Execution Piles in Water
Execution Piles in Water
Execution Piles in Water
1. The Permanent steel casings are used for the pile alignment and for the control of
the soft upper layer and protect concrete process from washing.
2. Length of these pipes will depend on the depth of the soft upper-layer and the
water level.
4. The Casing will be installed within a maximum deviation from the center point of
the pile of 10% D in any direction.
Drilling of the Piles:
• After fixing the casing, the borehole shall be drilled down to the set toe level by the use of
buckets and/or augers mantled on the Kelly bar of the drilling rig.
• Subsequent to the completion of the drilling, the borehole depth and coordinates shall be
verified with respect to the shop drawings and the project’s coordinates by the Owner.
Disposal of drilling spoils:
Spoils/slurry resulting from drilling of boreholes shall be stored on floated Tank.
Cleaning of the Socket:
• The concrete shall be checked for the slump and temperature. Cube samples shall then
be taken as per specification.
• The concrete shall be supplied to the pile by transit mixers and placed by the full length
tremie pipe method.
• A mobile concrete pump shall be used to transfer the concrete from the truck mixer to
the pile.
• The tremie tube size shall not be less than 200 mm.
• The bottom of the tremie pipe shall remain throughout the casting process of at least 2m
embedded inside the concrete.