Indian Electricity Grid Code

Contents
1. General
2. Role of various organisations and their linkages
3. Planning code for Inter State Transmission
4. Connection Code
5. Operating Code
6. Scheduling and Despatch Code
7. Miscellaneous

2
1. General
Introduction
IEGC

Rules
Guidelines
Standards

for

Utilities ISTS

To plan, develop, operate & connected with / using


maintain National/Regional
Grid
Power System Documentation of the principles
which define relationship
between various users
Facilitation of optimal operation
Facilitation power
markets and ancillary services
Facilitation 4
renewable energy sources
Compliance Oversight (1.5)

RLDC
Report
Repeated
Violation/
Persistent
suo-motto CERC
Non
Compliance Action

RPC Consensus
Report issues
not sorted

5
Compliance Oversight (1.5)

Non Compliance
by
NLDC, Report CERC
RLDC, by any
SLDC, person Action
RPC through
or any other person petition

6
2. Role of
Various Organizations and their
linkages
NLDC, RLDC, RPC, CTU, CEA,
SLDC & STU
Role of NLDC (2.2)
NLDC
Economy and Efficiency of National Grid
Monitoring of operations and grid security of National Grid
Restoration of synchronous operation of National Grid
Trans-national exchange of power
Feedback to CEA & CTU for national Grid Planning
Dissemination of information
Levy and collection of fee and charges - CERC
Disse Supervision Coordinate

Supervision & control


RLDC
Coordinate
RPC for
regional outage Plan
Inter Regional Links

Accounting
8
Role of RLDC (2.3)

RLDC

Real time operation , control & contingency


analysis
Generation scheduling/ re-scheduling
Exclusive Restoration
functions Metering & data collection
Compiling & furnishing of operation data
Operation of Regional UI pool Account. Reactive
energy account and Congestion charge account
Operation of ancillary services

9
Role of RLDC (2.3)

RLDC
Apex body Functions
for optimum scheduling
and despatch of
integrated electricity
operation Comply Directions Monitor grid operation
the Keep accounts of
directions SLDC electricity transmitted
Exercise Supervision
and control over
Central State the ISTS
For ST Licensee Real time operations
Open
Generating company
Access-
Nodal Generating station / Sub-
Agency stations
any other concerned person 10
Role of RPC (2.4 )

RPC
Facilitate the stable and smooth operations of the system
Functions:
regional level operation analysis
facilitate inter-state/inter-regional transfer of power
facilitate planning of inter-state/intrastate transmission system
coordinate maintenance of generating units
coordinate maintenance of transmission system
protection studies
Planning for maintaining proper voltages
Consensus on issues related to economy and efficiency

MS SRPC shall certify Availability Decisions


of transmission system
Prepare Regional Energy Account,
Weekly UI, Reactive & Congestion
charge account RLDC/SLDC/CTU/
11
STU/ Users
Role of CTU (2.5)
CTU

to undertake Planning shall operate


transmission of
electricity through RLDC
ISTS
to ensure development
of an efficient, co-
ordinated and
economical ISTS STU
State Govt.
State1 ISTS lines
Central RPC
Govt.
CTU/to provide non-discriminatory Open Access Generating
Will not engage in trading and generation
State2 Companies
For LTOA & MTOA nodal agency
CEA Licensees
12
Role of CEA (2.6)

CEA
(Central Electricity Authority)

will formulate short-term and perspective plans for transmission system


specify technical standards for construction of electrical plants, electric lines and
connectivity to the grid
specify safety requirements for construction, operation and maintenance of
electrical plants and electrical lines
specify grid standards for operation and maintenance of transmission lines
specify conditions for SEMs
Promote and assist timely completion of schemes
To collect and record electrical data- cost, efficiency
To carry out investigation ( Electrical system)
13
Shall Prepare National Electricity Plan (NEP)
Role of SLDC (2.6)
SLDC Apex body in a State
Optimum scheduling and despatch Ensure
Monitor grid operations compliance
Directions and
Keep accounts of electricity exercise
transmitted
supervision and
Activities of control
Real-time operation Licensee,
generating company,
exercise supervision and control generating station,
sub-station
Power System and any other
concerned person

Directions
State RLDC
14
Role of STU (2.8)
STU
to undertake
transmission of Planning shall operate
electricity through
intra-state transmission
system SLDC
to ensure development
of an efficient, co-
ordinated and
economical intra-state CTU
transmission system State Govt.
Intra-state transmission system
RPC Generating
STU/to provide non-discriminatory Open Access Companies

Licensees
CEA
15
Role of STU (2.8)
STU

Energy transfer Planning shall operate


Efficient Coordination
Economical SLDC
Provide non-discriminatory
open access

CTU
State Government
Intra-state transmission system Generartors
RPCs
CEA
Licencees

16
3. Planning Code for
Inter-state Transmission
Introduction
Objective
Scope
Planning Philosophy
Planning Criterion
Planning Data
Implementation of Transmission Plan
Introduction

Intra-State Inter-state Intra-State


CTU STU
STU

Transmission schemes
Transmission schemes for planning and
for planning and coordination
coordination CEA

18
Scope of planning code (3.3)

Connected to/using/developing ISTS


CTU ISGS GC

ISTS

SEBs
IPP
STU Objective
Licensees
specify principles,
Generation/Transmission of specify procedures
energy to/from ISTS specify criteria
promote coordination19
information exchange
Planning Philosophy (3.4)
Long-term plan (10-15 years) Annual plan (5 year forward term)

CEA CTU
inter/intra state transmission system Identification of major
inter state/regional lines including
continuously updated to reflect system strengthening schemes
load projections and generation scenarios Planning schemes shall also consider:
CEAs:
NEP Long-term perspective plan
Avoid congestion Electric Power Survey of India report
Transmission Planning Criteria and
guidelines
RPC Feedback
NLDC/RLDC/SLDC feedback
CERC Regulations
Renewable capacity addition (MNRES)

20
Planning philosophy (contd...)
System strengthening schemes by CTU:
shall be done in consultation with CEAs
Standing Committee for Transmission System Planning:
Planning
On the basis of PPA
No PPA/ no consensus CTU may approach CERC in
accordance with CERC (Grant of Regulatory approval
for Capital Investment to CTU for execution of ISTS)

Planning data:
submission by STUs/Users to CTU:
21
Planning philosophy (contd...)
Voltage management by:
capacitors, reactors, SVC and FACTs
similar exercise by STU
STU shall plan to evacuate power from ISTS
ISTS & intra-state transmission systems are
complementary & interdependent
If LTA Applications require strengthening of
intra-state transmission system applicant shall
coordinate with STU

22
Planning Criterion (3.5)
Planning criterion ISTSs security philosophyCEA guidelines

a) Without load shedding or rescheduling of generation, ISTS shall


withstand and secure against the following outages:
a 132 KV D/C line, a 220 KV /DC line,
a 400 KV S/C line, 765 KV S/C line
single Inter-Connecting Transformer (ICT )
one pole of HVDC Bi-pole
Outage of 765 kV S/C line

Without load shedding but could be with rescheduling of generation,


ISTS shall withstand and secure against the following outages:
a 400 KV D/C line
a 400 KV S/C line with TCSC
both pole of HVDC Bi-pole line
Outage of 765 KV S/C line with series compensation

23
Planning Criterion (3.5)
b) ISTS shall withstand the loss of most
severe single system infeed without loss of
stability
c) Any one of the events defined above should
not cause:
loss of supply
prolonged operation of frequency below and
above limits
unacceptable high or low voltage
system instability
unacceptable overloading of ISTS elements 24
Planning Data & Implementation
d)All S/S (132 kV & above) shall have at least two
transformers

e)CTU will carry out reactive power compensation


requirement of ISTS & at ISGS switchyard

f)SPS may be planned by NLDC/RLDC in


consultation with CEA, CTU, RPC & Regional
entities for enhancing transfer capability or to
take care of additional contingencies

25
Planning Data & Implementation
Planning Data (3.6)
As per CERC (Grant of Connectivity, LTA and MTOA
in ISTS and related matters) Regulations 2009
Implementation of Transmission Plan (3.7)
Actual program of implementation of transmission
lines, ICTs, reactors/capacitors and other transmission
elements as per CERC (Grant of Connectivity, LTA
and MTOA in ISTS and related matters) Regulations
2009

26
4. Connection Code
OBJECTIVE
Comply with Minimum Ensure the safe operation,
CEA( Technical technical & integrity and reliability of the
Standards for grid
connectivity to
design criteria Non-discriminatory
New/modified connection not
the Grid) 2007
suffer or impose unacceptable
SCOPE effects
In advance knowledge about
Connectivity
CTU
STU

ISTS

Users connected to ISTS or seeking connection to ISTS


Procedure for connection (4.4)
User seeking new/modified connection:
Shall submit an application on standard format
in accordance with CERC (Grant of
Connectivity, LTA and MTOA in ISTS and
related matters) Regulations 2009
CTU shall process as per above regulations

28
4.5 Connection Agreement

Connection agreement would


be signed by the applicant in
accordance with CERC (Grant
of Connectivity, LTA and
MTOA in ISTS and related
matters) Regulations 2009

29
Reactive Power Compensation 4.6.1

by /STUs and Users in the low voltage systems


close to the load points therby avoiding
exchange of reactive power to/ from the ISTS
Already connected shall provide additional
reactive compensation as per the quantum and
time frame decided by the RPC in consultation
with RLDC.
Installation and healthiness would be monitored
by RPC

30
Data and Communication Facilities (4.6.2)
reliable and efficient speech and
communication system to be provided
Users/STU/CTU shall provide systems to
telemeter power system parameters
Flow
Voltage
Status of switches
Status of transformer taps
Associated communication system to facilitate
data flow up to appropriate data collection point
on CTUs system as specified by CTU in the
Connection Agreement
31
System Recording Instruments (4.6.3)
Data Acquisition System/Disturbance
Recorder/Event Logging facilties/Fault Locator
(including time synchronization equipment )
shall be provided and always kept in working
condition
Responsibility for safety (4.6.4)
CEA (Technical Standards for connectivity to the Grid),
Regulations 2007
CERC (Grant of Connectivity, LTA and MTOA in ISTS
and related matters) Regulations 2009
CEA (Safety Requirements for construction, operation
and maintenance of electrical and electric lines)
Regulations, 2008 32
International Connections to ISTS (4.7)
By CTU in consultation with CEA and MOP

Schedule of assets of Regional Grid (4.8)


CTU and other transmission licensees shall
submit by 30th Sep a schedule of transmission
assets as on 31st March indicating ownership
on which RLDC has operational control and
responsibility.
33
5. Operating Code

34
Operating philosophy (5.1)
objective of the integrated operation:
enhance overall operational reliability and economy
Cooperate and adopt Good Utility Practice
NLDC:
overall operation of National/Inter-Regional Grid
develop/maintain detailed internal operating procedures
for national grid
RLDC:
overall operation of Regional Grid
develop/maintain detailed internal operating procedures
for regional grid
35
Operating philosophy (5.1)
SLDC:
develop/maintain detailed internal operating procedures
for State grid
All licensee, generating company, generating
station and any other concerned person:
comply with directions of RLDC/SLDC
e) round-the clock manning by qualified and trained
personnel of:
control rooms of NLDC, RLDC, SLDC, Power Plant,
Sub Stations (132 kV & above)
control centres of all regional constituents
36
System Security Aspects (5.2)
Synchronism:
all Users, CTU & STU
operate their power systems/stations in an integrated
manner
No deliberate isolation of part of the grid:
except under emergency
safety of human/equipment
when instructed by RLDC
restoration to be supervised by RLDC in coordination
with NLDC/SLDC

37
System Security Aspects (5.2)
Important elements list at RLDC:
not removed without RLDCs consent or prior consent
when specifically instructed
list of important elements to be prepared and shall be
put on website of NLDC/RLDC/SLDC
emergency removal intimated to RLDC
tripping, reason, likely time of restoration intimated to
RLDC say within 10 minutes
Important elements tripping to be informed to NLDC
by RLDC
Prolonged outage ------ sub-optimal operation----
monitored by RLDC------report to RPC-------- finalise
action plan for restoration
38
Restricted Governor Action (5.2(f))
Thermal generating > 200 MW and hydro units > 10 MW
on RGMO wef 01.08.2010
Gas Units, Combined Cycle, wind, solar & nuclear
exempted till CERC reviews
When frequency stabilise at 50.0 Hz FGMO would be
intoduced
RGMO
For Frequency < 50.2 Hz no reduction in generation when frequency
rises
Any fall in frequency generation should increase by 5% limited to 105%
of MCR (thermal), 110% MCR (Hydro)
After increase in generation, the unit mey ramp back to original level at
a rate of 1% per minute
At Frequency < 49.7 Hz ramp up could be at higher rate
governors: 3% - 6% droop
any exception: reason & duration to RLDC

39
System Security Aspects 5.2 (s)

Voltage- (kV rms)


Nominal Maximum Minimum
765 800 728
400 420 380
220 245 198
132 145 122
110 121 99
66 72 60
40
33 36 30
DEMAND ESTIMATION FOR
OPERARTIONAL PURPOSES

Daily Inform to
/Weekly RLDC/
/Monthly RPC
Wind
Energy
Forecast
ATC/
Demand Estimation
Active and reactive TTC
power
on-line estimation
for daily operationa historical data
l use and weather forecast

By 01.01.2011 online estimation of


41
demand for each 15 min block
Demand Management(5.4)
SLDCs shall control demand in the event of:
insufficient generating capacity/inadequate external transfer
breakdown/congestion problems
Demand disconnection
frequency:
below 49.7 Hz: shall initiate action to restrict their net drawal
below 49.5 Hz: requisite load shedding
Each User/STU/SLDC shall formulate contingency procedures and
make arrangements. Contingency Procedure to be regularly
updated and monitored by SLDC/RLDC
SLDC through respective SEBs/Discoms shall formulate and
implement state-of-the-art demand management schemes-
roatational load shedding/demand response (which may include
lower tariff for interruptible load) etc. SLDC to furnish periodic
report to CERC.

42
Demand Management(5.4.2(e)(f)(g)(h))
Interruptible load in four groups:
Scheduled load shedding/power cuts
Unscheduled load shedding
UFR/df/dt loads
SPS loads
RLDC may direct to decrease drawal in contingency---SLDCto send
compliance report
SLDC may direct SEB/Discom/bulk consumer to curtail drawal and
monitor
RLDC shall devise standard, instantaneous, message formats
Congestion requisite load shedding or generation backing down .
Implementation as per CERC ( Measures to relieve congestion in real
time operation), Regulations, 2009

43
Periodic Reports (5.5)

weekly report by NLDC (put on weekly report by RLDC (put on


website): website):
Performance of national/integrated Frequency and voltage profiles
grid Major generation & transmission
daily report by RLDC (put on outages
website): Transmission constraints
Performance of national/integrated Instances of persistent/significant
grid non-compliance of IEGC
Wind power injection Instances of congestion
Instance of inordinate delay in
quarterly report by RLDC : restoration
system constraints, reasons for not Non-compliance of instructions of
meeting the requirements, security SLDCs by SEB/Discom
standards & quality of service
actions taken by different persons RLDC shall provide
persons responsible for causing the information/report to RPC for
constraints smooth operation of ISTS

44
Operational Liaison (5.6)
Introduction
a) requirements for the exchange of information in
relation to Operations/Events on the total grid system
which have had or will have an effect on:
National grid
the regional grid
the ISTS in the region
the system of a User/STU
(the above generally relates to notifying of what is expected to
happen or has happened and not the reasons why)
b) Operational liaison function is a mandatory built-in
hierarchical function of the NLDC/RLDC/SLDC/Users
to facilitate quick transfer of information to operational
staff

45
Procedure for Operational Liaison
Procedure for Operational Liaison
a) Operations and event on the regional grid
before carrying out any operation, RLDC will inform User/SLDC/CTU whose
system will be affected
immediately following an event, RLDC will inform the User/SLDC/CTU with
details of what happened but not the reasons why
RLDC to NLDC if other region is going to be affected
immediately following an event, NLDC would keep all RLDCs informed
b) Operations and events on a User/STU system
before carrying out any operation that will affect regional grid, constituent
shall inform RLDC with details
RLDC to NLDC if other region is going to be affected
immediately following an event, the User/SLDC shall inform RLDC with
details but not the reasons why
immediately following an event, NLDC would keep all RLDCs informed
Prolonged Forced outages monitored at RPC level. RPC shall send a
monthly report to CERC

46
Outage Planning (5.7)
Introduction
a) procedures for preparation of outage schedules for the
elements of the National/Regional in a coordinated and
optimal manner and the balance of generation and
demand
b) generation output and transmission system should be
adequate after taking outages into account to achieve
security standards
c) annual outage plan for the financial year shall be prepared
by RPC Secretariat and reviewed during the quaterly and
monthly basis. ROR, wind & solar power to be extracted to
maximum

47
Outage Planning Process

proposed outage programmes by all concerned (30th Nov)

draft outage programme by RPC Secretariat (31st Dec)

final outage programme by (31st Jan)


monthly review quarterly review

Nov Dec Jan Feb Mar next financial year


Review by RPC Secretariat:
adjustments made wherever
found to be necessary in
coordination with all parties
concerned

48
Outage Planning (5.7.4)
In consultation with NLDC/RLDC
In Emergency RLDCs may conduct studies before
clearance
NLDC/RLDC are authorized to defer
- grid disturbance
- system isolation
- partial black out in a state
- any other critical event
Latest detailed outage plan updated
Each user, CTU and STU shall obtain one final approval
from RLDC
RPC shall submit quarterly, half yearly reports to CERC
indicating deviations

49
Recovery Procedures (5.8)

develops Detailed plans/procedures for


RLDC restoration of partial/total blackout
regional grid
consultations reviewed/updated annually
Concerned
Constituents
RPC secretariat
develop

Mock trials once


Detailed plans/procedures for
every 6 months
restoration of partial/total blackout
DG sets to be tested
on weekly basis- reviewed/updated annually
quarterly report to be
sent to RLDC 50
Recovery Procedures (contd...)
List of the following shall be available with
NLDC/RLDC/SLDC:
generating stations with black start facility
inter-state/regional ties
synchronising points
essential loads to be restored on priority
During restoration following blackout, RLDC
authorized to operate the grid with reduced
security standards for v & f
all communications channels for restoration shall
be used for operational communications only till
grid normalcy is restored
51
Event Information (5.9)
Introduction
reporting procedures in respect of events to all Users,
STU,CTU RPC secretariat, NLDC/RLDC/ SLDC
Responsibility
RLDC/SLDC shall be responsible for reporting events
to the Users/SLDC/ STU/CTU RPC secretariat/ NLDC
/RLDC

Users/ STU/CTU /SLDC shall be responsible for


collection and reporting all necessary data to
NLDC/RLDC and RPC secretariat for monitoring,
reporting, and event analysis

52
Reportable events (5.9.5)
i Violation of security Standards
ii Grid indiscipline
iii Non-Compliance of RLDCs instruction
iv System islanding/ system split
v Regional black out/partial system black
out
vi Protection failure
vii Power system instability
viii Tripping of any element
ix Sudden load Reduction 53
Reporting Procedure
NLDC
weekly written report
of events
Users/STU/
RLDC CTU/SLDC
written report
of events
Form of written reports:

i) Time and date vi) Duration of interruption


ii) Location vii) Recording System
informations
iii) Plant or equipment directly viii) Sequence of trippings with
involved time
iv) Description and cause of event ix) Remedial Measures
54
v) Antecedent Condition
6. Scheduling & Despatch Code
a) demarcation of responsibilities
b) procedure for scheduling & despatch
c) Reactive power and voltage control
mechanism
d) complementary commercial mechanism
(Annexure-I)

55
OBJECTIVE
Procedure for submission of Capability declaration
Procedure for submission of requistion/ drawal schedule by regional entities
Real time despatch/drawal instructions
Rescheduling
Commercial arrangement for UI/Reactive
Scheduling of wind/solar on 3 hourly basis
Appropriate Metering

SCOPE
Discoms Power
Exchanges ISGS

NLDC RLDC SLDC


Other Wind/Solar
SEBs/STUs concerned generators
Demarcation of responsibilities (6.4)
Role of RLDC
Scheduling of CGS (Except where
full share is allocated to host state)

Schedul
Scheduling
RLD ing of
of GS GS
connected C
both to
connect
ISTS and ed to
state grid ISTS
and home
state is less
then 50%

Scheduling of UMPP
57
Demarcation of responsibilities (6.4.4)
SLDC
Scheduling
Permitting drawal from
Open Access ISGS

SLDC
Regulating
net drawal

Scheduling and
6.4.8 Demand despatching
Estimation in Demand
coordination with Regulation
STU/Discoms 58
Demarcation of responsibilities (6.4.6/7)

System of each regional entity shall be operated as


notional control area
Scheduled drawal + Regional entity would
Bilaterals on day regulate its own
ahead basis generation and load so
that drawals are
close to schedules

Regional entity would Endeavour


for UI=0 at F<49.7 Hz.
At F< 49.5 Hz ,automatic demand
management scheme/manual
demand disconnection 59
Regional Entities Agreements
RLDC RPC
State1 State2 Joint/bilateral agreements for ISGS project1
State3 States share in ISGS projects
scheduled drawal pattern
ISGS project2
State4 tariffs
payment terms
ISGS projet3
State5

CTU Long Term, MTOA RLDC/SLDC

60
Declare DC 6.4.9 Role of ISGS/ DC during
Faithfully
Penalty : Capacity Generating Station Peak Hours
Charges reduced > Other
Planned Outages Hours
OCC of RPC
When F<49.7 ,
When maximize generation
F>50.2 ,
backdown
generation ISGS
Deviation
from
Schedule
Generate as per Proper UI
despatch schedule Operation
advised to them and
61
by RLDC Maintenance
Role of CTU

Weekly Install
Readings CTU SEMs

Constituents
where
SEMs
are CEA (Installation and operation of
located Meters ) Regulations 62
Demarcation of responsibilities
Role of RLDC
Periodically review UI
Report

RLD 15 min
C drawal
MS RPC and
injection

Gaming by ISGS

105 % in one block of 15 minutes and


101% over a day no gaming 63
Role of RPC

REA, UI, Outage


Var RPC Planning
Accounting

64
Scheduling of Role of NLDC
Inter-Regional
Power Exchanges HVDC
Settings

Trans-National
Exhange of
Power NLDC
Scheduling on
Inter Regional
Links .
Collective
Transaction Energy
Scheduling accounting
on IR Links-
65
with RLDC
Scheduling & Despatch Procedure (6.5)
List of ISGSs and beneficiaries
all ISGS whose output is shared by more than state
shall be listed on RLDC and SLDC websites
the station capacities and allocated/contracted shares
of different beneficiaries shall also be listed out
State entitlement:
Thermal ISGS:
(foreseen ex-power plant MW capability for the day) X
(states share in the stations capacity)
Hydro ISGS:
(MWH generation capacity for the day) X
(states share in the stations capacity)

66
Preparing final schedule

ISGS
station-wise revision final Despatch
MW/MWH Despatch Despatch schedule
capability schedule schedule starts

RLDC
12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1
AM noon PM

station-wise W/MWH
entitlement revision Drawal
required net final schedule
Drawal Drawal Drawal starts
schedule schedule schedule

SLDC
67
Scheduling of Collective Transaction 6.5.5
Power
Exchanges 3. Check for Congestion
1. List of , reworked as per CERC
Interfaces, directive
Control areas 2. Interchanges on
Interfaces, Control
areas

NLDC
4.
Consultation
6.
Individual
Transactions

SLDC 7. Schedule
individual
RLDC
transaction

5.Schedule
at respective 68
periphery
Revision of schedules during the day
any State may revise:
drawal schedule from any/all ISGS within their entitlementsto be
effective from 6h time block)
an ISGS may revise:
capability on account of forced outage. (to be effective from 4th
time block)
Revision (to be effective from 6h time block)
RLDC can revise:
In the interest of better system operation (to be effective from 4th
time block)
Shall formulate procedure for meeting contingency

69
Other Contingencies
In the event of bottleneck in evacuation of power,
RLDC may revise the schedules which will be
effective from 4th time block and for 1-3 time
blocks schedules would deemed to have been
replaced by actual.
Similarly for entire period of grid disturbance,
schedules will be replaced by actual
No revision if change in previous
schedule/capability is less than 2%.

70
Other Contingencies

For every change in generation schedule there


would be corresponding change in drawal schedule

Procedure for recording the communication


regarding changes in schedules taking into account
to be developed by CTU

71
Final schedule & Documentation
RLDCs final implemented schedule:
shall be the datum for commercial accounting
shall be open for 5 days for verification/correction
RLDC shall properly document the following:
station-wise foreseen ex-power plant capabilities
advised by the generating stations
the drawal schedules advised by beneficiaries
all schedules issued by RLDC
all revisions/updating of the schedules

72
Reactive Power & Voltage Control (6.6)
VAR Charges under Low
VAR Charges under High
Voltage
voltage

EHV grid EHV grid

Q Voltage: < 97% Q


Q Voltage: > 103% Q

Beneficiary1 Beneficiary2 Beneficiary1 Beneficiary2


VAR charges
VAR charges
Pool Account
Pool Account

73
VAR charges settlement
No VAR charges for its own lines emanating directly from ISGS

VAR charges at the nominal paise/KVArh rate as may be specified by


CERC and will be between beneficiaries and POOL (Present rate is
10.0 p/kvarh with escalation of 0.5 p/kvarh every year)

RLDC may direct Regional entity to curtail VAR drawal/injection for


safety and security of grid or safety of equipment

Beneficiaries to minimise injection/drawal of VAR if voltage goes


beyond + 5%.

ICT taps may changed as per regional entity request to RLDC

Tap changing (400/220 kV)and switching in/out of line reactors


(400kV) shall be carried out as per RLDC instruction.

74
Annexure-1 (6.1 d)
Complementary Commercial Mechanisms

75
Generation Cost

Capacity charge + Energy charge


beneficiary1
UI
UI
Settlement UI ISGS
UI System Full
reimbursement
for generation as
beneficiary2 per the
Capacity charge + Energy charge generation
schedule

76
Weekly bills & penalty (12, 13, 14)
UI
UI bills UI payment Settlement
RLDC System
Constituents
RPC VAR bills VAR payment Pool
Account
monthly payment
status

payment defaults CERC

payment within 10 days from date of billing


simple interest @ 0.04% per day to constituent for delayed payment
beyond 12 days.
77
Regional Energy Accounting
Sun
Mon
15-minute block
Tue
SEM readings for a week
Wed
Thu
Fri
Weekly raw Sat
ISTS Sun
Connections SEM data
Mon
Tue
Weekly
Wed
UI and
Thu
Fri VAR
Constituents Account
Sat RLDC
Sun
REA Mon
Tue
Monthly (6th):

RLDC to tabulate UI account and REA in RPCs CC 78


meeting on a quarterrly basis for audit by the later.
Complementary Commercial
Mechanism
Money left in VAR account shall be utilized
for training of SLDC operators and other
similar purposes
Thank you!