Notes On Critical Path Method: EM416/EA302
Notes On Critical Path Method: EM416/EA302
Method
EM416/EA302
What is network planning?
• Laddering. Some projects have a set of activities that are repeated several
times. Laddering is used to diagram this type of project so that the project can
be completed in the shortest possible time while making the best use of
resources.
•
The steps in preparing a network diagram
• Select the format to be used, AIB or AOA.
• Start drawing the activities in their logical sequence.
• Ask the following three questions for each activity:
• Which activities must be finished immediately before can start this
activity?
• Which activities can be done concurrently with this?
• Which activities cannot be started until this activity is finished?