Power System Operation and Control: by DR Sai Ram Inkollu Professor
Power System Operation and Control: by DR Sai Ram Inkollu Professor
AND CONTROL
By
DR SAI RAM INKOLLU
Professor
UNIT-1
2
Power System Economic Operation
• Different generation technologies vary in the:
– capital costs necessary to build the generator
– fuel costs to actually produce electric power
• For example:
– nuclear and hydro have high capital costs and low operating costs.
– Natural gas generators have low capital costs, and (with gas available
from fracking) moderate operating costs.
3
Power System Economic Operation
• Fuel cost to generate a MWh can vary widely from technology to
technology.
• For some types of units, such as hydro, “fuel” costs are zero but the limit
on total available water gives it an implicit value.
4
Power System Economic Operation
• Power system loads are cyclical.
• Therefore the installed generation capacity is usually much greater than the
current load.
• This means that there are typically many ways we could meet the current
load.
5
Thermal versus Other Generation
The main types of generating units are thermal and hydro, with wind and
solar rapidly growing.
For hydro the fuel (water) is free but there may be many constraints on
operation:
– fixed amounts of water available,
– reservoir levels must be managed and coordinated,
– downstream flow rates for fish and navigation.
6
Generator types
Traditionally utilities have had three broad groups of generators:
– “Baseload” units: large coal/nuclear; almost always on at max.
– “Midload,” ‘intermediate,” or “cycling” units: smaller coal or gas that cycle
on/off daily or weekly.
– “Peaker” units: combustion turbines used only for several hours. during
periods of high demand
7
Block Diagram of Thermal Unit
•Between 2-10% of power is used within the generating plant; this is known
as the auxiliary power.
8
Thermal generator Cost Curves
Thermal generator costs are typically represented by one or other of the
following four curves
– input/output (I/O) curve
– fuel-cost curve
– heat-rate curve
– incremental cost curve
For reference
- 1 Btu (British thermal unit) = 1054 J
- 1 MBtu = 1x106 Btu
- 1 MBtu = 0.29 MWh
9
I/O Curve
The IO curve plots fuel input (in MBtu/hr) versus net MW output.
10
Fuel-cost Curve
The fuel-cost curve is the I/O curve multiplied by fuel cost.
A typical cost for coal is $ 1.70/MBtu.
11
Heat-rate Curve
• Plots the average number of MBtu/hr of fuel input needed per MW of output.
12
Incremental (Marginal) cost Curve
Plots the incremental $/MWh as a function of MW.
13
Mathematical Formulation of Costs
Generator cost curves are usually not smooth. However the curves can
usually be adequately approximated using piece-wise smooth,
functions.
16
Incremental Cost Example
For a two generator system assume
C1 ( PG1 ) 1000 20 PG1 0.01PG21 $/hr
C2 ( PG 2 ) 400 15 PG 2 0.03PG22 $/hr
Then
dC1 ( PG1 )
IC1 ( PG1 ) 20 0.02 PG1 $/MWh
dPG1
dC2 ( PG 2 )
IC2 ( PG 2 ) 15 0.06 PG 2 $/MWh
dPG 2
17
Incremental Cost Example, cont'd
If PG1 250 MW and PG 2 150 MW Then
C1 (250) 1000 20 250 0.01 2502 $ 6625/hr
C2 (150) 400 15 150 0.03 1502 $6025/hr
Then
IC1 (250) 20 0.02 250 $ 25/MWh
IC2 (150) 15 0.06 150 $ 24/MWh
18
UNIT-2
Hydrothermal Scheduling
19
Introduction
1. Long-range (weeks to year): Here we need the load forecast and expected
water flow from a rainfall forecast. Then we can predict the energy availability
from the hydro facilities and compute the necessary thermal energy.
2. Short-range (day to 1 week): Using results from (1) and more precise load
and water information, we can formulate a problem where the solution yields
the minimum cost of running the thermal plants on an hour-to-hour basis.
Hydro Station
Terminology
Penstock: The pipe leading from the water intake to the turbine.
Spillage: releasing water over the dam rather than through the penstock.
Some dams have spillways, as shown in Fig. 17, which allow smolts
(adolescent salmon) to pass without transiting through the turbines.
UNIT-3
UNIT COMMITMENT
UNIT-4
• Synchronous Generators
– can generate or absorb Q depending on
excitation
– capability limited by field current, armature
current, and end-region heating limits
– automatic voltage regulator continuously adjusts
excitation to control armature voltage
– primary source of voltage support!
• Overhead lines
– at loads below natural or surge impedance load
(SIL), produce Q
– at loads above SIL, absorb Q
• Underground cables
– have high SIL due to high capacitance
– always loaded below SIL, and hence generate Q
Transformers
absorb Q due to shunt magnetizing reactance and series leakage
inductance
Loads
a typical "load bus" is composed of a large number of devices
composite characteristics are normally such that a load bus absorbs Q
industrial loads usually have shunt capacitors to improve power factor
– characteristic impedance,
– electrical length, θ = βl
• The term static is used to denote that there are no moving or rotating
components
– thyristor-controlled reactor
– thyristor-switched capacitor
– saturated reactor
• During high system load conditions, network voltages are kept at highest
practical level to
– minimize reactive power requirements
– increase effectiveness of shunt capacitors and line charging
• The highest allowable operating voltage of the transmission network is
governed by
– requirement that insulation levels of equipment not be exceeded
– need to take into consideration possible switching operations and
outage conditions