Project Cost Management
Project Cost Management
Project Cost Management
Management
Objective's of Presentation
Through this interaction, participants will enhance their:
Level of Knowledge and skills of project cost
management
Appreciation of the planning, estimating, budgeting
and controlling of project costs
Understanding of the professional cost management
methodologies, tools and techniques of PMBOK
Project Cost Management
PCM definition
“Project Cost Management includes the
processes involved in planning, estimating,
budgeting, and controlling costs so that the
project can be completed within the
approved budget”
:
Project Cost Management
Key Words:
project cost management, resource, planning,
estimating, budget, control, forecasting
Cost Estimating
Developing an approximation of the costs of the resources needed
to complete project activities.
Cost budgeting
Aggregating the estimated costs of individual schedule activities or work
packages to establish a total cost baseline for measuring project performance
Cost Control
Influencing the factors that create changes to the cost baseline
What Do We Want to Know by
Managing Cost?
through answering three questions,
How did we perform ?
How much we differ from plan?
What is the implication for future!
Cost Management Key Terms
PV - Planned Value, estimated value of the planned work
EV – Earned Value, estimated value of work done
AC – Actual Cost, what you paid
BAC – Budget at Completion, the budget for the total job
EAC –Estimate at Completion, what is the total job expected to
cost?
ETC – Estimate to Complete, forecasted costs to complete job
VAC – Variance at Completion, how much over/under budget do
we expect to be?
Work Breakdown structure
Company owners and project managers use the Work Breakdown
Structure (WBS) to make complex projects more manageable. The
WBS is designed to help break down a project into manageable chunks
that can be effectively estimated and supervised.
Some widely used reasons for creating a WBS include:
PARAMETRIC COSTING
Parametric estimating is a technique that uses a statistical relationship between historical data
and other to calculate a cost estimate for a schedule activity resource. This technique can
produce higher levels of accuracy depending upon the sophistication, as well as the underlying
resource quantity and cost data built into the model
BOTTOM-UP COSTING
This technique involves estimating the cost of individual work packages or individual schedule
activities with the lowest level of detail. This detailed cost is then summarized or “rolled up” to
higher levels for reporting and tracking purposes. The cost and accuracy of bottom-up cost
estimating is typically motivated by the size and complexity of the individual schedule activity
or work package. Generally, activities with associated effort increase the accuracy of the
schedule activity cost estimate
Determine Resource Cost Rate
The person determining the rates or the group preparing the
estimates must know the unit cost rates, such as staff cost
per hour and bulk material cost per cubic yard, for each
resource to estimate schedule activity costs. Gathering
quotes is one method of obtaining rates. For products,
services, or results to be obtained under contract, standard
rates with escalation factors can be included in the contract.
Reserve Analysis
reserves are estimated costs to be used at the discretion of the
project manager to deal with anticipated, but not certain, events.
These events are “known unknowns” and are part of the project
scope and cost baselines
Essential definitions
Enterprise Environmental factors-refer to both internal and external factors that surround or
influence a project’s success. These factors may come from any or all of the enterprises
involved in the project. Enterprise environmental factors may enhance or constrain project
management options and may have a positive or negative influence on the outcome. They
are considered as inputs to most planning processes
Organisational process Assets- are any or all process related assets, from any or all of the
organizations involved in the project that can be used to influence the project’s success.”
Examples include: plans, procedures, lessons learned, historical information, schedules, risk data
and earned value data. Organizational Process Assets fall into two broad categories—Processes
and Procedures, and the Corporate Knowledge Base.
WBS Dictionary-The WBS dictionary includes entries for each WBS component that
briefly defines the scope or statement of the work, defines deliverables, contains a list of
associated activities, and provides a list of recognized milestones to gage progress
Approved change requests-refers to a change request that has been submitted by the requestors, has
been reviewed by the appropriate parties through use of the integrated change control process, and has
been granted authorization to be take place
Essential definitions
Risk Register-The risk register or risk log becomes essential as it records
identified risks, their severity, and the actions steps to be taken. It can be a
simple document, spreadsheet, or a database system, but the most effective
format is a table. A table presents a great deal of information in just a few
pages
Cost Baseline-ultimately, project management includes a variety of
responsibilities within one’s team in order to achieve maximum results for their
employer. In regards to money and remaining in business, providing a budget
that is adjusted to time is considered a cost baseline.
Performance reports- is filled out by the project manager and submitted on a
regular basis to the sponsor, project portfolio management group, Project
Management Office or other project oversight person or group.
Earned Value Analysis-report shows specific mathematical metrics that are
designed to reflect the health of the project by integrating scope, schedule,
and cost information. Information can be reported for the current reporting
period and on a cumulative basis.
Essential Definitions
Resource Calendar-Keeping track of schedules and time
management is one of the most fundamentally important tasks that
are the responsibility of the project management team and or the
project management team leader. One of the best ways to
accomplish this feat is through the careful and well orchestrated
use of calendars to keep track of the multitude of project related
events, occurrences, and dates that will take place during the
project’s life cycle.
Enterprise environmental factors
– Market condition
– Published commercial information
Cost performance baseline
– Authorized time‐phased Budget at Completion
(BAC) used to measure, monitor and control
overall cost performance (S shape curve)
Cost Budgeting
• Budgeting is allocating costs to work packages
to establish a cost baseline to measure project
performance
• Remember Contingency items are for unplanned
but required changes it is not to cover things
such as:
Price escalation
Scope & Quality Changes
Funding Limit Reconciliation – Smoothing out
the project spend to meet management
expectations
Cost Aggregation
Schedule activity cost estimates are aggregated by work packages in accordance with the
WBS. The work package cost estimates are then aggregated for the higher component
levels of the WBS, such as control accounts, and ultimately for the entire project. Reserve
analysis establishes contingency reserves, such as the management contingency reserve,
that are allowances for unplanned, but potentially required, changes. Such changes may
result from risks identified in the risk register
Reserve Analysis
Management contingency reserves are budgets reserved for unplanned, but potentially
required, changes to project scope and cost. These are “unknown unknowns,” and the
project manager must obtain approval before obligating or spending this reserve.
Management contingency reserves are not a part of the project cost baseline, but are
included in the budget for the project. They are not distributed as budget and, therefore, are
not a part of the earned value calculations
Parametric estimating
The). parametric estimating technique involves using project characteristics (parameters) in
a mathematical model to predict total project costs. Models can be simple (e.g., one model
of software development costs uses thirteen separate adjustment factors, each of which
has five to seven points within it).
COST TYPES
Sunk Costs: A historical or expended cost. Since the cost has been expended,
we no longer have control over the cost. Sunk costs are not included when
considering alternative courses of action.
Costs: Nonrecurring costs that do not change based on the number of units,
like expenses related to equipment required to complete a project.
Variable Costs: Costs that rise directly with the size of the project, like
expenses related to consumable materials used to accomplish the project.
Indirect Costs: Costs that are part of the overall organization’s cost of doing
business and are shared among all the current projects. These include salaries of
corporate executives, administrative expenses, any cost that would be considered
part of overhead.
Opportunity Costs: The cost of choosing one alternative and, therefore, giving
up the potential benefits of another alternative.
Direct Costs: Costs incurred directly by a specific project. These include cost
for materials associated with the project, salary of the project staff, expenses
associated with subcontractors.
Cost Types
Direct Costs
Related “Directly” to the project
ex. Labor hours, material, equipment, food, travel. .
.
Indirect Costs
Overhead used for more than one project
ex. Building rent, taxes, janitorial services
Cost Types
A cost by any other name, really isn’t the
same!
Variable Cost – Changes with volume
Fixed Cost – Stays the same, regardless of volume
TC = VC+FC
COST vs VOLUME
Cost Types
Project Costs
Are incurred while the project is being fulfilled.
Working Capital
- Current Assets (Cash, Inventories, Accounts
Receivable)
- Liabilities (Notes, AP, Accruals)
Cost and Project Selection
Present Value
Is $10,000 in your pocket now worth more than the $10,000 in
your pocket one year from now?
Yes! You can use the money now to make more money. The
10,000 in a year from now should be “discounted” to the present,
since it’s not worth as much.
Present Value of Your PMP
Consulting Gig
1 10,000 10,000
2 10,000 9,090
3 10,000 8,264
4 10,000 7,513
5 10,000 6,830
Expressed as percentage
PV of Revenue – PV of Costs
Net Present Value: Your PMP Gig
Value (VAC)
Graph Target
Cost &
Schedule
Planned
Schedule
Value (PV) Variance
(Time)
Earned
Value (EV)
Earned Value Formulas
NAME FORMULA NOTES
Cost Variance (CV) EV-AC Negative = Over budget
Positive = Under budget
1–a 6–e
– 2–b 7-d
– 3–a 8-a
– 4–c 9-b
10 - a
– 5–a
EVA Question
Given a lawn to be cleaned up within four days at an estimated budget
Of Rm2,000, and today after three days the status of the project being;
EV=Rm1250, AC-Rm1750 with a daily planned expenditure=Rm500,
calculate the following:
PV EV CV
BAC CV CPI
SV SPI VAC(BAC-
EAC)
EAC(EAC/CPI) ETC(EAC-AC)
Answers to Questions (Cont’d)
What is: Calculation: Answer: Interpretation of Answer:
PV $500+$500+$500 $1,500 We should have completed $1500
We actually completed $1,250
EV $500+$500+$250 $1,250
worth of work
AC $500+$1000+$250 $1,750 We have actually spent $1,750
BAC $500+$500+$500+$500 $2,000 Our project budget is $2000
CV $1,250 - $1,750 -$500 We are over budget by $500
We are only getting $0.71 out of
CPI $1,250/$1,750 0.714 every dollar that we are spending
on the project
SV $1,250 - $1,500 -$250 We are behind schedule
We are progressing at 83% of the
SPI $1,250/$1,500 0.833
planned rate
We currently estimate the project
EAC $2,000/0.714 $2,801
will cost $2,801
We need to spend $1,051 to finish
ETC $2,801-$1,750 $1,051
the project
We currently expect to be $801
VAC $2,000 - $2,801 -$801 over budget when the project is
completed
Big Dig
Started construction on 1991 and planned
completion by 1997 (6 years), it was to cost $3
Billion, the project included 6 highways
($0.5 Billion per highway/year)
At the end of the first year, 1/2 highway was
completed and the cost was $2 Billion.
Do the EV analysis
Big Dig: The Numbers