NTPC Implementation of APDRP-II
NTPC Implementation of APDRP-II
restructured APDRP
during 11 Five year
th
1. Data Center
2. Circle Office
Creation of IT Infrastructures 3. Division Office
at : 4. Sub Division Office
5. Call Center
6. Substation
Call
Center
Data acquisition server
ID
Sub Division office S
Fire Wall
Radius Server Reverse Proxy
Fire Wall HQ/ other
acess
Interal
Offices Switch
Lan Interal
Lan
Core
IDS Core Mail Server DNS
Switch IDS LDAP
Switch
Web Server
GigabyteDual Lan
Distribution Switch
Db & CI Cluster
Db & CI Cluster for GIS & Map
for Applications
Interal
Lan San
San
switch
switch
NMS Server
` Application & GIS Server
Media
Library
`
Back Up Server
SAN Storage
Back Up Server
Data center architecture
Fault tolerant tier IV data center infrastructure
with simultaneous active distribution paths. All
hardware with duplicate power supply and
separate UPS with N+1 redundancy
Data base and main application servers shall be
enterprise level SMP RISC / Itanium processor
based UNIX systems
Data base servers shall be deployed in cluster fail
over mode and application servers in scale out
mode
Data center shall be connected to other utility
offices through VPN WAN
Data center architecture- Cont
The Data base servers shall have access to the
common single database on an external central
storage through a switched Fiber Channel Storage
Area Network (SAN).
The central storage shall support hardware based
(host independent) data replication to a remote DR
site and bi-directional data copy
To achieve zero performance impact backup,
backup server will back up from the mirror copy of
the database
Additionally the robotic controlled tape library shall
be central library of tapes for all the servers
offered in the system.
WAN
Creation of WAN Backbone, capable of carrying data
and voice and through secure VPN tunnel via internet.
The Router shall have ISDN BRI Card for ISDN
connectivity in case of link failure.
There will not be any connectivity in office hierarchy. All
utility offices shall be connected directly to the Data
centre.
Minimum 2 Mbps VPN link for connection between Data
center and Utility HQ ( If data center is not located inside
HQ premises ) and subdivision offices. Other offices
shall be connected through 512 Kbps VPN link.
Provision for upgrading band width
Datacenter to have 2 Mbps internet leased line for web
server
IT infrastructure at other offices
All Subdivisions shall have data
acquisition server fitted with front end
processor for data acquisition from
Feeder/ DT/ HT consumer meters at pre
defined interval.
All offices shall have a LAN connected to
switches and Router for upward
connectivity to data center.
IT infrastructure at S/s and DTs
All Substations shall have a data logger PC which will collect
all S/s Meter data through RS 485 port of the meters through
a RS 485/ RS 232 data converter unit.
The data logger data to be transmitted to data acquisition
server at sub division over GSM/CDMA/ PSTN lines.
Data logger at substation will have on screen display of the
S/s SLD and energy balance and losses at Bus bar and
Transformers ( Both instantaneous and aggregated Value)
Moreover data logger will display voltage, current and
demand ( both maximum and minimum) .
DTs and selected HT consumers (HT consumers of mixed
feeder) shall have meters with RS-232 ports and data
acquisition server at Subdivision shall poll meter data at
regular interval through GSM/ CDMA modems retrofitted on
meter RS 232 or optical port itself.
All the Sub division servers shall push the entire incremental
meter data to data center during off-peak hours for
aggregation and MIS generation as per various hierarchical
requirement of the utility.
Application packages
The application packages designed for defining the various
business processes of the utility have been categorized in
three parts in SRS Template-
Part-A (Modules essentially required by most of the
Utilities, since they do not possess these IT enabled
systems, like GIS based Consumer indexing, Asset
mapping and Network Analysis, Meter Data Acquisition,
Energy Audit, Customer care center, New connection,
Dismantling & disconnection, MIS )
Part-B (M,B,C) - If M,B,C and other standalone software
solutions are in place, the bidder has to integrate the same
with the offered solution including design and supply of
necessary middleware. However, he shall supply
necessary software solution for M,B,C also, if the same is
not available with the utility or the existing system is not
integratable with offered solution.
Part-C (Optional packages of Asset Mgmt. & Maintenance
Mgmt.)
(Facilities to be created by owner)