DESIGN-BUILD SERVICES
INTRODUCTION
 Intricate balance between time, quality, and cost.
 Devised several methods of project delivery
 Design-Build Service
 Design-Build by Administration
 Design-Build on a Guaranteed Maximum Cost
 Legal Responsibility
 The single-point-responsibility of project delivery puts the legal
liability for both the design and the construction on the
Architect alone.
DESIGN-BUILD SERVICE
• Design-Build by Administration
• Design-Build on a Guaranteed Maximum Cost
DESIGN-BUILD SERVICE BY
ADMINISTRATION
DESIGN-BUILD SERVICE BY
ADMINISTRATION
 When the Project is constructed under the direct and
sole responsibility of the Architect, he performs the
following services:
 Prepares schedule of work, construction program, estimate and
bill of materials, labor, plans, equipment and services.
 Hires construction personnel and designates duties and
remunerations thereof;
 Negotiates and enters into contract with piecework
contractors and evaluates work accomplished thereunder;
 Procures materials, plans and equipment, licenses and permits;
 Authorizes payments of accounts;
DESIGN-BUILD SERVICE BY
ADMINISTRATION
 When the Project is constructed under the direct and
sole responsibility of the Architect, he performs the
following services:
 Keeps records and books of accounts;
 Negotiates with government agencies having jurisdiction over
the project; and
 Manages all other businesses of the construction;
DESIGN-BUILD SERVICE BY
ADMINISTRATION
 The fee of the Architect for the Design-Build Service by
Administration is Seven Percent (7%) of the Project
Construction Cost in addition to the Architect’s Fee for
the Regular Design Services.
DESIGN-BUILD SERVICE BY
ADMINISTRATION
 The above services are performed with the following
conditions:
 All costs of labor and materials are paid directly by the Client. The
Architect does not advance any money for payment of expenditures
connected with the work.
 Although the Architect may prepare a detailed cost estimate of the
Project, the estimate may be guaranteed only on a range of Ten
Percent (10%) plus or minus the stated estimate.
 The Architect appoints, subject to the Client’s approval a construction
superintendent, a purchasing agent, a timekeeper or keepers, and a
property clerk aside from the usual labor personnel required. Salaries
of such persons are paid by the Client and is not deductible from the
Architect’s fee.
 Cost of all permits and licenses incidential to the work are paid by the
Client.
DESIGN-BUILD SERVICE ON A
GUARANTEED MAXIMUM COST
DESIGN-BUILD SERVICE ON A
GUARANTEED MAXIMUM COST
 Basically the services rendered by the Architect is the
same as that of the Design-Build by Administration.
 This method essentially consist of the Client being given a
guaranteed maximum cost for the construction of the
project.
 The manner of payment is by lump sum amount
scheduled to follow the progress of the Project. The
Architect does not advance any amount to buy materials
or pay labor. Instead, a “revolving capital” is given at the
start of the construction.
DESIGN-BUILD SERVICE ON A
GUARANTEED MAXIMUM COST
 If there is a savings on the cost of the Project, it is divided
equally between the Client and the Architect.
 If the guaranteed maximum cost is exceeded by not more
Ten Percent (10%), it is divided equally between the
Client and the Architect. However, if the excess is more
than Ten Percent (10%) , the Architect pays for all the
extra costs in excess of the Ten Percent (10%).
 The fee of the Architect for the Design Build Service on a
Guaranteed Maximum Cost is either Ten Percent (10%) of
the Project Construction Cost or is already built-in in the
Guaranteed Maximum Cost. Said fee is aside from the fee
of the Architect for Regular Design Services.