Super Structure Construction
Super Structure Construction
Super Structure Construction
Transmission Tower
Launching girders
Sky Scrapper
Bridge decks
Cooling Tower
Offshore platforms
Erecting light weight
Special forms for shells components on tall
Braced domes and structures
Space decks Support structure for heavy
High Rise Structures equipments and conveyors
Move the unit, full or part of the deck, if any, is added after the basic
girder structure with adequate bracings is slewed in
Where pier height is too much it is adopted and in existing bridges case,
this method is adopted to replace the existing structure with stronger
unit
Common for both railway and road bridges but one difference is
deck, except for linking of rails in case of railway bridges and
weathering course & parapet in case of road bridges
For new bridges the staging for casting will have to be put up by
the side of the piers on one side
For steel girder bridges , staging are arrange them one behind the
other, linked with temporary links and launch them together
Launching Girders
Fully cast prestressed concrete girders are not launched independently as
the cantilevering stress developed is considerable and the design difficult
Once the launching of this girder over the gap on one side is over, the first
main girder is moved over this temporary girder or frame, supported at
intervals or pulled across
When the full length of the main girder has come over the span, it is jacked
up and temporarily held in position and the launching girder can be side –
slewed to take the position of the next girder over the span.
The main girder launched earlier is then lowered into position with
the helps of jacks
The next girder cast and ready on the approach is then launched
longitudinally over the temporary girder again and the process
repeated till all the permanent girders are put in position
The launching girder can then be moved over to the next span and it
can take the position required for taking on the first girder of the
next span
The girders of the next span can then be longitudinally taken over
the girders erected in the previous span and then over the
temporary girder on the next span and the process repeated
Erection of Concrete Girders with Cranes/ Derrick
If the bed is dry, the girders can be cast on the bed by the side of the
span and they can be erected by using two mobile cranes one on either
and with the help of a suitable derrick in the centre or one derrick each
on either end
If the height of the pier is not much and girders are too heavy to be
handled by the available crane or derrick, the girder can be jacked up
from either end on temporary trestles to pier top level and then side –
slewed in position launched and slewed has the minimum weight
In this method, the erection starts from the abutment end and the
erection of the members ahead is done by using a crane which travels
on the top boom of the previously erected part of the structure in case
of steel and by using the support on the previously erected part
structure in case of prestressed concrete construction
The height of piers and abutments are reduced are reduced in the
deck type bridges
SPACE DECKS
Of recent years a range on standard section mild steel tubes has
been manufactured in increasing quantity .
SCHWEDLER DOMES
A schwedler dome also consists of meridional ribs connected together
to a number of horizontal polygonal rings to stiffen the resulting
structure. So that it will be able to take unsymmetrical loads
Each trapezium formed by intersecting meriodional ribs with horizontal
rings is subdivided into two triangles by a diagonal member
Sometimes the trapezium may also be subdivided by two cross – diagonal
members
This type of dome was introduced by a German engineer J.W.Schwelder in
1863
The great popularity of schwedler domes is due to the fact that, on the
assumption of pin – connected joints, the structure can be analyzed as
statically determinate
In practice, in addition to axial forces, all the members are also under the
action of bending and torsional moments
Many attempts have been made in the past to simplify their analysis, but
precise applied to find the actual stress distribution
HIGH RISE STRUCTURES
Transmission Tower
Transmission towers are tall structures with relatively small cross
section and with a large ratio between the height and the maximum.
Towers are also called as masts or pylon.
On general the towers may be built up with three or more legs. But
generally all towers are built up with four legs and spared suitably. This
is because four leg gives sufficient stability to the structures.
Flexible type towers are not rigid in the longitudinal direction ie., in the
direction along the transmission cables
Line towers, when there is a straight portion of the power line, line
towers are preferred
Angle towers, when the direction of the power line is changed angle
towers are provided
The towers of such height provide 6 – 10m clearance from the ground
surface to the point of maximum sag of the cables
These towers are also known as single, double or multiple circuit towers
depending upon the no of circuits supported by the towers
Single diagonal bracing tower have long free length and double
diagonal bracing or cross diagonal tower
Radio and television towers are self – supporting towers. For there
towers rigid diaphragms are provided at the top and at several
intermediate sections to the increase the stiffness of cross sections.
In masts they are guyed with wire ropes at one or more levels
The vertical loads acting on towers are the dead load and live load
The vertical loads on the power transmission line towers include self
weight of towers insulators, fittings, ice coating, line man with tools
Until the 19th century, buildings of over six stories were rare. It was
impractical to have people walk up so many flights of stairs, and water
pressure could only provide running water to about 50 feet (15m)
The walls than hang off this frame like curtains hence the architectural
term curtain wall for tall systems of glass that are laterally supported by
these skeletal frames.
Skyscrapers was a nautical term for a tall mast or sail on a sailing ship
Worlds 10 Tallest Buildings
Rank Building, City Year Storyes Height in
Meters Feet
1 Freedom Towers, New York 2005 121 541 1776
2 Taipei 101, Taipei, Taiwan 2004 101 509 1671
3 Petronas twin tower, Kuala lumpur, 1998 88 452 1483
Malaysia
4 Sears tower, Chicago 1974 110 442 1451
5 Jin Mao Buildings, Shanghai 1999 88 421 1380
6 Two International Finance Centre, Hong 2003 88 415 1362
Kong
7 CITIC Plaza, Guangzhou, China 1996 80 391 1283
8 Shun Hing Square, Shenzhen, China 1996 69 384 1260
9 Empire State Building, New York 1931 102 381 1250
10 Central Plaza, Hong Kong 1992 78 374 1227
COOLING TOWER
Cooling towers are widely used for cooling large quantities of water in
thermal power station , refineries , atomic power plants , steel plants , air
conditioning and other industrial plant.
The cooled water is collected in a pond at the bottom of the towers and
then recirculated for industrial use
Hyperboloid of revolution
Planning principle
System principle
Gravity principle
MATERIAL MANAGEMENT
Material management is concerned with ensuring that the quantity
and quality required are on the job as per requirement
Bulk items
Standard items
Fabricated items
Bulk items - like earth , bricks , cement , sand , stone chips , steel sheet
and asphalt that are obtained in a semi-processed state
Standard items - all shelf items that can be procured from the market
like pipes and pipe fittings.
Fabricated items – are the items that are specially built as per
specification and sizes for the project. Built as per specification like roof
truss, doors, windows, electrical panel etc.
ERECTING LIGHT WEIGHT COMPONENTS ON TALL STRUCTURE
Tall buildings are generally multi storey structures where greater part
of construction of beams and stanchreons
Erection Procedure for Multi Storey Building
The order of erection follows pattern of columns, girder and beams or
columns, trusses and purlins. Buildings are generally erected by
cranes and beyond the reach are erected guy derricks
The step wise operation is as follows
Guy derrick mast is assembled on ground with its base in
approximate required location. The mast is tipped up vertically and
guys are anchored to column bases. The boom is inserted and topping
lift and load lines are served. The derrick is ready to operate. The first
– tier steel is erected
The bottom is removed from boom seat by picking with topping
lift falls, revolved 18degree and placed in a temporary jumping
shoe. The top of boom is guyed off with temporary guys
The load falls are attached to mast above its center of gravity, the
mast guys are moved to top of next tier and mast is raised to its
new position. The mast guys are adjusted and load falls unhooked
The temporary guys of boom are removed and the topping lift falls
are used to raise the boom and place it in the boom seat. The
derrick is now ready to operate and the next tier of steel is erected
All bolts and splice material on lattice derricks and crane sections
have been inserted
This foundation consists of two or more layers or tiers of steel beams, the
layers being provide one above the other at right angles at each other .
The column rests on a base plate through which the load is transmitted to
the upper tiers beams
These beams in turn transfer the loads to the lower tier beams. From the
lower tier beams the load will be transmitted to the soil.
ERECTION OF ARTICULATE STRUCTURE
Bow String Girder Type Bridges
The bow string girder type bridges derives its name from its shape. The
arch rib and the tie respectively resemble bow and string.
The flooring of bridge rests on ties and the load is transmitted to the arch
rib through suspenders
Suitable bracing may also be provided in case of steel bow string girders
The bow string girder type bridge removes the following two
disadvantages of the arch bridges
The bow string girder type bridges are therefore very much suitable for
multiple spans and at places where the available clearance is restricted
In the deck type truss bridges, the floor system rests on the top chord.
In the through type truss bridges, the floor system rests on the bottom
chord. Through type warren truss bridge with verticals
Although the parallel chord trusses are used for the through type truss
bridges, but the lines of various numbers of parallel chord truss bridges
are more in harmony with deck type truss bridges
Component Parts of Truss Bridge
The various component parts consists of
But the two bridges support the load of the roadway in very different ways.
The difference lies in how the cables are connected to the towers
In suspension bridges, the cables ride freely across the towers, transmitting
the load to the anchorages at either end
In cable-stayed bridges, the cables are attached to the towers, which alone
bear the load
In a parallel pattern, cables are attached at different heights along the tower,
running parallel to one other
Construction Sequence of Cable Stayed Bridge
The cable stayed bridges are similar to the suspension bridge except that
there are no suspenders in the cable stayed bridges and the cables are
directly stretched from towers to connect with the decking
Thus no special internal anchorage is required for the cables as in case of
suspension bridges because the anchorage at one end is done in the girder
and at the other on top of tower
Each because in the girder introduces horizontal and vertical forces
The cables can be arranged with two plane system or one plane system.
The two plane system requires additional width to accommodate the
towers and deck anchorages
But in case of one plane system the anchorage at deck level can be
accommodated in the traffic median and it results in the least value of
total width of the deck
In principle the cable stayed bridge essentially of the following three
elements
Bridge deck
Pylons or tower
Stay cables
The stay cables are the principal structural elements because they play an
important role in the design, stability and performance of the structure as
a whole
The cable stayed decks are less prone to the wind induced oscillations than
the suspension bridges because of the damping effect of the inclined cables
The brick deck may be in the form of steel prone or RCC or prestressed
concrete girders.
As their damping effect is very high, the vibration effects are also small
They possess much higher stiffness and hence, they exhibit comparatively
less deflection