Litra Master Plan: Details of Plan and Missions
Litra Master Plan: Details of Plan and Missions
3or5 working days 1 working days 3or4 working days 2or3 working days 1or2 working days 1or2 weeks
NOW
Details of plan and missions
Relative
Items Mission Target Time Owner Update Status
Department
Meeting with Confirm the details of the
Communicate with client, confirm the details of the test plan 6/14/2017 Open
clients test plan
LiTRA server Server power on, and service can interwork in the server 6/19/2017 NIS Open
Prepare terminals and simcards, and terminals can access to the core 6/19/2017
Prepare material FrontlineR&D Open
network which the server is connected,(We recommend EP820)
Prepare terminals
Prepare switch, router and so on to connect the LiTRA Server with core 6/19/2017
Frontline Open
network
Plan clarification Negotiate connection plan Communicate with clients to make the connection plan 6/19/2017 R&D Open
6/23/2017
Setup environment Install and configure software system for LiTRA Service R&D Open
6/23/2017
Apply IP Apply IP for LiTRA Server Client Open
Setup environment
6/23/2017
Core network Add IP in PGW for interworking with PTT Server Open
6/23/2017
Connect with core network PTT server connects with core network R&D Open