BMB & CKD MCD Va
BMB & CKD MCD Va
BMB & CKD MCD Va
MCD Handover will be accepted when all systems are commissioned and accepted by offshore disciplines with
TAs approval prior final acknowledgement project handover by POD Manager
Expected to start commissioning BMB on Sep 8, 2012 (7 days prior mobilized date of Drilling)
HUC
Drilling
Sep 8
Flow Line
Installation
Sep 15
Feb
2013
Pedestal Crane
Electrical
Auxiliary Generator
UPS Power
Navigational Aid
Emergency Lighting
Finding Gaps;
Ineffectiveness of communication between Project/Design Engineers, F&E (TA) and End Users
to review all problems in the past, lesson learn and/or additional improve requirements to be
accepted and implemented in the project.
Package equipment documents / drawings are not available and/or provide enough info to review
prior FAT/SAT subsequently no specific items / functions that need to be concentrated.
Function and authorization of PMT QA/QC (Project or TA representative?)
Improper workflow and response timeframe of Design/TA Engineers on the design issue.