Hoover Dam: by Project Monsters
Hoover Dam: by Project Monsters
Hoover Dam: by Project Monsters
By Project Monsters
Presenters: Nazimah Abdul Rahim
Hakki Isik
HOOVER DAM
• Concrete dam in Black
Canyon, on the border
between Arizona and Nevada
• Named after Herbert Hoover,
who played an important role
in its construction
• Built by Six-Companies, Inc.
• Operated by Bureau of
Reclamation of the US Dept.
of the Interior
• Lake Mead is the reservoir
constructed behind the dam
The Need for a Dam
• Turbulent Colorado River periodically flood
vast areas of California and Arizona
• The flood destroyed canals built for irrigation
and drinkable water
• Herbert Hoover proposed construction of the
high dam to solve the problems
Who is Herbert Hoover?
• Was Secretary of
Commerce under
President Coolidge
• Graduated from
Stanford University
• A successful mining
engineer, humanitarian
• Elected as the 31st
President of the United
States
Questions That Were Raised
What would be the location of the dam?
Who would build the dam?
How would the dam going to be
financed?
Which states would get the water and
electricity?
Scope
• Construction of the high dam would
control the periodic floods, store water
for irrigation, municipal and industrial
use
• The customers would be the people
getting water, electricity from the dam
Resources
• 5200 workers on the construction with 3
shifts/day
• 5 millions barrel of cement used in the
concrete
• 9,000 tons of structured steel components
• 44,000 tons of large steel pipe and fittings
• Giant cooling towers
Time Management
• Hoover met with the 7 state governors
(AZ,CA,CO,NV,NM,UT,WO) to work out
suitable arrangement for their states’ use
• November 1922, Colorado River Compact was
signed
• In 1928, the Congress passed the Boulder
Canyon Act, allocating $175 million for the
dam construction
Time Management
• Composite bid was accepted for $50 mil by
Six Companies in March 6 1931
• Construction began in April 20 1931
• June 1931, sufficient housing facilities were in
place
• Construction was completed in March 1, 1936
• The construction was completed 2 years ahead
of schedule
Cost Management
• The most difficult part of the project –
period of Great Depression
• It cost a total of $165 million - $49
million to build the Hoover Dam
• Unskilled labor paid $4/day and
minimum wage cost was <$6/hr
• Paid back over a period of 50 years to
Federal Treasury by selling electricity
Project Management
• One of the biggest engineering project at that
time - also the greatest testimony to functional
organizations and old fashioned management
control techniques
• Active management was left in 4 hands: Henry
J. Kaiser, Charles A. Shea, Felix Kahn and
S.D. Bechtel
Project Management
Project Management
• Frank Crowe (a.k.a Hurry Up) worked under
Shea – acted as the man point between Board
of Directors and the operations personnel
• It was Shea’s responsibility to carry out the
construction on time and budget
• Each department was headed by a manager
and held accountable for their work
Project Management
• Dam construction was divided into 3
areas:
* Diversion tunnels and penstocks
* Concrete arched structure
* Power plant
Problems
• Workers’ strike (August 1931) – triggered by
deaths of many of the workers’ wives and
children due to extreme heat and lack of
sanitation in the campsite area
• Huge dam size required a lot of cement and
engineers predicted it would take 125 years to
dry and cure
• Heat generated in the chemical rxns in the
drying process would physically alter the
landscape
Solutions to the Problem
• Housing facilities were built, known as
Boulder City
• Giant cooling tower/plant built to cool the
entire dam – pumped ice water (37oF) at 1000
gal/min as the concrete was poured
• With this approach, the dam was cooled in 20
months
FAQs
• Height : 726.4 ft
• Weight: 6.6 million tons
• Total storage capacity : 30.5 million acre ft
• Power generating capacity: 2.8 million kW
• Has 17 generators
• Part of a system that provides water to
over 25 million people in Southwest United
States