Construction Failures-Harbour Cay Condominium

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 62

CONSTRUCTION FAILURE

Investigation of construction failure of

HARBOUR CAY
CONDOMINUM
at cocoa beach florida

PRESENTED BY:ROSHAN PRAJAPATI ( PT401716

CONSTRUCTION FAILURE

OVERVIEW
The investigation of collapse of a five storey
reinforced concrete flat plate structure under
construction is presented
Most probable cause of the failure was
insufficient punching shear capacity in 5th floor
slab to resist construction loads.
Two factors contributed the low punching shear
capacity,

At design stage
Smaller slab thickness

At construction stage
Chairs having insufficient height to support top reinforcement

Content
INTRODUCTION

INTRODUCTION

Background
Type of
structure
Use of
building
Nature of
collapse

Calamities
Inspection

Five storey flat plate RCC


structure
RESIDENTIAL-Under construction
During the placement of concrete
for roof slab, the entire structure
collapsed vertically with each
floor slab breaking away from the
columns and landing on the
ground floor
11 workers died, 23 injured
OSHA(Occupational safety and health

Documents supplied by OSHA


field office to NBS for analysis
Construction documents

DESCRIPTION OF THE STRUCTURE


AND COLLAPSE

BUILDING PLAN

Structure Details

G+5 RCC flat Plate construction

Overall dimensions: 242 ft.(74mt.) x 58ft.(18mt.)

Formwork system used: Flying Forms

Concrete grade: 4000 psi(27.60 Mpa)

Grade of steel: Deformed bars ASTM grade 60

Live load

ROOF-20 psf(0.96 Kn/m2)


FLOOR- 40 psf(1.91 kn/m2)
PUBLIC BALCONY- 60 psf (2.87 kn/m2)
STAIRWAYS- 80 psf(4.78 kn/m2)

Structure Details
Column

size:

254 mm x 457 mm
254 mm x 305 mm(on grid line A and K)
203 mm x 305 mm(exterior of stairwells)

Slab

Thickness:

Floor slabs 203 mm


Balcony slab varied from 184mm to 165mm
at the edge
Walkway slab 191 mm
The elevator tower was structurally detached
from the building

Structure Details

The elevator tower was structurally detached


from the building.
At the foundation Lvl, the columns were
supported by pile caps containing two to nine
piles each
The exterior caps were connected by
continuous wall footings
Non Load bearing concrete masonry
construction was used for the exterior walls of
the building.

CONSTRUCTION METHODOLOGY

CONSTRUCTION METHOD

FALSEWORK SYSTEM USED- FLYING FORMS

FLYING FORMS

CONSTRUCTION METHOD

CONSTRUCTION METHOD

CONSTRUCTION
METHOD

CONSTRUCTION METHOD

CONSTRUCTION METHOD

RESHORE
LAYOUT

CONSTRUCTIO
N METHOD

COLLAPSE

EVENT

The collapse occurred at approximately 3:00


p.m., on march 27,1981.

It appears to have been triggered by a failure in


the fifth story slab in the center position of the
building, and propagated straight down to the
ground.

As a result, 11 workers died, and another 23


were injured.

The stage of construction at


time of collpase

COLLAPSE

COLLAPSE

COLLAPSE

Location of workers
in building at time
of collapse

SITE INVESTIGTION

BASED ON SITE VISIT


Types of high chairs used

5.75IHC(146mm)(Individual high chairs)


for one way top r/f in middle strips)
4.25IHC
for two way top r/f in the column strips

The use of 5.75 chairs with 5 support bars


would result in a clear cover of 0.88 to
1.12(22-29mm) at middle strips to the top.
This exceeds the 0.75 (19mm) cover specified
in structural drawings but it is within the 9,5mm
tolerance limit.

BASED ON SITE VISIT

At the column strips, the use of 4.25(108mm)


chairs where slab is 8(203mm)thick would
result in a net cover ranging from 41mm to
54mm for bar sizes 5 and 8.
During the investigation , The calculated
effective depth at a column where the top r/f in
the slab consists of 8 & 9 is 5.3(135mm)
which are less than required effective depth
6.3(160mm) thick.
Less effective depth is provided.
The increase in eff. Depth by 1 increase the
critical cross sectional area to resist the
punching shear by 25%, which, in turn,

BASED ON SITE VISIT

BASED ON SITE VISIT

BASED ON SITE VISIT

The failure mode appeared to be of the


punching shear type, because the slabs had
broken away from the columns at the slabcolumn interface.
There was no evidence that sideways or
overturning of the building had occurred.
Measurements of the outside dimensions of
selected column and slab sections indicated
conformity with the structural drawings.
The reinforcing steel in some first story columns
did not meet the clear spacing requirements of
ACI code.

BASED ON WORKER
INTERVIEW

It was not possible to establish the exact layout


of reshores at the time of collapse.
Floor

Amount of reshores

4th

Full

3rd

Not enough

2nd

Not enough

1st

Few exterior reshores


in place

Extensive cracking occurred in floor slabs when


supporting formwork was removed.

BASED ON WORKER
INTERVIEW

The concrete produced by the on site batch


plant was non uniform in terms of consistency
and finishability.

Description of the collapse by workers on the


site indicate that the most probable origin of the
collapse was in fifth floor slab in the vicinity
beneath where the roof concrete was being
placed.

LAB INVESTIGTION

OBJECTIVE

The objective of the laboratory investigations


was to establish the strength of concrete in the
structure at the time of collapse.

The approach used involved gathering data


from site and preparing concrete mixtures
representative of the inplace concrete.

TESTS CONDUCTED

INFERENCES FROM
INVESTIGATION

There was insufficient documentation of the


quantities of ingredients used in each batch of
concrete.

The compressive strength of cored taken from slab


sections satisfied the ACI code strength criteria for
a specified strength of 4000 psi(27.6 Mpa).

The compressive strength of cores taken from


column sections were lower than the strength of
slab cores, and the average strength of the cores
from the fifth column did not satisfy the ACI code
criteria for the specified strength.

INFERENCES FROM
INVESTIGATION

Core strength values had high variability.

Petrographic analyses of core samples revealed that


the volumetric proportions of paste and aggregate
were in agreement with the stated mix designs. The
proportions, however, did show high variability.

The computed cement contents based on the


chemical analysis of core samples were lower than
stated in the mix designs. Since the low values are
inconsistent with the core strengths, it was
concluded that the calculated cement content
values were imprecise.

INFERENCES FROM
INVESTIGATION

The strength development curves of the three


mixes prepared by NBS were consistent with the
average value of core strengths.

The tensile strength characteristics of the NBS


mixes were typical of normal weight concrete.

The reinforcing steel was grade 60.

COLLPASESTRUCTURE ANALYSIS

EFFECT OF SHORING AND


RESHORING

Regardless of the shoring scheme used, as


construction progresses upward, the building is
subjected to unidentical cycle of loading and
unloading which produce residual forces in the
structure.
At certain stage of construction, when a new floor is
cast, the forces introduced combine with the residual
forces to produce the highest load in particular slab
The magnitude of this load depend
on the shoring system used
stiffness properties of the partially matured concrete structure
amount of precompressions in the reshores where they are

first installed

EFFECT OF SHORING AND


RESHORING IN HARBOUR CAY

In this case, flying forms were used.


At the time of the collapse, three stories were
reshored with wood posts.
A flying form is an integrated system which
incorporates shores and formwork into a large
unit capable of forming several bays at a time.
The method of replacing flying forms with
reshores results in unloading a tier of bays at a
time( 2 or 3 bays in this case), allowing the floor
above that area to deflect under its own weight
before reshores are installed.

METHODOLOGY FOR
ANALYSIS

POSSIBLE SOURCES OF
LOADING AT TIME OF COLLAPSE

The self weight of structure

The weight of fresh concrete in the roof slab

The weight of the shoring system

The weight of the construction workers,


equipments and materials

Wind

Impact

RESULTS

RESULTS

DESIGNING OMISSIONS

There was no calculations to indicate whether


the deflection or minimum thickness provisions
of the code were met.

There was no calculations to indicate whether


the punching shear and beam shear provisions
of the code were met.

There were no checks to determine if the


column reinforcement would satisfy the
necessary spacing requirements specified by
the code

DESIGNING OMISSIONS

The steel area calculations for the flexural


reinforcement in the slabs were based on ASTM
Grade 40 steel. This is at variance with the
grade 60 steel specified in the structural
drawings.

The effective depth of the slab in flexural


reinforcement calculations was not defined
explicitly but appeared as part of a constant
multiplier of computed moments. Back
calculations showed that the designer used the
value of around 6.3 inch (160 mm) for the
effective depth in steel area calculations.

INFERENCES FROM ANALYSIS

Flat plate structures are inherent weak in shear at


the slab-column connection and, when punching
shear failure occurs, the structure is highly
susceptible to progressive collapse unless it is
adequately designed and carefully constructed.

The use of lower individual chairs for supporting


the top layer reinforcing bars in the column strips
than required to provide the 0.75 (19mm) cover
called for in the structure drawing reduced the
effective depth and punching shear capacity of
slab.

INFERENCES FROM ANALYSIS

Omission in the slab design of a check for


punching shear resulted in an 8 slab which was
shallower than needed to safely support the
design loads for the complete structure.

This reduced the margin of safety such that the


slab had insufficient reserve strength to
accommodate the use of 4.25(108 mm)
individual high chairs within the column strips.

COLLAPSE

The structure analysis showed that failure of the


slab most likely initiated at column G-2.
The analysis also showed that the shear
stresses at many column locations on the fifth
floor exceeded that nominal shear strength.
Once punching shear failure had initiated at
column G-2, it propagated throughout the slab
causing the total collapse of fifth floor, which, in
turn, caused the successive collapse of the
lower floor slabs.

LESSONS LEARNED.

LESSONS LEARNED..

A punching shear strength check is critical to the


success of a flat-slab, since punching shear is the
most common failure mode of concrete slabs.

Minimum depth of a flat-slab must be checked to


assure proper strength and acceptable deflections.

Reinforcing bars, both at the top and at the bottom


of the slab, should be placed directly within the
column periphery to avoid progressive collapse.
This can easily be accomplished routinely in all
flat-slab jobs at no additional cost at all.

LESSONS LEARNED..

Proper construction control must be provided in


the field, including design of formwork by
professionals. This must include shoring and
reshoring plans, procedures, and schedules, with
data on minimum allowable stripping strength of
the concrete.

When there are failure warning signs of any type


on a construction site, work must stop. All aspects
of the project must be carefully evaluated by
experienced professional help. Immediate
evacuation of the structure must be considered.

LESSONS LEARNED..

Redundancy within structural design is essential


to prevent progressive collapse.

Before the removal of shoring, the concrete


strength should be ascertained.

CONCLUSION

CONCLUSION
The Harbour Cay Condominium collapse

demonstrates
the
consequences
of
improper
design
and
construction
procedures.
A punching shear failure on the fifth floor
initiated a progressive collapse of the
entire structure.
Punching shear calculations were omitted
by the structural engineer when the
structure was designed. Reinforcement
bars were placed too low in the concrete
slabs, which reduced the effective depth

CONCLUSION
Warning signs of a potential failure were

brought to the attention of supervisors


and the structural engineer but were
basically ignored.
The Harbor Cay disaster could have easily
been prevented had simple design checks
and careful construction techniques been
performed.

REFERENCES
Norbert J. Delatte Jr., BEYOND FAILURE,

JULY 2008
H.S.Lew,
N.J.Carino,
S.G.Fattal
and
M.E.Batts, Investigation of construction
failure of harbour cay condominium in
cocoa beach, Florida, National Bureau of
standards,August,1982.
Formwork failure: cases and causes, the
master builder, march 2012

THANK YOU

You might also like