Ppp/Pfi Terminology Unravelled: Richard Dyton (Simmons & Simmons) and Nick Hopkins (KPMG) 16 January 2007
Ppp/Pfi Terminology Unravelled: Richard Dyton (Simmons & Simmons) and Nick Hopkins (KPMG) 16 January 2007
Ppp/Pfi Terminology Unravelled: Richard Dyton (Simmons & Simmons) and Nick Hopkins (KPMG) 16 January 2007
Part 3: Conclusion
2/RRD/247DB70
Part 1: Some Background
What is PFI?
Terminology Quiz - 1
3/RRD/247DB70
What is the difference between PPP and PFI?
Is it:
A) Not a lot?
4/RRD/247DB70
The PPP Range
PPP
5/RRD/247DB70
Headlines Quiz
6/RRD/247DB70
Terminology Quiz - 1
What does “PIN” mean and how does it fit into the PFI process?
7/RRD/247DB70
Terminology Quiz - 1
8/RRD/247DB70
Terminology Quiz - 1
A) Integrated Testing Network - prototype scheme used to roll out and test
the features of a PFI scheme
9/RRD/247DB70
Part 2: The Legal Framework
Principal documents
Treasury Guidance
10/RRD/247DB70
Basic Contractual Structure
11/RRD/247DB70
(Basic Contractual Structure)
Shareholders/Sponsors
Lenders
(Shareholders Agreement) Insurers
(Inter-Creditor Agreement)
Loan Agreement
Equity Insurance
Direct Agreement policies/agreements
Direct Agreement
AUTHORITY
Contractor Construction
Construction Contractors
(SPV) Agreement
Concession Agreement
(may include Land transfer
agreement or lease)
Operating Suppliers/
Agreement Subcontractors
Possibly collateral warranties
12/RRD/247DB70
Terminology Quiz - 2
13/RRD/247DB70
Terminology Quiz - 2
A) The point at which all the contracts are signed by all parties
involved in the project
C) The point at which the final payment is made by the public sector
to allow operation of the project to commence
D) The point at which the final payment is made by the public sector
upon termination of the project
14/RRD/247DB70
Principal Documents
Concession Agreement
Subcontracts
Direct Agreement
Loan Agreement
Insurance
Shareholders Agreement
15/RRD/247DB70
Principal Documents
Concession Agreement
Service requirement
Payment mechanism
Performance regime
Change mechanisms
Termination
16/RRD/247DB70
Principal Documents
Risk allocation
– authority risks
– contractor risks
– operating risks
17/RRD/247DB70
(Principal Documents)
Subcontracts
Construction Contractor
18/RRD/247DB70
(Principal Documents)
Direct Agreement
19/RRD/247DB70
(Principal Documents)
Loan Agreement
20/RRD/247DB70
Treasury Guidance
Assumes:
– Contractor is an SPV
– there is a construction phase and an operational phase
– there is limited recourse debt
21/RRD/247DB70
(Treasury Guidance)
22/RRD/247DB70
Part 3: Conclusion
23/RRD/247DB70
Future of PFI
So far the National Audit Office has concluded that PFI deals have
saved public money, but early schools deals proved to be more
expensive than conventional procurement
24/RRD/247DB70
PPP/PFI terminology
unravelled
[or An idiot's guide to the curious
world of Public Private
Partnerships]
25/RRD/247DB70