09 - Construction & Fabrication Management
09 - Construction & Fabrication Management
09 - Construction & Fabrication Management
Revamping Projects
Oil & Gas Downstream Projects
9. Construction and Fabrication Management
I. Introduction
II. Preliminary Studies
III. Basic Engineering (or FEED)
IV. EPC Contracting
V. Organization and Engineering
VI. Procurement
VII. HSE, Quality and Risk Management
VIII. Project Control (cost/schedule)
Scope
• Prefabrication of equipment and transportation to project site
• Site preparation including civil works
• Erection of main equipment, installation and connection
Objectives
• Assure prefabrication of equipment and transportation to the site
• Confirm and implement the site construction strategy and
organization
• Ensure timely mobilization and control of field subcontractors
• Achieve the construction challenges (Safety, Quality, Schedule,
Cost)
And for:
• Revamping projects with modules which will be installed during
shut-downs, instead of erecting corresponding facilities
Skids are often small (“EPC”) units; concerns for alignment with
other facilities design, procurement & construction include:
• Design capability of Vendor e.g. for instrumentation, electrical
design to be carefully checked and controlled
• Equipment standardization: consider free issue of components
(instrumentation, minor piping parts, pump seals)
• Process Control integration (PLCs: Programmable Logic
Controllers…): standardization, design, FATs, SATs
• Acceptance of “Vendors standards” in particular for utilities skids
such as N2 production, instrument air, cooling systems
Materials Management
Change Management
Interfaces Management
Roles and responsibilities between Subcontractors, and with
Owner
Decision Process (changes, financial matters, safety issues)
Project quality documentation circulation, approval and follow-up
Communication (periodic meetings, reporting, staff
presentations)
Deviation Requests to construction standards, approval
authorities
Non-conformance procedure, near-misses, incident investigation
Workfront availability
“Job Cards” sheets: a method to define and control revamping works (in
particular S/D) by detail itemization of work & required resources, material &
time
Work is defined by reference to Commissioning sub-systems; PIDs, GA
drawings tie-ins list per discipline (showing work definition for ea. S/D)
Equipment card: new or modified equipment
Piping card: a piping network with limits defined by tie-ins, equipment nozzles
or sub-systems limits (a commissioning sub-system includes 1 or several JC)
Job Cards identify applicable technical documents (PID, installation and
dismantling dwgs, list of included isos & tie-ins), & include:
• Detail work description; sketches showing system dismantling, installation, tie-ins
• Safety requirements with required personnel
• Construction personnel & man-hours
• Construction equipment (scaffolding, crane, tools… with sketches for erection)
The Job Card detail work split allows, ahead of Shutdown, to:
• Estimate man-hours by Card and globally required
• Plan/schedule Shutdown by Card, with manpower histograms
• Assign construction teams by geographical areas
• Use similar system for construction & commissioning
• Prepare materials by Card (piping spools are identified by their Card
number, erection materials are bagged & tagged per Card)
Site Preparation
Progress Measurement
• Weekly Progress follow up by Work Quantities / Man-hours
Productivity Analysis
Man-hours Expenditure
• Weekly man-hours follow up per trade
I. Specific construction
Transportation procedures
Safety procedures