Developed by .. 1) Rakesh Raghavani (11Cl083) 2) Rahul Raghavani (11CL084) 3) Jayadeep Rana (11CL084)
Developed by .. 1) Rakesh Raghavani (11Cl083) 2) Rahul Raghavani (11CL084) 3) Jayadeep Rana (11CL084)
Developed by .. 1) Rakesh Raghavani (11Cl083) 2) Rahul Raghavani (11CL084) 3) Jayadeep Rana (11CL084)
1) Rakesh Raghavani(11Cl083)
2) Rahul Raghavani(11CL084)
3) Jayadeep Rana(11CL084)
Water Bond macadam
Macadam's road building technology was applied to roads by other
engineers.
One of these engineers was Richard Edge worth, who filled the gaps
between the surface stones with a mixture of stone dust and water,
providing a smoother surface for the increased traffic using the
roads.
1. 90 to 40 100 100
80 65 - 85
63 25 - 60
40 0 – 15
20 0 -5
2. 63 to 40 80 100
63 90 – 100
50 30 – 70
40 0 – 15
20 0–5
3. 50 to 20 63 100
50 95 – 100
40 35 – 70
20 0 – 10
10 0-5
2. Screenings :
The screenings are used to fill up the voids in the
compacted layer of coarse aggregate.
The screening consists of aggregates of smaller size,
generally of the same material as the coarse
aggregates.
The grading requirements of screenings for WBM
construction are given in table.
Grading Size of screening Sieve size % by weight passing
B 10 mm 10 mm 100
4.75 mm 85 – 100
150 micron 10 – 30
3. Binding Materials :
Binding material consisting of fine grained material is
used in WBM construction to prevent revelling of the
stones.
Kanker nodules or lime stone dust may also be used.
Binding material should have plasticity index between
4 to 9 when WBM is used as surfacing coarse.
Binding material need not be used where crushable
type material like moorum or soft gravel is used as
screenings.
Construction method :
1. Preparation of foundation for receiving the WBM
coarse :
The foundation receiving the new layer of WBM may be
either the subgrade or sub-base coarse.
This foundation layer is prepared to the required grade and
camber.
It is also cleaned of all dust and loose materials.
Any ruts or soft spots should be corrected and rolled.
The foundation should be well dried.
When the existing road is black topped.
Furrows are cut at 1 m intervals at 45 degrees to the centre
line of the carriage way.
2. Lateral confinement of aggregates :
If the aggregates are placed on the subgrade, they are
likely to be loosened and come out under the load of the
traffic.
Hence, the aggregates have to be confined.
This is done by constructing the shoulders first to the
thickness of the WBM(7.5 mm).
The inside edges are trimmed and the included area is
cleaned of all spilled materials.
4. Rolling :
After spreading the coarse aggregates compaction is done
by a three wheeled power roller of capacity 6 to 10 tonnes.
The rolling should begin from edges with the roller
running forward and backward until the edges have been
compacted.
The roller should overlap each preceding wheel track by
one half width.
Rolling is stopped when the aggregate are partially
compacted to permit application of screenings.
5. Application of screening :
After the coarse aggregate are compacted adequately, the
dry screening are applied over the surface to fill the
interstices in three or more application.
Dry rolling is continued as the screening are being spread
and brooming carried out.