Introduction To Project Management: Malcolm Kear
Introduction To Project Management: Malcolm Kear
Introduction To Project Management: Malcolm Kear
Malcolm Kear
Initiate Project
Prepare Technical Design
Ensure Machine Compatibility Prepare
Safety Case Modification
Undertake Tender
Project
set-up Project
Major
Definition Conceptual
Project Scheme
Design
Proposals Design Detailed Tender
Appoint Project Sponsor Design Invitation &
Assess Project Priority
Assess Budget Implications
Est. Proj. Deliverables and Objectives
Raise/Extend/Update initial TCD-R/PERF Assessment
Prepare Outline Conceptual Design
Appoint Project Leader
Define Design Constraints Prepare Extend TCD-Rs/PERFs
Approve Project Set-up
Interface Requirements Spec. (IRP) Prepare Sub-system Detailed Design Hold
Finalise Conceptual Design Detailed Design Review (DDR)
EFDA/CSU/JOC Management Hold Conceptual Design Review (CDR) Clear Sub-system DDR Issues
Clear CDR Issues Use TCD-I/MMAC for Sub-system DD Approval
Initiate Modification Safety Case Prepare Final Documents including:
Update PMP - Design Documents., Machine Compatibility *** These will comprise:
Approve Proceed to Detailed Design Documents., Safety Case Modification - Technical Specification
- Drawings
Project Team/IRP/EFDA/CSU/JDC Project Team/Interfaces/EFDA/CSU/JDC - Contractual Requirements
Obtain
WHEN PRINTED
Acceptance of Completed Project
**** This includes Project Team/ICM
supporting documentation
Project Team/EFDA/CSU
Key Points in Project Set-up and Definition
Bulk W Bulk Metal Torus Installation Contractual Prepare & Ship Bulk Metal Tiles Erosion/Deposition
Divertor Tiles Group Management JET Be Install Prep. Assemby & Calib.
1.1.2.0.0 1.2.2.0.0 1.3.2.0.0 1.4.2.0.0 1.5.2.0.0 1.6.2.0.0 1.7.2.0.0
R&D Engineering D&M ILW Tile Removal FZJ Contract Install Prep.
Management Management & Replacement Management Management
1.1.5.0.0 1.2.5.0.0 1.3.5.0.0 1.4.5.0.0 1.6.5.0.0
Thomson Scattering
Core (LIDAR)
5.5.C.1.0.0.0.0
LIDAR Project LIDAR System Laser Collection Laser Path Control & LIDAR LIDAR Interfaces &
Management Concepts Systems Optics Optics Acquisition Port Engineering Services Integrated Testing
1.1.0.0.0 1.2.0.0.0 1.3.0.0.0 1.4.0.0.0 1.5.0.0.0 1.6.0.0.0 1.7.0.0.0 1.8.0.0.0 1.9.0.0.0
Key Project Overall Cluster Lasers Collection Laser Path Control System Shutters Water LIDAR
Milestones Co-ordination 1.3.1.0.0 Optical Design Optical Design Interface Definition 1.7.1.0.0 Services Interfaces
1.1.1.0.0 1.2.1.0.0 1.4.1.0.0 1.5.1.0.0 1.6.1.0.0 1.8.1.0.0 1.9.1.0.0
Key Project Performance Laser Collection Laser Control Labyrinth Interspace Mock-up
Deliverables Analysis Layout Windows Windows System 1.7.2.0.0 Vacuum Facility
1.1.2.0.0 1.2.2.0.0 1.3.2.0.0 1.4.2.0.0 1.5.2.0.0 1.6.2.0.0 1.8.2.0.0 1.9.2.0.0
Key ITER LIDAR Laser Beam In-Vacuum Plasma Facing Acquisition Extension Tubes & LIDAR Basic Mock-up
Milestones & IPL Neutronics Combiner Collection Mirrors Laser Mirrors System Mirror Mounting Power Tests
1.1.3.0.0 1.2.3.0.0 1.3.3.0.0 1.4.3.0.0 1.5.3.0.0 1.6.3.0.0 1.7.3.0.0 1.8.3.0.0 1.9.3.0.0
Overall Scattering Ex-Vacuum Other Laser LIDAR External Port Optics Spectrometer Tokamak
Management Theory Collection Optics Mirrors Instrumentation Mounting Area Tests
1.1.4.0.0 1.2.4.0.0 1.4.4.0.0 1.5.4.0.0 1.6.4.0.0 1.7.4.0.0 1.8.4.0.0 1.9.4.0.0
Safety & HP R&D Collection Optics Laser Path Safety Bioshield Laser Final System
Management Tasks Mechanical Design Mechanical Design Interlocks 1.7.5.0.0 Room Testing
1.1.5.0.0 1.2.5.0.0 1.4.5.0.0 1.5.5.0.0 1.6.5.0.0 1.8.5.0.0 1.9.5.0.0
Risk Radiation Spectrometer Beam Safety BSM Port Cell/ System Assembly
Management Effects Data System Dump System Penetrations Interspace & Dis-assembly
1.1.6.0.0 1.2.6.0.0 1.4.6.0.0 1.5.6.0.0 1.6.6.0.0 1.7.6.0.0 1.8.6.0.0 1.9.6.0.0
Engineering Calibration
Analysis System
1.2.9.0.0 1.4.9.0.0
Project Planning WBS (1)
Lowest Level of WBS is the Work Package
(WP)
WP can be clearly defined allowing package
to be costed, scheduled and resourced
WP contains a list of Tasks to be Performed
that form the basis for the Schedule
WP allows assignment of responsibilities
(Work Package Manger, WPM)
Project Planning WBS (2)
WBS allows hierarchical build-up of costs
and schedule
Cost and Schedule can be reported at any
level of the WBS
WBS facilitates strong management during
project execution (Cost and Schedule
control)
WBS can be used for many other things -
Document Management, Risk Management
etc.
Project Planning
A word about Scheduling
Schedules (task durations) can have a wide
variation
There is no unique answer. Rather, there is a
statistical variation depending on assumptions
Need to understand the basis of scheduling
(Most challenging; Most likely; Absolute certainty
- bet your life on it!)
Most people are very optimistic/naive
Common schedule development
Accuracy of Timescale Estimates
100
90
80
Subsequent
70 Estimates
Probability
60
50
40
30 First
Estimate
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Timescale
Example WBS for the
ITER-Like Wall & TSCL Projects
MJ Kear
Project Planning Key Points
Recognise that adequate project planning is
essential
Produce a sound WBS
Use the framework provided by the Project
Management Plan (PMP) template
Involve the right people
Allow enough time
Be systematic
Project Risk Management
Project Risk Definition (1)
Project risk is an uncertain event or condition
that, if it occurs, has a positive or negative
effect on a project objective
Project Risk Definition (2)
A combination of the probability of a defined
threat or opportunity (Likelihood) and the
magnitude of the consequences of the
occurrence (Impact) defines a Risk Index
Risk Impact
Threat Scope Poor Quality Product
Threat Schedule Late Delivery
Threat Cost Overspend
MJ Kear
Risk Management Key Points
Make the management of risk integral to the
way the project is managed
Ensure that cost and time contingencies are
consistent with identified risks
Focus on the significant few dont try to
manage too many risks
Be vigilant and proactive
Project Monitoring and Control
Exercise 3
Write down three typical project
control/monitoring activities
Project Monitoring
Typical Monitoring Activities
regular reviews of progress against schedule
using WBS as basis (Plan against Baseline)
regular review of actual costs (O/P from SAP)
against budgeted costs and Earned Value at
WBS level
regular review of resource loading
regular progress meetings with project team
regular meetings with contractors
production of periodic progress reports
risk reviews
inspections/ audits
Project Control
Typical Control Activities
assign responsibilities at Work Package level
staged authorisation of work to be done
staged release of budgets (staged release of
WBS(e) numbers)
ensure PM has a Management Reserve under
his control
seek corrective action reports when WPs go off
track (overrunning or overspending)
release Management Reserve carefully
Project Monitoring and Control
Summary
Monitor against the plan status regularly
Take a factual approach to decisions
Identify management action early
Check that defined controls are being
applied correct if necessary
Apply change control
Introduction to Design Management
Design Management
Design takes place as part of a project
Design Management is part of Project
Management
Design Management considerations must be
included in the PMP
Exercise 4
Write down three Design Management
Activities
Exercise 4 - Design Management Activities
Sub-divide Design Stages (CD, SD & DD)
Sub-divide Tasks (WBS)
Define Constraints and Interfaces (WPD
Summary Sheet)
Formally Initiate the Design (TCD-R/PERF)
Ensure Design conforms to H&SE and CDM
Requirements
Hold Design Reviews (Peer review)
Formally Approve Design (TCD-I/MMAC)
Design Stages
Conceptual Design
Scheme Design
Detailed Design
Conceptual Design Phase
TCD-R
Decide Local or TCS route
Develop Conceptual Design
Define Constraints & Interfaces
Carry out Conceptual Design Review
Initiate Safety Case Modification if required
Obtain Approval to Proceed to next stage
Scheme and Detailed Design
Basic considerations and process similar to
concept
Need to ensure that safety & environmental
issues receive proper consideration as
design develops (CDM Regulations)
Exercise 5
List who should be invited to a design review
Write down three issues that should be
considered at a design review
Exercise 5 - Design Reviews, Attendance
Project Leader or nominee (Chairman)
RO (Work Package Manager)
Customer
End User
Safety and Quality Reps
All other Relevant Interfaces/Stakeholders
Other Experts in the area being reviewed
Exercise 5 - Design Reviews, Issues to
Consider
Assumptions and Constraints
Technical Solutions - Does it meet the Spec?
Safety, Environment and CDM issues
Can it be Manufactured/Maintained?
Actions from previous DRs
Issues to be resolved (including Timescales)
Safety & Environment
Need to ensure that safety & environmental
issues receive proper consideration as
design develops
Involve the right people from the start
Systematically identify issues Hazards/Risks,
Environmental Aspects & Impacts
Carry out rigorous reviews at each design stage
Control Design Changes
MUST take note of CDM Regulations
CDM Regulations
CDM - Construction (Design & Management)
Regulations recently updated
Now must have someone in EACH Project
Responsible for CDM
Currently information is on the Conceptual,
Scheme & Detailed Design steps on the
Process Maps
More information will be developed over the
coming months
Design Change control
Needs to be a formal and defined procedure
New procedure in place CD/P/J008 for JET
Facilities
Confirm Completion
Ensure design records are complete and
accurate
Ensure any outstanding actions or issues
are addressed
Ensure Maintenance Records are produced
Ensure User Manuals are produced
Hold a formal Post Project review