Project Management and Control
Project Management and Control
AND CONTROL
Project tracking
Prioritizing monitoring
We might focus more on monitoring
certain types of activity e.g.
Critical path activities
Activities with no free float if
delayed later dependent activities
are delayed
Activities with less than a specified
float
High risk activities
Activities using critical resources
2
Getting back on track:
options
Renegotiate the deadline if not possible then
Try to shorten critical path e.g.
Work overtime
Re-allocate staff from less pressing work
Buy in more staff
Reconsider activity dependencies
Over-lap the activities so that the start of one activity
does not have to wait for completion of another
Split activities
3
Exception planning
Some changes could affect
Users
The business case (e.g. costs increase
reducing the potential profits of
delivered software product)
These changes could be to
Delivery date
Scope
Cost
In these cases an exception report is needed
4
Exception planning -
continued
First stage
Write an exception report for sponsors (perhaps
through project board)
Explaining problems
Setting out options for resolution
Second stage
Sponsor selects an option ( or identifies another option)
Project manager produces an exception plan
implementing selected option
Exception plan is reviewed and accepted/rejected by
sponsors/Project Board