Critical Path Method (CPM) : Presented by

CRITICAL PATH METHOD is needed to know whether a project can be late or be faster than what's witten in contract

Uploaded by

Nova Chua
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views

Critical Path Method (CPM) : Presented by

CRITICAL PATH METHOD is needed to know whether a project can be late or be faster than what's witten in contract

Uploaded by

Nova Chua
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 8

CRITICAL PATH METHOD (CPM)

Presented By:
1. Rizki Maulida (15 0404 052)
2. Nova Sonia (16 0404 046)
3. Chikita Rizka Rani (16 0404 047)
4. Pangeran Siregar (16 0404 056)
5. Aziz Saputra (16 0404 067)
6. Richard Jordan (16 0404 079)
DURASI
No. Node AKTIVITAS KODE AKTIVITAS PENDAHULU
(MINGGU)

0,1 PEK.PERSIAPAN A - 1
1,2 PEK.PONDASI1 B A 2
2,3 PEK.BETON BERTULANG C B 7
2,4 PEK.TANGGA D B 3
2,5 PEK.DINDING
2 E B 5
5,7 PEK.JENDELA & PINTU F E 3
8,9 PEK.LANTAI G I 3
7,9 PEK.LISTRIK H F 2
4,8
3
PEK.SANITASI I D 1
3,6 PEK.ATAP J C 2
6,8 PEK.PLAFOND K J 1
9,10 4
PEK.PENGECATAN L G;H 2
FP FORWARD PASS/HITUNGAN MAJU
HITUNGAN MAJU

3 J 6
10 12 K
2
C 7 1

0 A 1 B 2 4 I 8 G 9 L 10
D
0 1 3 3 6 1 13 3 16 2 18 18
1 2
E H
5 F 7 2
5
8 3 11
01
BP BACKWARD PASS/ HITUNGAN MUNDUR

0
HITUNGAN MUNDUR

3 J 6
10 12 K
2
C 7 1

0 A 1 B 2 D 4 I 8 G 9 L 10

0 1 3 3 12 1 13 3 16 2 18 18
1 2
E H
5 F 7
5 2
11 3 14
FINAL CPM

3 J 6
10 10 12 12 K
2
C 7 1

0 A 1 B 2 D 4 I 8 G 9 L 10

0 0 1 1 3 3 3 6 12 1 13 13 3 16 16 2 18 18
1 2
E H
5 F 7
5 2
8 11 3 11 14