

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times

Critical Path includes activities where earliest start


A 2time and 3 E 2time Fare 4equal
B latest start G 3 End

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Activities not on the critical path have “slack.”
The latest start time
3 andEthe2earliest 4startGdate
3 are
A 2 B F End
different
Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Start Finish
Early 0
Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Start Finish
Early 0 2
Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F Start Finish
E 0 2 Early 2 5
L Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F
E 0 2 E 2 5
L L

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Start Finish
Early 2 5
Activity Description
Late A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F
E 0 2 E 2 5
L L

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F Start Finish
E 0 1 Early 1
Activity
2
Description
L Late A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F Start Finish
E 0 2 E 2 5 Early 5 7
L L Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F
S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L L

Latest finish is the minimum of latest start of


succeeding tasks. Latest start is the latest finish
minus duration.

Course on Project Management


Earliest and Latest Start and
Finish Times
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L L

Latest finish is the minimum of latest start of


succeeding tasks. Latest start is the latest finish
minus duration.

Course on Project Management


Earliest and Latest Start and
Finish Times
S F S F S F S F
S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F S F

E 0 2 E 2 5 E 5 7 E 7 11 E 11 14

L 0 2 L 2 5 L 5 7 L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
Activity Description
E 0 1 E 1 2
L 3 4 L 4 5 A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Slack Time
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L 0 2 L 2 5 L 5 7 L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L 3 4 L 4 5

Slack time = Latest start – Earliest start

Course on Project Management


Critical Path
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L 0 2 L 2 5 L 5 7 L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L 3 4 L 4 5

Critical path includes activities with no slack.

Course on Project Management


Communicating Project Schedule

 Time scaled network of activities


 Gantt chart
 Time an activity graphs and
completion graphs

Course on Project Management


Communicating Project Schedule

 Time scaled network of activities


 Gantt chart
 Time an activity graphs and
completion graphs

Course on Project Management


Communicating Project Schedule

 Time scaled network of activities


 Gantt chart
 Time an activity graphs and
completion graphs

Course on Project Management


Activity Splitting

A B E F G

C D

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Activity Splitting

A B E F G

C D

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Activity Splitting

A B E F1 G

C D F2

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses (F1=early, F2=Late) E
G Analyze data F

Course on Project Management


Software

 Discovery of Critical Path

Course on Project Management


Crashing Schedules

 Cost time tradeoff


 Order of crashing

Course on Project Management


Take Home Lesson

The critical path includes activities


with no slack