Hazard and Operability Study
Hazard and Operability Study
Hazard and Operability Study
STUDY
Introduction
Tiga tujuan utama dari
SAFETY ENGINEERING
Identify hazards :
Eliminate hazards
Mitigate hazards
Safety & Layers of Protection
Safety Instrumented Function
M
Independent Protection Layers
Plant and/or
I Emergency Emergency response layer
T Response
I
G
A
Dike Passive protection layer
T
I
Relief valve,
O Rupture disk Active protection layer
N
Safety Emergency Shut
Instrumented
System Down action Isolated protection layer
Trip level alarm
P
R Operator Wild process
E Process control layer
Intervention parameter
V High level alarm
E High level
N Basic
T Process Process
Control value Process control layer
I
System
Normal behavior
O Low level
N Plant
Design
Metode analisa bahaya dan
keandalan proses untuk tujuan
‘safety’ :
Monomer
Feed Refer to reactor system shown.
REVERSE Reverse cooling Failure of water Less cooling, possible Install check valve
flow source resulting in runaway reaction
backward flow
MORE More cooling flow Control valve failure, Too much cooling, reactor Instruct operators
operator fails to take action cool on procedures
on alarm
AS WELL AS Reactor product More pressure in reactor Off-spec product Check maintenance
in coils procedures and
schedules
OTHER THAN Another material Water source May be cooling inefffective If less cooling, TAH will
besides cooling contaminated and effect on the reaction detect. If detected,
water isolate water source.
Back up water source?
Case Study – Shell & Tube Heat
Exchanger
• Using relevant guide works, perform HAZOP study on shell & tube heat
exchanger
Process
fluid
Cooling water
HAZOP on Heat Exchanger –
Guide Word
Answer 1
Deviation Causes Consequences Action
Less Less flow of cooling Pipe blockage Temperature of process fluid High Temperature Alarm
water remains constant
More More cooling flow Failure of cooling Temperature of process fluid Low Temperature Alarm
water valve decrease
More of More pressure on Failure of process fluid Bursting of tube Install high pressure
tube side valve alarm
Corrosion Corrosion of tube Hardness of cooling Less cooling and crack of Proper maintainence
water tube
HAZOP on Heat Exchanger –
Guide WordAnswer 2
Deviation Causes Consequences Action
Install Temperature indicator
NONE No cooling water flow Failure of inlet cooling Process fluid temperature is
water valve to open not lowered accordingly before and after the process
fluid line
Install TAH
MORE More cooling water Failure of inlet cooling Output of Process fluid Install Temperature indicator
flow water valve to close temperature too low before and after process fluid
line
Install TAL
LESS Less cooling water Pipe leakage Process fluid temperature too Installation of flow meter
low
REVERSE Reverse process fluid Failure of process fluid Product off set Install check valve (whether
flow inlet valve it is crucial have to check?)
CONTAMINATION Process fluid Contamination in cooling Outlet temperature too low Proper maintenance and
contamination water operator alert