Chennai Metro Rail Project: Submitted By: Ashish Kumar Neeraj Kumar Parag Chaubey
Chennai Metro Rail Project: Submitted By: Ashish Kumar Neeraj Kumar Parag Chaubey
Chennai Metro Rail Project: Submitted By: Ashish Kumar Neeraj Kumar Parag Chaubey
DETAILED PROJECT
REPORT
Chennai Metro Rail Project
Submitted
By :
Ashish
Kumar
Neeraj
Kumar
Parag
STAGES OF PLANNING
CONSTRUCTION STAGE
INVESTMENT DECISION
STATUTORY CLEARANCES
EVALUATION & APPRAISAL
ENVIRONMENTAL
TECHNO ECONOMIC
COST ESTIMATE
FEASIBILITY REPORT/
OTHER INPUTS
DETAILED PROJ REPORT
CIVIL, MECH, ELECT & C&I
INPUTS
BASIC ENGG
SITE SPECIFIC STUDIES/INVESTIGATIONS
PROJECT
SITE SELECTION/PRE-FEASIBILITY STUDIES
FEASIBLITY
RECONNAISSANCE
Basic Components
Tie-up of Basic Inputs
Conduct Site Specific Studies/
Investigations
Basic Engg./System
Finalization
Technical Inputs
Inputs other than Technical
Clearances / Commitment
Financing Plan
Cost Estimates
1.14
0.53
3.47
0.10
20.98 26.22
4.34
1.68
3.88
0.38
10.28
2.17
0.00
4.10
2.37
3.94
12.58
7.65
2.21
4.10
9.72
4.42
20.98 49.08
Year
2016
2014
2026
Traction
Corridor Auxiliary
1
Total
Traction
Corridor Auxiliary
2
Total
10.3
31.4
41.7
10.4
7.2
17.6
13.2
32.1
45.3
15.0
8.6
23.6
18.9
39.7
58.6
21.7
10.1
31.8
TOTAL
59.3
68.9
90.4
Corridor
-1
Corridor
-2
Grid Substation
(with i/p
voltage)
GMR Vasavi
(230/110
kV)
Location of
RSS of
Metro
Authority
Approx Length of
Cables
Jail Complex
(110/33 kV)
2km. 110 kV
(Double Circuit Cables)
2km. 110 kV
(Double Circuit Cables)
Koyambedu Koyambedu
Grid SubDepot
station
(110/33 kV)
(230/110
1km. 110 kV
(Double Circuit Cables)
2011
2016
2016
Corridor
Daily
s
Passeng
er
Length
(km)
Pass-km
Pass
km/km
(lakh)
Corr-1
318532
22.5
2632748
1.2
Corr-2
254144
21.3
2137984
1.0
Total
572676
43.8
4770732
1.1
Corr-1
403169
22.5
3280363
1.5
Corr-2
353297
21.3
2866624
1.3
Total
756466
43.8
6146987
1.4
Corr-1
542444
22.5
4575592
2.0
Corr-2
521605
21.3
4323905
2.0
1064048
43.8
8899496
2.0
Total
System Finalization
Track
Standard Gauge (1435mm) for the
following reasons :
a.Intensive usage
b.Long lasting
c.Minimum maintenance
d.Safety, reliability and comfort
e.Minimum noise and vibrations.
System Finalization
Traction System
750 V DC third rail for the following
reasons :
a.Height of metro structures including
train heights need to be restricted to
12 mtr.
b.25 kV AC traction system with
overhead wires provides cluttered
looks to system.
System Finalization
Signaling & Train Control
Distance to go Automatic Train
Protection and Automatic Train
Supervision
To provide capacity optimization
Provide best services to public.
System Finalization
Telecommunication
Backbone for communication
Signaling
SCADA, AFC
Operational & Administrative
requirements
Passenger Information System
Crisis Management during emergencies
System Finalization
Automatic fare Collection
To handle large number of passengers
Efficient and Proper Ticket issue & fare
collection
Simple & easy to operate
Easy accounting
Less manpower requirement
Amenable for quick fare changes
Cheaper in long run
Prevent leakage of revenue
Less cost of recyclable tickets
System Finalization
Rolling Stock
Same as used in DMRC for the
following reasons:
Proven Reliability
Passenger Safety Feature
Energy Efficiency
Low Life Cycle Cost
Light Weight
High rate of acceleration and deceleration
Rail Network
Line Map
Schematic Map
Technical Inputs
Civil Engineering
Description of Alignment
Corridor 1
Breakup of Alignment length
Total Elevated length = 8.785km
Total Underground length = 14.300km
Total Alignment length = 23.085km
Corridor 2
Break-up of alignment length
Alignment length is 22.000 km from dead end to dead end
Technical Inputs
GEOTECHNICAL INVESTIGATION
A total of 75 Boreholes were carried out along the corridors.
Archeans rock, found in the peninsular region are generally composed of granite
and Gneisses of Peninsular Gneissic Complex, composition of duke is mainly
Doleritic whereas sedimentary formations are mainly of shale and sand stone
with or without fossiliferous beds.
UTILITY DIVERSION
Following engineering items have been studied and described in this chapter:
Existing utilities and planning for their diversion during construction, if
necessary.
Land acquisition necessary for the project both on permanent basis as well as
temporary, including its break up between Government and private ownership.
Technical Inputs
POWER SUPPLY SYSTEM
Broad estimation of auxiliary and traction power demand is made
based on the following assumptions:I. Specific energy consumption of rolling stock 70KWh/1000 GTKM
II. Regeneration by rolling stock 20%.
III. Elevated/at grade station load initially 200KW, which will increase to 300
KW inclusive of Property Development loads in the year 2026.
IV. Underground Station load initially 2000 kW, which will increase to 2500
kW in the year 2026.
V. Depot auxiliary load initially 2000KW, which will increase to 2500 KW in
the year 2026.
SCADA SYSTEM
I. The entire system of power supply (receiving, traction & auxiliary supply)
shall be monitored and controlled from a centralized Operation Control
Centre (OCC) through SCADA system. Modern SCADA system with
intelligent remote terminal units (RTUs) shall be provided. Optical fibre
provided for telecommunications will be used as communication carrier for
SCADA system
Maintenance Depots:
Two depots are proposed in phase-I. The Koyambedu Depotcum-Workshop will be the main depot and located on corridor
2. the second depot is at Minambakkam on corridor 1 for
stabling & inspection.
Total 184 coaches (92 coaches for Corridor 1 & 92 coaches for Corridor 2) are
required in the year 2011.
Clearances and
Commitments
Approvals
Government of Tamil Nadu have
approved in principle the two initial
corridors on 7-11-2007
Government of India have approved
the Chennai Metro Rail project on
28-1-2009.
Cost Estimates
Capital costs workout at March 2007 price level as
described hereunder
Financing Plan
Revenues
Fare Structure
The metro fare obtained by multiplying the bus fare by 2 times has
been rounded off to the nearest rupee.
References
www.chennaimetrorail.gov.in
www.cmdachennai.gov.in
Japan International Co-operation Agency
www.jicago.jp
International Association of Public
Transport www.uitp.org/regions/AsiaPacific/activities.cfm
www.uitp.org/PublicTransport/metro/index.cfm