Budgeting and Cost Management: Civil Engineering Management B

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 28

Budgeting and Cost

Management
Civil Engineering Management B

Session Objectives
Includes:
The estimating of costs and the setting of an agreed budget
The initial cost estimate is developed in line with the scope,
schedule and resources
The budget is phased over time to predict expenditure thus
allowing a cashflow forecast to be developed.
Cost management is the monitoring and control of actual
expenditure against the budget/cashflow forecast.
By comparing actual cost against the expenditure profile,
trends can be identified and corrective action taken to
minimise adverse variances.
Such reviews form the basis of Earned Value management
which is covered in a later lecture.

People aspects
Pay
hourly rate basic/overtime

Subsistence
People overhead

Pension
National Insurance contributions
Holiday
Sick pay
Equipment car/phone/office
Overheads typically 100-250%

Equipment aspects
Rate e.g. hourly/daily/weekly
Hired/own ~ equivalent hire
charge
Establishment charge

Equipment overhead
Typical plant overhead 5-10%
(E.g. fuel, oil, cleaning)

Material aspects
Unit cost m, m2, m3;
mass (kg/tonnes)
Delivery charge
Material overhead
Wastage/breakage/theft
Up to 5% typically 2%

Cost of doing the work

Contractors own resources

Using a Subcontractor

Equipment
+ O/H

Fixed cost
but..remeasurable

People
+ O/H

Materials
+ O/H

People
+ O/H

Equipment
+ O/H

Materials
+ O/H

Cumulative Cost (k)

Cumulative cost curve

Time

Cumulative Cost (k)

Cumulative cost curve


Based on
ES
Based on
LF
Cost
Envelope
Time
Non-critical tasks

Cumulative Cost (k)

Cumulative cost curve


Contractor
Cost

Payment to
Contractor
(Employer cost)
Time

Cumulative cost curve


Cumulative Cost (k)

B. Profit
Contractor
Cost

A. Break even
point
C. Borrowing
Payment to
Contractor
(Employer cost)

Time

The Cost project


Developing a cashflow from a Gantt chart
Task

Precedence

Duration
(Weeks)

Estimated
Cost
( x 1000)

Follows Start

50

Follows A

100

Follows B
Precedes Finish

200

Follows A

100

Follows B and D

50

Follows A

50

Follows F

50

Follows A
Precedes Finish

100

Follows E and G
Precedes Finish

10

300

The Cost project

Using the Cost project Gantt, determine


the cost for each four week period
Accumulate the costs and plot the
cumulative cost against the duration,
assuming all costs occur at the end of
each four week period
This could then be repeated for all late
finishes

Determine the cost for each four


week period
Task

50

100

50
50
33

100

100
50
17

25

Precedence

Estimated
Cost
( x 1000)

Follows Start

50

Follows A

100

Follows B
Precedes Finish

200

Follows A

100

Follows B and D

50

Follows A

50

Follows F

50

Follows A
Precedes Finish

100

Follows E and G
Precedes Finish

10

300

50x4/6 = 33.333

50
33

Duration
(Weeks)

Take as 33
17

50-33=17

25
60

120

120

Cost (k)

50

333

192

108

77

120

120

Cu Cost (k)

50

383

575

683

760

880

1000

Cumulative cost curve


Cumulative cost (k)

1000 -

X
X

800 -

X
X

600 -

400 -

200 X
I
4

I
8

I
12

I
16

Time (weeks)

I
20

I
24

I
28

Determine the cost for each four


week period

50

100
50

50
33

17

33
25

100

100

120

100
120

17
25
60

Cost (k)

50

50

183

75

102

220

320

Cost (k)

50

100

283

358

460

680

1000

Cumulative cost curve


Cumulative cost (k)

1000 -

X
X

800 -

X
X

600 -

X
X

400 -

X
X

200 X
I
4

X
I
8

I
12

I
16

Time (weeks)

I
20

I
24

I
28

Costs and incomes something to


work on

Cumulative cost curve


Cumulative Cost (k)

B. Profit
Contractor
Cost

A. Break even
point
C. Borrowing
Payment to
Contractor
(Employer cost)

Time

An Estimating sum
542m of 150mm diameter drain are to be laid at an
average depth to invert of 1.675m.
The construction details:

Backfill with excavated


material
Pipe Bedding

450mm

600 mm

An Estimating sum
The Estimator has estimated:
Output is expected to be 22m per 8 hour day using:
Hired JCB + Operator at 34.70p per hour
Three own operatives at 7.80p per hour
Compactor at 25 per day + Trench Supports at 73 per day
150 diameter pipes at 14.20p per m + 2% wastage
Pipe bedding at 28.00 per Tonne + 5% wastage
Disposal of surplus excavated material is included
The Company has determined:
Own labour overhead is 120%
Hired equipment overhead is 4%
Material overhead is zero but wastage is to be included.
Site overheads are 8% and Head Office overheads, risk and profit are 13%
Determine a rate per m for the installation of this 150mm diameter drain

An Estimating sum
Estimated rate for 150 drain

542
Duration =
= 25 days
22
People
3 operatives x 8hrs x 25 x 7.80 = 4680.00
O/H 3 ops. x 8hrs x 25 x 7.80 x 1.20 (120%) = 5616.00
total labour = 10296.00

An Estimating sum
Estimated rate for 150 drain (continued)
Equipment
JCB 1 x 8 x 25 x 34.70 = 6940.00
Compactor 1 x 25 x 25.00 = 625.00
Trench supports 1 x 25 x 73.00 = 1825.00
Subtotal equipment = 9390.00
Overhead at 4% = 375.60
total equipment = 9765.60

An Estimating sum
Estimated rate for 150 drain (continued)
Materials
Pipes 542m x 14.20 x 1.02 (wastage) = 7850.33
Pipe bedding
Volume = 542 x 0.6 x 0.45 = 146 m 3
Pipe volume
DDT pipe = 10 m3
150
= 136 m3
x 542= 10m
4
At 1.8 T/m3= 136 x 1.8 = 245T
245T x 28.00 x 1.05 (wastage) = 7203.00
total materials = 15053.33
2

An Estimating sum
Estimated rate for 150 drain (continued)
Sum up (People, Equipment and Materials) = 35114.93
8% site overhead = 2809.19
New total = 37924.12
13% head office overhead = 4930.14
Total = 42854.26
Divide Total by 542m for rate per m = 79.07
Note: Normally done using a spreadsheet

An Equipment rate sum


A Company is considering buying and owning an excavator rather than
hiring which they are doing at present at a rate of 39.00 per hour including
operator. Enquiries have indicated that:
The cost of purchase is 60,000 and the resale value after 3 years is
12,000.
Fuel is estimated to cost 4,700 per annum and miscellaneous disposals
are to be costed at 10% of fuel cost. A service cost of 900 per annum is to
be included and it is anticipated that there may be three breakdowns/repairs
per year estimated to cost 600 each. 3000 is to be included for one
major repair during the operating life.
Utilisation is expected to be 80% and a 5 day 8 hour 47 week working
period is expected.
A plant overhead of 7% is to be recovered.
The own operator is to be charged at 7.50per hour + 150% labour
overhead.
Determine an equivalent hire rate and comment on the proposal to
purchase this item of plant.

An Equipment rate sum


Consider three year life
Capital
Cost of purchase = 60, 000.00
Residual value = 12, 000.00
Capital is = 48, 000.00

An Equipment rate sum


Consider three year life
Running costs
Annual fuel = 4, 700.00
Misc.
= 470.00
Service = 900.00
B.downs (3) = 1, 800.00
7, 870 x 3 = 23, 610.00
major repair 3, 000.00
Running costs = 26, 610.00
Total cost = 74, 610.00
7% O/H = 5, 222.70
Total costs to recover = 79, 832.70

An Equipment rate sum


Consider three year life
Utilisation
Usage = 5d x 8hrs x 47wks x 3yrs = 5, 640 hrs
But only 80% = 4, 512 hrs
Therefore plant rate = 79, 832.70/4, 512 = 17.69 per hr
Labour for operator = 7.50 +150% = 18.75 per hr
Therefore equivalent hire rate = 36.44 per hr
This is less than 39.00 so proposal is cost effective.

You might also like