Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)
(WBS)
By: AMRIL HADRI BIN JAMALUDIN
Faculty of Civil Engineering
UiTM Arau, Perlis
In the end of the lesson, students
should be able to:
Work Package 1
Concrete Ground Floor Slab
Excavate the footings
Install the edge forms
Install under slab fill
Install vapor barrier
Install the reinforcing
Place the concrete
Finish the concrete
Strip the form work
WBS (cont)
In other word, work package consists of the Main
activity & its Sub-activities
Work Package 1
Main activity
Concrete Ground Floor Slab
Excavate the footings
Install the edge forms
Install under slab fill Sub-activities
Install vapor barrier
Install the reinforcing
Place the concrete
Finish the concrete
Strip the form work
WBS (cont)
Work Package 2
This is what we called
- Main activity 2
Work Breakdown
Sub-activity 2.1 Structure (WBS)
Sub-activity 2.2
Sub-activity 2.n
Work Package 3
- Main activity 3
Sub-activity 3.1
Sub-activity 3.2
Sub-activity 3.n
Example of various usage of
WBS in construction projects
Summary
WBS is an organizational tool which can
be used to establishes the basic building
blocks of estimate & schedule.
Main purposes is to organize & identify the
work of the project by breaking each
division of work into a separate work
package.
It also avoids us from overlook any of the
steps needed to complete the work.
Conclusion
Remember: