Crashing of Activities Example

The critical path is A-B-E-F with a total normal duration of 15 weeks. To shorten the project duration by 3 weeks, tasks A and D should each be shortened by 1 week, costing an additional $500 + $2000 = $2500. The new critical path after crashing would be checked to ensure it is still shortened by 3 weeks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
162 views2 pages

Crashing of Activities Example

The critical path is A-B-E-F with a total normal duration of 15 weeks. To shorten the project duration by 3 weeks, tasks A and D should each be shortened by 1 week, costing an additional $500 + $2000 = $2500. The new critical path after crashing would be checked to ensure it is still shortened by 3 weeks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Example: Crashing of activities

Activities Preceding Normal Crash Time Cost Cost


Activities Time in Wks in Wks Normal $ Crash $
A - 4 2 10000 11000
B A 3 2 6000 9000
C A 2 1 4000 6000
D B 5 3 14000 18000
E B,C 1 1 9000 9000
F C 3 2 7000 8000
G E,F 4 2 13000 25000
H D,E 4 1 11000 18000
I H,G 6 5 20000 29000
Key
ABDHI 22 wks
Crash A by 2 wks
Crash D by 1 wk
A) What are the critical path(s) and the estimated completion time, normal time.
Addnl Cost =
B) To shorten the duration of the project by 3 weeks, which tasks should be shortened and by
500+500+2000
how many weeks , and what would be the additional cost to do that.
Check critical path after
each week of crashing
Review
Quiz
Activity Immediate Preceding Duration in days
Activities

A - 5
B A 7
C A 3
D C 3
E B,D 3
F E 2

1 Draw the network diagram


2 Identify the critical path(s).
3 If activities can be crashed at cost per day given below, can you complete the project in 15 days , and what would be
the additional cost?
Cost of crashing per day A:$80, B=$50, C=$75, D=$100,E=$200,F=$175
till duration reaches 2 days and no more crashing is possible.