Method of Statement Bore Pile Foundation
Method of Statement Bore Pile Foundation
By : RENDI SEPTRIAWAN
Method of Statement of Bore Pile
Foundation
1. Dry Method
2. Wet Method
3. Casing Method
1. Dry Method
The dry method is suitable for use on soil above the groundwater level
when the drill holes are not landslides, such as homogeneous rigid clay.
The dry method can be carried out on soil under the groundwater
table, if the soil has a low permeability, so when drilled, water does
not enter the drill hole when the hole is open
In a dry method, the holes are made using a drill machine without
a protective pipe without casing
The bottom of the drill hole is dirty by the clearance of the soil is
cleaned, the reinforced strands are inserted into the borehole and then
casted
2. Wet Method
Wet method is generally done when drilling passes water table, so the drill
hole always avalanche if the wall is not retained.
In order for the hole not to slide, inside the drill hole is filled with clay soil
solution or polymer solution, so the drilling is done in solution
If the desired depth has been reached, the drill holes are cleaned
and the embedded strands are inserted into the borehole which still
contains the bentonite liquid (Polymer)
The concrete mix is inserted into the borehole with the tremie tube, the
bentonite solution will be pushed and carried up by the concrete mix
The solution coming out of the drill hole, accommodated and can be used
again for drilling at the next location.
3. Cassing Method
This method is used if the drill hole is very easy to landslide, for example the land location is
clean sand beneath the water table.
To hold the drill hole is not avalanche used steel pipe casing (Casing)
The installation of a sheath pipe into the borehole is accomplished by placing, shaking or
pressing the steel pipe to the specified depth.
Prior to penetrating the ground water surface the sheath pipe is inserted.
The soil inside the shell pipe is removed during excavation or after the casing to the desired
depth. Then the drill hole is cleaned and the coupled rebar is inserted into the sheath pipe
The concrete mixture is inserted into the hole (when hole preparation is used, the tremie pipe
is used for casting)
The sheath pipe is pulled up, but sometimes the pipe is left in place.
Phase to work of Bore Pile Fondation
Type 3
1. Preparetory Work
2. Drilling Work
3. Installation Work
4. Cast Work
1. Preparetory Work
Prepare heavy
equipments and
Marking and
Cleaning other equipments
setting out bore Ready mix what needed for
borepile points
pile point ( with standby Prepare pump drilling.
Assembly rebar
area
theodolite) (according to for cleaning (like Crawler crane as shop
(can use ,rig bor, Earth drill,
Make sure the technical borepile hole auger bucket, drawing
excavator for bucket bor, bucket
point as shop specifications)
cleaning area) cleaning, tremie
drawing tube, sling, casing
pipe)
2. Drilling Work
Drill ground as with Manual checking Install the casing Cleaning borehole
borehole point with borehole tube to avoid from earth, mud,
Heavy Equipment landslide at wall water, and etc
(can use crawler borehole
crane with auger or
drilling machines)
3. Installation Work
Fill the borehole with Lift the tremie pipe along Lift the shell pipe back
concrete from ready mix cast concrete till again as needed
with concrete bucket lift concrete fulled the
with crane till borehole is full
by concrete. During casting
borehole
use vibrator.
Next cast concrete for the
pile cap if borepile has
been finish
Cast work must be
continous till full
Thank You