Activity Based Costing
Activity Based Costing
Activity Based Costing
HP:Ch-5
Activity based costing (ABC)
Activity based costing (ABC) is an alternative
approach to absorption costing.
It involves the identification of the factors (cost
drivers) which cause the costs of an organization's
major activities.
The reasons for the development of ABC
Reasons
In the past:
• Most organizations used to produce only a few products.
• Direct labour costs and direct material costs accounted for the largest
proportion of total costs and so it was these variable costs that needed to be
controlled.
• Overhead costs were only a very small fraction of total costs and so it did
not particularly matter what absorption costing bases were used to apportion
overheads to products.
Nowadays:
• Costs tend to be fixed and overheads huge.
• Manufacturing is capital and machine intensive rather than labour
intensive and so direct labour might account for as little as 5% of a product's
cost. For example, furniture is no longer made by skilled workers. Instead
complicated expensive machines are programmed with the necessary skills and
workers become machine minders.
Many resources are used in support activities such as
setting-up, production scheduling, first item inspection
and data processing.
These support activities help with the manufacture of a
wide range of products and are not, in general, affected
by changes in production volume. They tend to vary
instead in the long term according to the range and
complexity of the products manufactured.
Problems of using absorption costing in today's
environment
Overhead absorption rates might be 200% or 300% of unit labour costs.
Unit costs are distorted and so cost information is misleading.
Overheads are not controlled because they are hidden within unit
production costs rather than being shown as individual totals. Products bear
an arbitrary share of overheads which do not reflect the benefits they
receive.
Absorption costing assumes all products consume all resources in proportion
to their production volumes.
It tends to allocate too great a proportion of overheads to high volume
products (which cause relatively little diversity and hence use fewer support
services).
It tends to allocate too small a proportion of overheads to low volume
products (which cause greater diversity and therefore use more support services).
Required
Calculate product costs using absorption costing and ABC.
A. Using absorption costing
Workings
$3,080 ÷ 440
W1 machine hours = $7 per machine hour
$10,920 ÷ 14
W2 production runs = $780 per run
$9,100 ÷ 14
W3 production runs = $650 per run
$7,700 ÷ 14
W4 production runs = $550 per run
C. Comparison
Product P1 P2 P3 P4
Output in units 120 100 80 120
Costs per unit: $ $ $ $
Direct material 40 50 30 60
Direct labour 28 21 14 21
The four products are similar and are usually produced in production runs of 20 units.
The total of the production overhead for the period has been analyzed as follows.
$
Set up costs 5,250
Stores receiving 3,600
Inspection/quality control 2,100
Materials handling and despatch 4,620
You have ascertained that the following 'cost drivers' are to be used for the costs shown.
Set up costs Number of production runs
Stores receiving Requisitions raised
Inspection/quality control Number of production runs
Materials handling and despatch Orders executed
The number of requisitions raised on the stores was 20 for each product and the number of orders executed was
42, each order being for a batch of 10 of a product.
Required : The total costs and per unit for each product using activity based costing
P1 P2 P3 P4
$ $ $ $
Direct material 4,800 5,000 2,400 7,200
Direct labour 3,360 2,100 1,120 2,520
Production overhead *
Set up costs(D1) 1,500 1,250 1,000 1,500
Stores receiving(D2) 900 900 900 900
Inspection/quality control(D1 600 500 400 600
Material handling and despatch(D3) 1,320 1,100 880 1,320
* Overhead costs will be divided in the following ratios, depending upon the number of
production runs, requisitions or orders per product.
P1 P2 P3 P4
D1-Production runs 6=120/20 5=100/20 4=80/20 6=120/20
D2-Requisitions raised (as given) 20 20 20 20
D3-Orders executed 12=42*6/21 10=42*5/21 8=42*4/21 12=42*6/21
Analytics of costing system design
Costing as an approximation exercise:
In most organizations costing systems serve many different needs such as
product costing,
pricing,
product line decisions,
capacity planning and allocation,
performance measurement and control,
project scheduling, project selection, and
benchmarking, among other uses.
In order to assess the cost implications of their short- and long-term planning
and control functions, managers try to understand how costs behave and how
cost objects consume resources by means of cost functions.
Indirectcosts:
indirect wages(£) 33,000,000
depreciation(£) 85,000,000
material and tools(£) 17,000,000
Total: 135,000,000
A costing example
Panel B: Traditional costing with direct labour hours as allocation base
Product A Product B Product C
Direct material cost(£) 2,500 2,300 2,000
Direct labour cost(£) 1,400 2,100 700
Indirect cost(£) 3,000 4,500 1,500
Total 6,900 8,900 4,200