Litra Master Plan: Details of Plan and Missions

The LiTRA Master Plan outlines the key steps and timeline for setting up and testing a new LiTRA service. It involves: 1) Equipment arrival and setting up the service environment over 3-5 working days. 2) Connecting to the core network over 3-4 working days. 3) Presetting and testing the service over 2-3 working days, followed by a debriefing on status. 4) Acceptance testing of the service over 1-2 weeks before the project is completed.

Uploaded by

ellonndlovu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views1 page

Litra Master Plan: Details of Plan and Missions

The LiTRA Master Plan outlines the key steps and timeline for setting up and testing a new LiTRA service. It involves: 1) Equipment arrival and setting up the service environment over 3-5 working days. 2) Connecting to the core network over 3-4 working days. 3) Presetting and testing the service over 2-3 working days, followed by a debriefing on status. 4) Acceptance testing of the service over 1-2 weeks before the project is completed.

Uploaded by

ellonndlovu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 1

LiTRA Master Plan

Begin Setup Connect with core Service Service


Equipment arrive environment network presetting acceptance Test launched Test finished

3or5 working days 1 working days 3or4 working days 2or3 working days 1or2 working days 1or2 weeks

2017-06-14 2017-06-14 2017-06-22 2017-06-26 2017-07-03 2017-07-7 2017-07-14 2017-07-17

NOW
Details of plan and missions
Relative
Items Mission Target Time Owner Update Status
Department
Meeting with Confirm the details of the
Communicate with client, confirm the details of the test plan 6/14/2017 Open
clients test plan
LiTRA server Server power on, and service can interwork in the server 6/19/2017 NIS Open
Prepare terminals and simcards, and terminals can access to the core 6/19/2017
Prepare material FrontlineR&D Open
network which the server is connected,(We recommend EP820)
Prepare terminals
Prepare switch, router and so on to connect the LiTRA Server with core 6/19/2017
Frontline Open
network
Plan clarification Negotiate connection plan Communicate with clients to make the connection plan 6/19/2017 R&D Open
6/23/2017
Setup environment Install and configure software system for LiTRA Service R&D Open
6/23/2017
Apply IP Apply IP for LiTRA Server Client Open
Setup environment
6/23/2017
Core network Add IP in PGW for interworking with PTT Server Open
6/23/2017
Connect with core network PTT server connects with core network R&D Open

Verify service environment 6/28/2017 Open


LiTRA Service test LiTRA Service test Preset terminal for testing 6/28/2017 R&DClient Open
Preset dispatcher console 6/28/2017 Open
Debrief for the presetting After finish the service preset, debrief to client for the status of service
Debrief of process 7/03/2017 R&DNIS Open
status verification and the test plan for the next phase
FrontlineR&D
Service acceptance Service acceptance LiTRA Service function acceptance 7/07/2017 Open
Client
Prepare one copy of LiTRA Service operation manual 7/14/2017 R&DSales Open
Service testing Service testing
Acceptance testing 7/19/2017 FrontlineClient Open