Stéphane Giraud EGIS France PPP
Stéphane Giraud EGIS France PPP
Stéphane Giraud EGIS France PPP
CONTRACTS
23/09/2011
Content
1. INTRODUCTION : THE NGRBA AND THE FRENCH
SUPPORT
2. HOW TO CHOOSE THE BEST FIDIC
CONSTRUCTION CONTRACT FOR A WASTE/WATER
INFRASTRUCTURE PROJECT IN PPP ?
3. MAIN PITFALLS IN CONSTRUCTION CONTRACT
BEFORE COMMERCIAL OPERATIONS
MEASURING RESULTS
200
1990
2008
9
10
FIDIC PRESENTATION
FIDIC founded by French engineers in 1913 as
Fdration Internationale des Ingnieurs Conseils
(International Federation of Consulting Engineers)
1945 = 40 Engineers Associations ; 2009 = 80
Engineers Associations including India
1957 = 1st Red Book as Conditions of Contract
for Construction for Building Works designed by
the Employer, 2008 = 1st Gold Book
www.fidic.org , HO in Geneva, Switzerland.
11
The Employer
DESIGN
BUILD
Disputes
(Adjudication
Board)
SERVICE
CONTRACT
CONTRACT
OPERATION
TAKING-OVER
The Engineer
or Employers
representative
CERTIFICATE
Auditing Body
SERVICE
CONTRACT
The Contractor
FIDIC contract
Administration
No contractual link !
12
13
14
yes
no
The Contractor undertakes
the design
The project is a plant and includes a
balanced risk allocation ?
Fixed Cost
Risks borne mainly by the
Contractor
yes
no
Discuss in details
no
yes
Operations(DBO)
yes
no
15
Increase risk
for The
Contractor
GOLD
BOOK /
SILVER
BOOK
YELLOW
BOOK
RED
BOOK
Increase risk for
the Employer
Increase design
control by the
Employer
16
1 YEAR
1 YEAR
FRANCE
CCAG P.I.
IDEA => DEGREE OF PRECISION
CONCEPT
PFS -FEED
DTL DESIGN
2 YEARS
< 20 YEARS
CCAG
TRAVAUX
LAW
CONSTRUCTION
OPERATIONS
FIDIC
Red book
Yellow book
Silver book
Gold book
17
Design responsibilities :
Strict definition of design criteria
Unforeseable difficulties to be foreseen (!)
Interfaces management (networks Vs. treatment plant)
Claim management :
Special care for drafting the Contract (Particular
Conditions of contract to be fit with the Laws)
Contemporary records to be kept
Mechanisms to avoid disputes
18
20
CLAUSES
193 SUBCLAUSES
CLAUSE 4 The Contractor
COST
COSTS
FIDIC
CLAUSE 5 Design
CLAUSE 6 Staff and Labour
CLAUSE 7 Plant, Materials, Workm
CLAUSE 11 Testing
CLAUSE 12 Defects
QUALITY
CLAUSE 8 Commencement,
Completion and Programme
CLAUSE 9 Design-Build
CLAUSE 10 Operation Service
GOLD
BOOK
CLAIMS
NO
ES
TIC
DEL
AYS
CONTRACT
TIME
19
20
21
22
23
24
25
26
27
28
29
DELAYED
FOR SITE
INVESTIGATIONS
TOPOGRAPHY AND
GEOTECHNICS (SC 2.1)
FORCE MAJEURE
(EARTHQUAKE,
STRIKE, WAR) (SC
18)
New Critical
Path
Civil works
ADVERSE SUB-SOIL
CONDITIONS =>
COST +40% (SC
4.12)
Procurement
Initial Critical
Path
Erection
Commissioning
WHO PAYS FOR DELAY ? (SC
9.13)
OPERATIONS
Time of Completion
YEAR 1
YEAR 2
Cut-Off
UP TO Date
20 YEARS
30
CONCLUSION
INTERNATIONAL FIDIC DBO CONTRACT GOLD BOOK IS
PARTICULARLY FIT FOR THE PURPOSE OF PPP WATER
TREATMENT; IT IS
COMPLETE
COMONLY SHARED BY ALL INTERNATIONAL PARTIES
DRAFTED TO AVOID AND TREAT PITFALLS
F O CONTRACT
- THANK YOU FOR YOUR ATTENTION THINK ABOUT FRENCH EXPERTISE ON FIDIC AND ON WATER PROCESS !
31