6 - Time Management
6 - Time Management
Activity Planning
Introduction 1
The unit will cover several methods
Precedence analysis
Gantt Charts
PERT / CPA
On Arrow Networks
Precedence Networks
Introduction 2
Activity Planning will help to:
ensure that the appropriate resources will be
available precisely when required
avoid different activities competing for the same
resource at the same time
produce a detailed schedule showing which staff
carry out each activity
Produce a detailed plan against which actual
achievement may be measured
produce a timed forecast
re-plan the project during its life to correct drift from
a target
Precedence analysis
Must be done before an activity plan can
be produced
Reviews the activities that are to be
carried out
Decides what activities must be carried
out before particular activity can start
Gantt Charts
Developed by Henry Gantt, around 1917
Gantt charts are easy to use and produce
They are very useful for use on less
complex projects
Commonly used due to there simplicity
Gantt charts are easily understood and
easy to read
Gantt Charts
2 d
a
e 5 g
b End
Start 1 3 5
h
c
f 5
4
Terminology
Activity
A specific task, uses resources takes time to
complete
Event
The result of completing an activity
Events use no resources
They are instances in time, points on the
network, conditions of a system that can be
recognised
Terminology
Network
The combination of all activities (often drawn
as lines) and events (often drawn as nodes at
the beginning and end of each line) defines the
project and the activity precedence
relationship.
Arrow heads placed on the lines indicate the
direction of flow. Before and an event can be
realised all the activities that immediately
precede it must be completed
Terminology
Path
The series of connected activities (or
intermediate events) between any two events
in a network
Critical
Activities, events, or paths, which, if delayed,
will delay the completion of the project
A projects critical path is understood to mean
that sequence of critical activities (and critical
events) that connect the projects start event
to its finish event
Terminology
Critical Path:
The longest time path through the task network;
The "longest" path (in terms of time) to the completion
of a project. If shortened, it would shorten the time it
takes to complete the project.
Network syntax
Time moves from left to right
Nodes are numbered sequentially
A network may not contain loops
Precedents are the immediate preceding
activities
Network syntax
Time moves from left to right
Nodes are numbered sequentially
a b
1 2 3
Network syntax
A network may not contain loops
d 4
c
a
1 2 3
b
This is not allowed
Network syntax
Precedents are the immediate preceding
activities
3
On Arrow Networks
What not to do
c
a 2 4
start 1
b
d 5
3
e
6
On Arrow Networks
A better way
c
a 2
start 1
b
d
3
e
On Arrow Networks
It is then less confusing that c & d go to
the same event but what about e & f ?
c f
a 2 4 6
start 1
b d
e
3 5
On Arrow Networks
The completed on arrow network .
c
a 2 4 f
start 1
b d 5 end
e
3
On Arrow Networks
Another on arrow network to draw
TasksPrecedence Time
a - 6 weeks
b - 4 weeks
c a 3 weeks
d b 4 weeks
e b 3 weeks
f - 10 weeks
g e,f 3 weeks
h c,d 2 weeks
On Arrow Networks
The network with activity times added
2 c=3
a=6
Event
number
Earliest Latest
date date
Slack
Event
Event numbers
3 6
1 4
5
Timed activities
2
C=3
A=6
3 H=2 6
1 D=4 4
B=4
E=3
G=3
F=10 5
Forward pass
2
6
C=3
A=6
3 H=2 6
1 D=4 4
B=4 4 13
0 9
E=3
G=3
F=10 5
10
Backward pass
2
6 8
C=3
A=6
3 H=2 6
1 D=4 4
B=4 4 13 13
0 0 7 9 11
E=3
G=3
F=10 5
10 10
Event, Slack and Activity Float
2
6 8
2 C=3
A=6
3 H=2 6
1 D=4 4
B=4 4 13 13
0 0 7 9 11 0
0 3 2
E=3
G=3
F=10 5
10 10
0
The Complete On Arrow Network
2
6 8
2 C=3
A=6
3 H=2 6
1 D=4 4
B=4 4 13 13
0 0 7 9 11 0
0 3 2
E=3
G=3
F=10 5
10 10
0
Precedence Networks
Precedence network also known as
Activity on Node
Becoming more common as it is used by
many project planning software packages
Often preferred by project managers
Slack Time:
The amount of time a task can be delayed before
the project finish date
Total slack can be positive or negative. If total slack is
a positive it indicates the amount of time that the task
can be delayed without delaying the project finish date.
If negative, it indicates the amount of time that must be
saved so that the project finish date is not delayed.
Total Slack = Latest Start - Earliest Start
Precedence Networks
a d
g
Start b e End
c f h
This is the same network drawn as an On
Arrow network
2 d
a
e 5 g
b End
Start 1 3 5
h
c
f 5
4
Precedence Networks
Draw the following as an Precedence network
Tasks Precedence Time
a - 5 days
b - 4 days
c a 6 days
d b 2 days
e b 5 days
f c,d8 days
Precedence Networks
The completed Precedence Network
a c
Start d f End
b e
The same network drawn as an On Arrow
Network
c
a 2 4 f
start 1
b d 5 end
e
3
Precedence Networks
Another on precedence network to draw
TasksPrecedence Time
a - 6 weeks
b - 4 weeks
c a 3 weeks
d b 4 weeks
e b 3 weeks
f - 10 weeks
g e,f 4 weeks
h c,d 2 weeks
This is the same network drawn as an On
Arrow network
2 C=3
A=6