Chapter 20 Quality Control
Chapter 20 Quality Control
Management
“Six Sigma” (a registered trademark of the Motorola
Corp.) is the relentless and rigorous pursuit of the
reduction of variation in all critical processes to
achieve continuous and breakthrough improvements
that impact the bottom line of the organization and
increase customer satisfaction.
It is an organizational initiative designed to create
manufacturing, service and administrative processes
that produce approximately 3.4 defects per million.
Opportunities (DPMO).
Relationship between the Voice of the
Customer and the Voice of the Process
Six Sigma management promotes the idea that the
distribution of output for a process (the Voice of the
Process) should take up no more than half of the
tolerance allowed by the specification limits (the
Voice of the Customer)
This assumes that the measurement data is from a
stable and normal distribution of output whose mean
can shift by as much as 1.5 standard deviations over
time.
The following figure shows the Voice of the Customer
as spoken in the language of a nominal value, m, and
the lower and upper specification limits, LSL and
USL, for a quality characteristic.
This assumes
– Distribution of process output is measurement data
– The process is stable
– The distribution is normal
– The process average is on nominal
– The distance between nominal and either specification limit
is 3 times the process standard deviation
If these five conditions are met we all the process a
3-sigma process.
A 3-sigma process will produce 2,700 defects per
million opportunities.
LSL
3-sigma Process USL
An Example of a 3-sigma Process
The number of days to complete a month accounting
report is stable and normally distributed with an
average of 7 days and a standard deviation of 1 day.
The lower specification limit is 4 days and the upper
specification limits is 10 days.
Next we see a quality characteristic represented by
measurement data that:
– Is stable
– Is normally distributed
– Has a process output that can shift by as much as 1.5
standard deviations on either side of nominal
– Has a distance between nominal and either specification
limit of 3 standard deviations of process output.
This is a 3-sigma process with a 1.5 sigma shift in the
mean.
This process will generate 66,811 defects per million
opportunities or 93.33189% of its output between the
specification limits.
Accounting process with process average shifts of 1.5
standard deviations.
Next we see a scenario where the voice of the
process takes up only half the distance between the
specification limits. The process mean remains the
same, but the process standard deviation has been
reduced to one half-day
Output for the monthly accounting process with the
standard deviation reduced to one-half day through process
improvement activities.
Next we will see the voice of the customer and the
voice of the process for a quality characteristic that:
– Is represented by measurement data
– Is stable
– Is normally distributed
– Has a process average that can shift by as much as 1.5
standard deviations on either side of nominal
– Has the distance between nominal and either specification
limit is 6 standard deviations of the process output.
This is a process that will generate 3.4 defects per
million opportunities, or 99.99966% of its output
within specification limits in the near future.
Six sigma accounting process with a 1.5 sigma shift in
the mean
The DMAIC Model
Mission Statement:
Put the Right Information in the right Place.
RIP it!
POI’s Business Objectives and Indicators with Potential Six Sigma Projects
1400000 UCL=1393879
1300000
Individual Value
1200000
1100000 Mean=1096880
1000000
900000
800000 LCL=799881
Subgroup 0 10 20 30 40 50 60 70
400000
UCL=364863
300000
Moving Range
200000
100000 R=111672
0 LCL=0
10
Fr equen cy
5
0
890000 930000 970000 1010000 1050000 1090000 1130000 1170000 1210000 1250000 1290000
Increase W .35 3 3 0 0
the number E
of orders I
G
H
Increase T .10 1 3 0 0
the number S
of POI
services
utilized by
each
customer
Minimize .40 0 0 9 3
production
costs
Eliminate .15 0 0 9 9
employee
complaints
1 55 70
2 50 55
3 60 65
4 65 60
5 70 50
Average 60 60
3b. Why do the MSD project now?
The Paper Shuffling Department is experiencing very high monthly production costs.
Also, internal customers, including managers and hourly employees, are submitting an
increased number of complaints as recorded in the Purchasing Department’s complaint
log for the fiscal year 2000:
– 14 in the first quarter
– 18 in the second quarter
– 32 in the third quarter
6e. How much can the team spend beyond $30,000.00 without seeking
additional authority?
Nothing.
1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2
0 1 2 3 4 5 6 7 8 9 0 1
Define BA X X X X X X
Mesure BA X X
Analyze BA X X X
Improve BA X X X X X X
Control BA X X X X
7. What are the benefits of the project?
The soft benefits of the project include eliminating
complaints from the Paper Shuffling Department
and increasing employee morale.
The hard (financial) benefits of the project are
minimizing labor costs and material costs. The
hard cost benefits are estimated from the following:
100 employees in the Paper Shuffling Department
x 40 hours/week/paper shuffling employee
x 10% of time devoted to clipping
@ 400 hours/week devoted to clipping in PSD
x $25/hour/paper shuffling employee
$10,000/week devoted to clipping
x 50 weeks/year
$500,000/year devoted to clipping
x .60 defective clips (judgment sample estimate of durability of the
current system) Broken clips are not selected for use on jobs. This
makes 0.6 a conservative estimate of the percentage of defective clips in
the current system. Note: This conservative estimate does not include
problems arising from defective clips not detected until after they have
been used and have caused failure on the job.
$300,000/year on defective clipping for current system
x .0062 defective clips (durability of the proposed system) Again, broken
clips are not selected for use on jobs.
$3100/year on defective clipping for proposed system
Hence, the annual savings on labor costs from
improving MSD purchasing process is $296,900
($300,000 - $3,100).
The PSD incurs a 10% annual employee turn over.
To capitalize on savings in labor costs, the
department will now higher 4 new employees
instead of 10 new employees, for a savings of 6
full-time employees ($296,900/$25 = 11,876 hours;
11,876/40 hours per week/50 weeks per year =
5.938= ~ 6 employees saved).
x50 weeks/year
@ 300,000 projects/year requiring 3,000,000 MSDs (10 clips per project on average)
x.01/clip
x.01/clip
Purchasing
receives order from
Paper Shuffling
Department
Purchasing agent
calls vendor
No
Does vendor
have MSD
in stock?
Yes
Place order with
vendor
Store product
received into
inventory (new
boxes go on bottom
back of shelf)
PSD removes
products from
inventory
Stop
Conduct a “Voice of the Customer” Analysis
The third part of the define phase involves team
members collecting and analyzing “Voice of the
Customer” data. “Voice of the Customer” data is
verbal or written information collected from a
sample of users, in a selected market segment.
The questionnaire used to collect data from users
of MSDs in the PSD is:
Questions
What needs and wants come to mind when you think about MSDs?
Note: These questions do not consider the opinions, feelings and attitudes of the
upstream, downstream, and external customers of the PSD.
Team members analyze the “Voice of the
Customer” data by market segment.
Next, they use all the raw “Voice of the Customer”
data points to create affinity diagram.
Themes, called focus points using numbers linking
columns 2 and 3 in column 3 in the following table
are identified.
Next, team members identify the engineering issue
underlying each focus point, called cognitive
issues.
Then, team members convert each cognitive issue
into one or more quantitative engineering
variables, called Critical-To-Quality (CTQ)
variables.
Finally, team members develop technical
specifications for each CTQ.
Affinity Engineering
Selected Diagram issue
Market Raw “Voice of the Customer” theme (Focus (Cognitive Tech.
Segment data Point) issue) CTQ Spec.
Paper “My employees are frustrated Variation in Durability Ability to >= 4 bends
organizing about the MSDs. They complain durability (1) withstand without
managers that they break too fast” 1&2 bending breaking
“My employees are complaining Variation in Color The = 1 color of
that the MSDs are not holding color (2) number of MSDs
up during the organizing different
process.” 1 MSD colors
“The employees are Variation in Functionality The <=5
complaining that the color of the functionality number of broken
MSDs change from one day to (3) broken MSDs in a
the next. It seems to be MSDs in a box
confusing them.” 2 box
“My employees are very
unhappy with the purple and
blue MSDs. They would prefer
only one color of MSDs be used
consistently” 2
“My employees say that more
than 5 MSDs per box arrive
broken.” 3
“I’ve heard from numerous
employees that the MSDs
coming straight from inventory
are already broken.” 3
...
Affinity Driving
Selected Diagram issue
Market Raw “Voice of the Customer” theme (Focus (Cognitive Tech.
Segment data Point) issue) CTQ Spec.
Hourly "The MSDs are falling apart Variation in Durability Ability to >= 4 bends
employees before we are ready to file the durability (1) withstand without
papers in to binders. An MSD bending breaking
should be able to take at least 4
bends." 1
"The MSDs aren't helping us to Variation in Color The = 1 color of
do our work efficiently." 1 & 2 color (2) number of MSDs
different
MSD colors
“I would prefer if we only used Variation in Functionality The <=5
one color of MSDs.” 2 functionality number of broken
(3) broken MSDs in a
MSDs in a box
box
“I don’t understand why we use
different colors of MSDs.” 2
"The MSDs just break when
trying to bend them over the
paper stacks. They should take
at least 4 bends" 1
“It is very frustrating when you
open a brand new box of MSDs
and find that more than 5 of the
clips are already broken.” 3
“It is very time consuming to sift
out the broken MSDs from a
brand new box coming straight
from inventory.” 3
...
Returning to the first part of the define phase, team members can now define the project’s objectives.
• Project Objective 1: Decrease (direction) the percentage of MSDs that can not withstand 4 or more bends without
breaking (measure) bought by the Purchasing Department (process) to 00.62% (goal) by January 1, 2003 (deadline).
Go for 4-sigma!
• Project Objective 2: Decrease (direction) the percentage of boxes of MSDs with more than 5 broken clips (measure)
bought by the Purchasing Department (process) to 00.62% (goal) by January 1, 2003 (deadline). Go for 4-sigma!
• A correlation exists between the project objectives. A broken MSD cannot withstand 4 or more bends because it is
already broken. Improving the percentage of functional MSDs per box will increase the percentage of MSDs that can
withstand 4 or more bends.
Measure Phase
• The measure phase has three steps:
• operationally define the CTQs
• perform a gage R&R study on each CTQ
• develop a baseline for each CTQ.
11 1
10 2
9
Fuctionality
8
7
6
5
4
Box 1 2 3 4 5
11
10
9
Fuctionality
8
7
6
5
4
Box 6 7 8 9 10
The procedure for selecting a box of MSDs is simply to select the top-front most box on the shelf. The selection process was not altered during a sampling period of two 8-hour
shifts.
15
Individual Value
UCL=12.21
10
5
Mean=3.875
-5 LCL=-4.458
Subgroup 0 5 10 15
1
10 UCL=10.24
Moving Range
5
R=3.133
0 LCL=0
Note: Use of the I-MR chart assumes approximate normality of the CTQ (durability). The
durability data is clearly not normally distributed, see dot plot that follows.
• Hence, use of the durability I-MR chart is not advised
at this time.
• However, the distribution of durability may
approximate a Poisson distribution.
• Consequently, team members constructed a c-chart
for the “count of bends” before each MSD breaks,
see next slide.
1. Develop a more detailed process map (that is, more detailed than the
process map developed in the SIPOC analysis of the Define phase)
2. Construct operational definitions for each input or process variable
(called Xs)
3. Perform a gage R&R study on each X (test the adequacy of the
measurement system)
4. Develop a baseline for each X
5. Develop hypotheses between the Xs and Ys. The Ys are the output
measures used to determine if the CTQs are met.
Purchasing
receives order from
Paper Shuffling
Department
Purchasing agent
calls vendor
No
Does vendor
have MSD
in stock?
Yes
Place order with
vendor X1 – Vendor (Ibix or Office Optimum)
X2 – Size (Small or Large)
Receive order from X3 – Ridges (With or Without)
vendor X4 = Cycle time from order to receipt for MSDs
X5 = Discrepancy in count from order placed and
MSDs placed into
order received
inventory (new boxes
go on the bottom
back of shelf) X6 = Cycle time to place product in inventory
PSD removes
box from X7 = Inventory shelf time (in days)
inventory
Stop
Develop an operational definition for each X.
•Team members develop an operational definition for each X
variable identified on the process map. The operational
definitions for X1, X2, X3 and X8 relate to individual MSDs and
are shown below.
Criteria: Compute cycle time in days by subtracting the order date from the date on the bill of lading.
Test: Select a box of MSDs upon receipt of shipment from vendor. Compute the cycle time.
Decision: Determine X4 for the selected box of MSDs.
Decision: Compute the value of X6 in days for the selected purchase order.
X6 Cycle time to place product in inventory In days
Criteria: Compute inventory shelf-time in days for a box of MSDs by subtracting the date the box was placed in inventory from the
date the box was removed from inventory.
Decision: Compute the value of X7 in days for the selected box of MSDs.
• For a two-week period the first box of MSDs brought to the PSD each hour
was selected as a sample; this yielded a sample of 80 boxes of MSDs
• For each sampled box, team members determined the durability (Y 1) and
functionality (Y2) measurement. Furthermore, they collected information
concerning the vendor (X1), size of the MSD (X2), whether or not the MSD
has ridges (X3), and inventory shelf life will be recorded (X 7).
• Note that Purchasing Department will separately study cycle time from order
to receipt of order (X4), discrepancy between ordered and received box counts
(X5), and cycle time from receipt of order to placement in inventory (X 6).
• These last factors may influence such concerns as choice of vendor, ordering
procedures, and inventory control, but they do not impact durability and
functionality.
• Furthermore, the MSDs are not tested after they are used so the type of
usage (X8) is not studied here.
•As was indicated in the Define phase, certain variables (e.g., X 4, X5, X6, and X8)
can be addressed in subsequent Green Belt projects.
• As before, this indicates very poor levels for the CTQs in the Paper
Shuffling Department.
• For comparison purposes the judgment sample carried out by the team
during the Define phase showed that the yield was approximately 40%
(i.e., the team assumed the failure rate was approximately 60%) for
both durability and functionality.
• The slight increased yields in this study can be due to
natural variation in the process.
1. The values of durability tend to be low or high with a significant gap between 4 and 6 for X1, X2, X3 and X7, and
2. The variation in durability is about the same for all levels of X1, X2, X3 and X7.
• Since there are no clear differences in variation (i.e., spread) of durability for
each of the levels of X 1, X2, X3 and X7, the team wondered if there might be
differences in the average (i.e., center) for each level of the individual X’s.
• Team members constructed a main effects plot for durability to study differences
in averages, see following figure.
Main effects plot for durability by X1, X2, X3, and X7.
Develop hypothesis between Xs and Ys.
The main effects plot for durability indicates that:
• For the range of shelf lives observed there is no clear pattern for the relationship of shelf life (X 7) to the average
Durability.
• On the other hand, it appears that ridges (i.e., X 3 = 1) has a positive relationship to the average Durability.
• At first glance it would seem that the better results for the average Durability are seen when the vendor Ibix is
chosen using small MSDs (i.e., X 1 = 1 and X2 = 0), while using large MSDs from Office Optimum
• (i.e., X1 = 0 and X2 = 1) yield worse results.
• While discussing the dot plots and main effects plot it was suggested that it is dangerous to make any
conclusions without knowing if there are interaction effects.
• An interaction effect is present when the amount of change introduced by changing one of the Xs
depends on the value of another X.
• In that case, it is misleading to choose the best value of the Xs individually without first considering the
interactions between the Xs.
• Consequently, team members did an interactions plot
for X1, X2, and X3.
• When there is no interaction the lines should be parallel to each other indicating the amount of change in
average Durability when moving from one level of each X variable to another level should be the same for
all values of another X variable.
• This plot shows the lines on the graph of X1 and X2
not only are not parallel, but they cross.
• In order to study all this further the team decides that during the Improve phase they will run a full
factorial design to examine the relationship of X1, X2, and X3 on Durability (Y1) since the main
effects plot indicates potential patterns.
• Again, there does not appear to be a relationship between Durability (Y 1) and X7.
Discussion of the Analysis of Functionality
Main effects plot for functionality by X1, X2, X3, and X7.
Interaction effects plot for functionality by X1, X2, and X3
• The main effects plot indicates that higher values of shelf life (X7) yield higher values for Functionality (Y2).
• The team surmised that the longer a box of MSDs sits in inventory (i.e., higher values of shelf life), the higher the count
of broken MSDs (i.e., functionality will be high).
• From a practical standpoint, the team felt comfortable with this conclusion.
• They decided the Purchasing Department should put a “Six Sigma” project in place to investigate whether the potential
benefit of either a “just in time” MSD ordering process or establishing better inventory handling procedures will solve the
problem.
• The interaction effects plot indicate a potential interaction between the X2 (i.e., size) and X3 (i.e., ridges).
• The better results for functionality (i.e., low values) were observed for large MSDs without ridges
(i.e., X2 = 1 and X3 = 0). Why this may be the case would need to be studied further.
• Also, there may be an interaction between X1 (i.e., vendor) and X2 (i.e., size), but it appears that better results are observed
whenever Office Optimum is used (i.e., X1 = 0).
• In other words, the average count of broken MSDs is lower (i.e., functionality average is lower) whenever Office Optimum is
the vendor.
Analyze Phase Summary.
• Hypothesis 1: Durability = f (X1=Vendor, X2=Size, X3=Ridges) with a strong interaction effect between X1 and X2.
• Hypothesis 2: Functionality = f (X1=Vendor, X2=Size, X3 = Ridges, X7=Shelf Life) with the primary driver being X7 with
some main effect due to X1 and an interaction effect between X2 and X3.
• X7 is the main driver of the distribution of Functionality (Y2) and is under the control of the employees of POI. Hence,
team members restructured Hypothesis 2 as follows:
• Functionality = f (X1=Vendor, X2=Size, X3=Ridges) for each fixed level of X7 (Shelf Life).
Improve Phase
The improve phase involves:
• Designing experiments to understand the relationship between the Ys and the vital few Xs and major noise variables
• Generating the actions needed to implement the levels of the vital few Xs that optimize the shape, spread and center of the distributions of the Ys
• A 23 full factorial design with 2 replications (8 trials) was performed for durability and
functionality.
• The factor conditions for Vendor (X1) are Office
Optimum (-1) or Ibix (1); the factor conditions for Size
are “Small” (-1) or “Large” (1), and the factors
conditions for Ridges (X3) are “Without Ridges” (-1)
or “With Ridges” (1).
The major effects (i.e., those that have significance level less than .
10, in other words over 90% confidence level) for Durability are the
interaction of Vendor and Size and the main effect due to Ridges.
Pareto Chart of Effects for Functionality
There are no significant effects due to Vendor, Size,
or Ridges present for Functionality.
This indicates that since the effect of Shelf Life was
held constant in this designed experiment, while it
was shown to affect Functionality in the data mining
analysis, the team can restrict its attention to
improving Functionality by addressing Shelf Life first.
As Durability is the only outcome influenced by
Vendor, Size, or Ridges in this designed experiment,
further consideration in this study will be restricted to
Durability.
Another project can address Shelf Life and its effect
on Functionality.
Since interaction effects should be interpreted prior to
studying main effects the team decided to construct
an interaction effect plot for Vendor and Size.
• The interaction effect plot between Size and Vendor indicates that the best results for
Durability are obtained using small MSDs supplied by Office Optimum or large MSDs
supplied by Ibix.
• The reasons for this interaction may be due to factors such as materials used for each
size MSD, differences in supplier processes for each size MSD, or other supplier-
dependent reasons.
• Team members can ask each vendor why their sizes
show significant differences in average durability, if
there is a preference to use only one vendor.
• Therefore, since Ridges is a main effect independent of any interaction effects, then the right selection of
MSDs is to use Office Optimum for small MSDs with ridges and Ibix for large MSDs with ridges.
• If the experimental results are used, then the average Durability for Office Optimum’s small MSDs with
ridges is (10 + 9) / 2 = 9.5 while the average Durability for Ibix’s large MSDs with ridges is (11 + 9) / 2 =
10.0.
• Both averages are well above the required
corresponding CTQ of at least 4.
• In addition, the choice of Vendor and Size will be as follows: (Vendor = Office Optimum) and (Size = Small) or (Vendor =
Ibix) and (Size = Large) to maximize average durability.
• In addition, the team decided to take on another project to reduce Shelf Life to less than 5 days to address Functionality.
• The revised flowchart for the Purchasing Department incorporating the findings of the Six Sigma project is shown next.
Start
Yes
Stop
Pilot Test.
Vendor Size Ridges Durability
Hour
Shift 1 – Hour 1 Office Optimum Small With 10
Ibix Large With 11
Shift 1 – Hour 2 Office Optimum Small With 7
Ibix Large With 11
Shift 1 – Hour 3 Office Optimum Small With 10
Ibix Large With 11
Shift 1 – Hour 4 Office Optimum Small With 8
Ibix Large With 11
Shift 1 – Hour 5 Office Optimum Small With 9
Ibix Large With 10
Shift 1 – Hour 6 Office Optimum Small With 9
Ibix Large With 9
Shift 1 – Hour 7 Office Optimum Small With 8
Ibix Large With 11
Shift 1 – Hour 8 Office Optimum Small With 9
Ibix Large With 10
Shift 2 – Hour 1
Office Optimum Small With 9
Ibix Large With 11
Shift 2 – Hour 2
Office Optimum Small With 8
Ibix Large With 10
Shift 2 – Hour 3
Office Optimum Small With 10
Ibix Large With 9
Shift 2 – Hour 4
Office Optimum Small With 7
Ibix Large With 9
Shift 2 – Hour 5
Office Optimum Small With 7
Ibix Large With 10
Shift 2 – Hour 6
Office Optimum Small With 9
Ibix Large With 11
Shift 2 – Hour 7
Office Optimum Small With 10
Ibix Large With 9
Shift 2 – Hour 8
Office Optimum Small With 8
Ibix Large With 11
RTY 32/32=1
• The RTY for durability is 100%.
• Functionality was also tested, but not shown here, using Shelf Life = 0 days; that is, the MSDs were tested immediately upon
arrival to POI before they were placed in inventory.
• The effect on Functionality of Shelf Life and inventory control procedures will be investigated in subsequent projects if
management decides these projects should be chartered.
• With all things being equal, large MSDs from Ibix should have a higher average durability then small MSDs from Office Optimum.
Control Chart for Durability
13
UCL=12.73
12
Indiv idual Value
11
Mean=10.25
10
9
8
LCL=7.768
7
Subgroup 0 5 10 15
3 UCL=3.049
Mov ing Range
1 R=0.9333
0 LCL=0
• Durability (Y1) is in control, but it is dangerous to compute any process capability statistics
due to the small sample sizes.
• However, estimates for the mean and standard deviation of Small MSDs from Office
Optimum are 8.625 and 1.05 (calculated from the data but the calculation is not shown
here), respectively.
• The mean and standard deviation for Large MSDs from Ibix are 10.25 and 0.83,
respectively.
• Since the CTQ for durability requires the number of
bends to be 4 or more, then this requirement is 4.4
standard deviations below the mean for Small MSDs
from Office Optimum and 7.5 standard deviations
below the mean for Large MSDs from Ibix.
• Mistake proofing the improvements and/or innovations discovered in the Six Sigma project
• Establishing a risk management plan to minimize the risk of failure of product, service or process
• Preparing a control plan for the process owners who will inherit the improved or innovated product,
service or process, and turn the improved process over to the process owner for continuous
improvement using the PDSA cycle
Mistake Proof the Revised Process.
Team members identified and prioritized two problems while mistake proofing the process
improvements discovered in the improve phase; they were:
Team members use risk management to identify two risk elements, they are:
1. Failing to train new purchasing agents in the revised purchasing process
2. Office Optimum and Ibix are out of MSDs with ridges.
Risk
Risk Likelihood of Impact of element
Risk Elements Category occurrence occurrence score
• The risk abatement plan for “failing to train new purchasing agents” is to document the revised purchasing
process in training manuals.
• The risk abatement plan for “Vendor out of MSDs with ridges” is for POI to request that both Office Optimum
and Ibix manufacture only MSDs with ridges due to their superior durability.
• This is a reasonable and acceptable suggestion to POI, Office Optimum and Ibix because the cost structures
for manufacturing MSDs with and without ridges are equal, and neither Office Optimum nor Ibix has other
customers requesting MSDs without ridges.
• Office Optimum and Ibix agree to produce only MSDs with ridges after a six-month trial period in which they check
incoming purchase orders for requests for MSDs without ridges.
• If the trial period reveals no requests for MSDs without ridges, then the POI Purchasing Department will revise the
process and the appropriate ISO 9000 documentation to reflect the possibility of purchasing only MSDs with ridges.
• Additionally, Office Optimum and Ibix thanked POI for pointing out to them that average durability is higher for MSDs
with ridges than MSDs without ridges.
• Both vendors claim that they are going to experiment
with possible different ridge patterns to increase
durability and decrease costs.
• The MSD project took effect in month 73 as per the next control chart.
I and MR Chart for Prod Costs by C3
1 2
1400000
Subgroup 0 10 20 30 40 50 60 70 80 90
1 2
400000
300000
Moving Range
UCL=249930
200000
100000
R=76495
0 LCL=0
Turn over the Process to the Process Owner