LNG Process Safety - Final04122018

You are on page 1of 50

Process Safety

At the Alaska LNG Liquefaction Facility and Marine Terminal


April 12, 2018

Leslie “Fritz” Krusen

AKLNG-4030-PPP-PRS-DOC-00001
Agenda

• LNG Site Overview


• Hazard Analysis Report
• Flares
• Noise
• Seismic Design
• Emergency Response Plan

2
Agenda

• LNG Site Overview


• Hazard Analysis Report
• Flares
• Noise
• Seismic Design
• Emergency Response Plan

3
LNG Site Overview

• Summary
– Highly modularized
– 3 train liquefaction plant - 6.7 MTPA each
– About 900 acres of land required
• Design Basis
– Air Products C3MRTM process; two refrigeration cycles
• C3 = Propane
• MR = Mixed Refrigerant (mix of propane, ethane, & nitrogen)
– Power plant (combined cycle), with distribution system optimized to
reduce capex; Black-Start tie in to local utility
– 2 x 240,000 m3 LNG storage tanks
– Marine jetty with 2 loading berths, LNG loading rate 12,500 m3/hr
• Execution Basis
– Material Offloading Facility (MOF) to support the unloading of bulk
materials, modules, and construction equipment; Temporary facility

4
LNG Site Overview

5
Agenda

• LNG Site Overview


• Hazard Analysis Report
• Flares
• Noise
• Seismic Design
• Emergency Response Plan

6
Hazard Analysis Report - Overview

• Required by FERC and DOT PHMSA to evaluate hazards associated with:


– Flammable Gas Dispersion (vapor dispersion exclusion zone)
– Pool Fires (thermal radiation exclusion zone)
– Jet Fires (hazard zone)
– Refrigerant vapor dispersion (hazard zone)
– Overpressure from ignition of flammable refrigerants (hazard zone)
– Toxic vapor dispersion (hazard zone)
• All piping has a “hole size” associated with it based on DOT PHMSA FAQ
website
• Piping table has been created to list every piece of pipe in the facility
along with its “hole size” – over 140 release scenarios have been
evaluated
• Modeling is performed on the “bounding scenarios” to ensure hazards do
not impact the public – 18 bounding scenarios have been selected.

7
Hazard Analysis Report – Gas Release

• Flammable Gas
Dispersion for
LNG (1/2 LFL)
Purple = release
from loading line at
jetty
Blue = release from
loading line on
shore
Green = release
from LNG rundown
lines

8
Hazard Analysis Report – Pool Fire

• Pool Fires for


Process Areas
Yellow = low flux
(1,600 Btu/ft2-hr)
Orange = medium
flux (3,000
Btu/ft2-hr)
Red = high flux
(10,00 Btu/ft2-hr)

9
Hazard Analysis Report – Pool Fire

• Pool Fires for


LNG Tanks
Yellow = low flux
(1,600 Btu/ft2-hr)
Orange = medium
flux (3,000
Btu/ft2-hr)
Red = high flux
(10,00 Btu/ft2-hr)

10
Hazard Analysis Report – Jet Fire

• Jet Fires for LNG,


low flux (1,600
Btu/ft2-hr)
Purple = release
from unloading line
at jetty
Blue = release from
unloading line on
shore
Green = release
from LNG rundown
lines

11
Hazard Analysis Report – Jet Fire

• Jet Fires for


Mixed
Refrigerant, low
flux (1,600
Btu/ft2-hr)
Purple = MCHE
release
Green = HP MR
Compressor
outlet release

12
Hazard Analysis Report – Jet Fire

• Jet Fires for


Propane
Refrigerant, low
flux (1,600 Btu/ft2-
hr)
Green = Propane
Storage Bullet
Blue = Propane
subcooler outlet
Purple = connection
on propane cooler
Orange = release
from reflux drum

13
Hazard Analysis Report – Gas Release

• Refrigerant
vapor dispersion
for mixed
refrigerant (1/2
LFL)
Purple = MCHE
release
Green = HP MR
Compressor
outlet release

14
Hazard Analysis Report – Gas Release

• Refrigerant vapor
dispersion for
propane refrigerant
(1/2 LFL)
Green = Propane
Storage Bullet
Blue = Propane
subcooler outlet
Purple = connection
on propane cooler
Orange = release
from reflux drum

15
Hazard Analysis Report - Overpressure

• Overpressure
from mixed
refrigerant
ignition (1 psi)
Purple = MCHE
release
Green = HP MR
Compressor
outlet release

16
Hazard Analysis Report - Overpressure

• Overpressure from
propane refrigerant
ignition (1 psi)
Green = Propane
Storage Bullet
Blue = Propane
subcooler outlet
Purple = connection
on propane cooler
Orange = release
from reflux drum

17
Hazard Analysis Report - Toxics

• AEGL = Acute Exposure Guideline Level, 3 levels


– AEGL 3: Lethal (Life threatening health effects or death)
– AEGL 2: Disabling (Irreversible health effects, impairs escape)
– AEGL 1: Non-Disabling (Notable discomfort, reversible)
• Exposure Durations from 10 minutes to 8 hours
• PHMSA analysis: AEGL Levels 1, 2, & 3 @1 hour
• Different hazard from asphyxiant, flammable, or
explosive
• Website reference: WWW.EPA.GOV/AEGL
18
Hazard Analysis Report - Toxics

AEGL Info from EPA; exposure = 1 hour, concentration in parts per million

COMPOUND AEGL1 AEGL2 AEGL3


Aromatics (Benzene) 52 800 4,000
C6+ (Hexane) Not Recorded 2,900 8,600
C5’s (Pentane) No Information N.I. N.I
C4 (Butanes) 5,500 17,000(1) 33,000(1)
C3 (Propane) 5,500 17,000(1) 33,000(1)
C2 (Ethane)(2) Not Listed N.L. N.L.
C1 (Methane)(2) Not Listed N.L. N.L.

Notes:
(1) Flammability hazard is at a lower concentration
(2) Alaska LNG gas at plant entrance is about 97% methane and ethane

19
Hazard Analysis Report - Toxics

• Toxic vapor
dispersion from
heavy
hydrocarbons
(1/2 AEGL)
• (solid line –
AEGL-2)
• (dotted line –
AEGL-3)

20
Hazard Analysis Report - Toxics

AEGL Info from EPA; exposure = 1 hour, concentration in parts per million

COMPOUND AEGL-1 AEGL-2 AEGL-3


Aromatics (Benzene) 52 800 4,000
C6+ (Hexane) Not Recorded 2,900 8,600
C5’s (Pentane) No Information N.I. N.I
C4 (Butanes) 5,500 17,000 33,000
C3 (Propane) 5,500 17,000 33,000
C2 (Ethane) Not Listed N.L. N.L.
C1 (Methane) Not Listed N.L. N.L.
Methyl Mercaptan* Not Recorded 23 68
Chlorine* .050 2 28

*Note: Methyl mercaptan and chlorine are not present at the LNG facility and are listed for
reference only.

21
Hazard Analysis Report - Summary
• All exclusion zones (thermal radiation and vapor
dispersion) meet DOT PHMSA requirements and do not
impact the public
• All hazard zones (jet fires, refrigerant vapor dispersion,
refrigerant overpressure, and toxicity) meet DOT
PHMSA requirements and do not impact the public
• Alaska LNG Hazard Analysis Report is publically-
available; see AGDC’s Alaska LNG website
WWW.Alaska-LNG.com, then
– Upper Tab Regulatory Process – FERC Application Exhibits
(Resource Reports)
– Resource Report 13 (LNG Plant), Appendix Part 1, page 279

22
Agenda

• LNG Site Overview


• Hazard Analysis Report
• Flares
• Noise
• Seismic Design
• Emergency Response Plan

23
Flares

• There are two flares at Alaska LNG


– High-Pressure Ground Flare
– Low-Pressure Elevated Flare
• High-Pressure Ground Flare
– Located at south end of plant
– Handles inlet gas (“wet”), LNG process (“dry”), and refrigerant compressor
overpressure situations
– Three 50% units, each 260 ft X 350 ft
– Each enclosed by 50 ft tall radiation fence, no “sterile zone” required (to
get to 500 BTU/ft2-hr radius)
– Flare area surrounded by 500 ft “no hydrocarbon-handling equipment”
radius (equipment-spacing insurance guideline)
• 500 BTU/ft2-hr: Allows continuous exposure with appropriate clothing

24
Flares

• Low-Pressure Elevated Flare


– Located near bluff at middle of plant
– Handles LNG Carrier (ship) and LNG tank
overpressure situations, plus ship cool-down
– One 24” tower, currently 200 ft tall
– Tower surrounded by fence with 120 ft radius for
“sterile zone” (to get to 500 BTU/ft2-hr)
– Ship cool-down could occur 4-5 times per year and
could last about 17 hours (depends on ship size)

25
LNG Site - Flares

26
Agenda

• LNG Site Overview


• Hazard Analysis Report
• Flares
• Noise
• Seismic Design
• Emergency Response Plan

27
Noise - Introduction
• Two Operations-phase noise criteria for the Alaska LNG Plant
– 85 dBA: Within-plant, at 3 ft from noise-generating equipment
– 55 dBA, Off-site at “Noise Sensitive Areas” (NSA’s) as per FERC 18 CFR
157.206
• Operations phase analysis does not include upsets such as flares
• Four NSA’s identified and measured on 10-11 March, 2015 for
pre-construction background, 2015; see map
– LT-1: 10,500 ft NW of center Train 2, about 6160 ft from plant fence
– LT-2: 3,700 ft E of center of Train 2, about 300 ft from plant fence
– LT-3: 6,600 ft S of center of Train 2, about 300 ft from plant fence
– ST-4: 5,700 ft SE of center of Train 2, about 300 ft from plant fence
• LT station measurements were made for about 48 hours, ST
measurements for about 40 minutes

28
Noise – Pre-Construction Background

29
Noise - Operational
• Numerous design optimizations were made to reduce
operational noise:
– Low-noise blades on the airfin coolers
– Low-noise inlet air ducts and exhaust stacks on the gas turbines
– Noise-abatement insulation on compressor discharge piping
– Enclosures and buildings around noise-generating equipment
– Etc
• The four NSA’s currently look to be under the 55 dBA
Operational noise limit during steady-state operations,
see map

30
Noise - Operational

31
Noise - Construction
• Construction phase uses Federal Highway
Administration (FHWA) protocols to address
intermittent nature of activities such; average noise
may exceed 55 dBA at NSA’s (see map)
• Pile-Driving is likely the loudest construction activity
– Probably will be limited to 12 hours per day
– Plant permits will included piled foundations
– But good Nikiski soils may allow some spread-footing
foundations instead of piles
• Pile-Driving will occur for the offshore structures
• Kenai Spur Highway Re-Route is not currently
included in the LNG Plant construction (or
operational) noise assessment
32
Noise - Construction

33
Noise - Comparisons

• 90 dBA: Power mower at 25 ft

• 80 dBA: Garbage disposal

• 70 dBA: Vacuum cleaner

• 60 dBA: Conversation at restaurant

• 50 dBA: Conversation at home

34
Noise - Conclusion

• With design mitigations, the Alaska LNG Plant will meet


the steady-state Operational offsite criteria of 55 dBA
• Construction could be noisier than 55dBA at offsite
receptors, but impact will be intermittent
• Alaska LNG Liquefaction Facility Environmental Sound
Level Assessment Report is publically-available; see
AGDC’s Alaska LNG website WWW.Alaska-LNG.com, then
– Upper Tab Regulatory Process – FERC Application Exhibits
(Resource Reports)
– Resource Report 9, Appendix P

35
Agenda

• LNG Site Overview


• Hazard Analysis Report
• Flares
• Noise
• Seismic Design
• Emergency Response Plan

36
Seismic Design Considerations I
• Nikiski is known to be a high-seismic area
– 1964 Great Alaska Earthquake (magnitude 9.2)
– Recent (Jan, 2016) magnitude 7.1 earthquake felt on Kenai
Peninsula
• Several design code give guidance to ensure robustness
– Overall: DOT Title 49 CFR 193, FERC Draft 2007 Seismic
Design Guidelines
– LNG-Containing/Controlling Equipment: NFPA-59A
– Buildings and Structures: ASCE 7-05 and 7-10
– Marine Facilities:
• USCG Title 33 CFR 127.103
• California MOTEMS (Marine Oil Terminal Engineering & Maintenance
Standard)

37
Seismic Design Considerations II
• Facilities must be designed for:
– Operating Basis Earthquake (OBE): Equipment remains
functional
– Safe Shutdown Earthquake (SSE): Equipment may be
damaged and require repair, but containment is maintained
• Seismic design details are confidential, but Alaska LNG
(LNG plant) Facilities Seismic Engineering Report is
publically-available; see AGDC’s Alaska LNG website
WWW.Alaska-LNG.com, then
– Upper Tab Regulatory Process – FERC Application Exhibits
(Resource Reports)
– Resource Report 13 (LNG Plant), Appendix Part 4

38
Agenda

• LNG Site Overview


• Hazard Analysis Report
• Flares
• Noise
• Seismic Design
• Emergency Response Plan

39
Emergency Response Plan - Overview
• A combined Emergency Response Plan (ERP) will be developed to incorporate not just the
Liquefaction Facility, but also the GTP and Pipeline that are part of the overall Alaska LNG Project
• Within this combined plan will be individual ERPs that will meet all regulatory requirements and
address the site-specific nature of the covered facilities.
– Individual ERPs will be site-specific and identify the types of emergencies that will require
notification to appropriate agencies.
– The individual ERPs will contain the response organization and resources (e.g., diagrams,
maps, plans, and procedures) necessary to respond adequately.
• The combined ERP will be developed using the nationally recognized Federal Emergency
Management Agency (FEMA) guidelines and use the National Incident Management System
(NIMS) as the methodology with the Incident Command System (ICS) organizational structure.
– The ICS is the common emergency response tool used by industry and local emergency
response agencies.
– The Project’s ICS will link to plans maintained by other affected response agencies or third
parties and thus help to ensure appropriate communications, understanding, and
cooperation are in place.
• The combined and individual plans will be prepared in consultation with stakeholders to ensure
that all actions to emergencies are coordinated and understood by emergency responders, local
community leaders, the government, and the general public.

40
Emergency Response Plan – Possible TOC
• Background on LNG
• Facility, Process Descriptions, and Safety System Descriptions
• Incident Command System: Description, Organization Chart, Roles, and
Responsibilities; Onsite Emergency Response Personnel
• Emergency Response Contacts/Proximity and Mutual Aid Arrangements
• Description of Onsite Emergency Response Equipment
• Definition of Emergency Events
• Response Plans for the Emergency Events
• Emergency Access & Egress Routes within/adjacent to Facilities, including LNG
Vessels
• Onsite and Public Emergency Notification Plan
• Emergency/Security Drill Plan
• Incident Reporting Requirements
• Post-Incident Investigations

41
Other Emergency Response Documents
• LNG Transfer Manual (USCG)
• Spill Prevention Control & Countermeasure (SPCC) Plan
• Material Safety Data Sheets (MSDS’s)
– Methane
– Ethane
– Propane
– N-Butane
– Nitrogen
– Diesel
• Alaska LNG Hazard Analysis Report is publically-available; see
AGDC’s Alaska LNG website WWW.Alaska-LNG.com, then
– Upper Tab Regulatory Process – FERC Application Exhibits (Resource
Reports)
– Resource Report 13 (LNG Plant), Appendix Part 1, page 206
42
Pipeline

• 800-mile, 42” buried pipe


• ~55 miles within KPB
• 49 CFR Part 192
• Construction Right-of-Way
• Nominal 120’

43
Route Map

44
Buried Pipe

45
Pipeline Construction

46
Road Crossing

47
Integrity Management during Operations

Integrates:
(Required by 49 CFR 192.605 Procedural Manual for Operations, Maintenance • Technology
and Emergencies) • Operating Procedures
• Management protocols
Key items addressed:
• Worker qualification
• Periodic contact with stakeholders
• Public Education & Awareness
• Right-of-Way Patrols
• Pipeline markers
• Participation in Alaska’s “One-Call” system (811 Dispatch)
• Cathodic Protection inspection and monitoring
• Pipeline In-Line-Inspection (ILI) - “smart pigs”
• Training Programs
• Procedures for ensuring public safety during planned maintenance and
corrective action procedures

48
AGDC Committed to Maximize Local Hire

The project is expected to generate thousands of jobs, including


constructions support facilities:

• Project offices, personnel housing and support, and logistics


support sites
• Construction work pads (gravel/ice or snow/grade)
• Laydown yards and storage facilities
• Port facilities
• Access roads
• Airports and airstrips

49
AGDC.us

You might also like