Work Sampling
Work Sampling
CONDUCTING A STUDY
It is recommended that a uniform procedure should be followed to perform a
work sampling study is to
1.
First, the objective of the study should be established. Work sampling can
be used to determine an overall perspective on the work done.
2.
Second, the people performing the task must be identified, i.e. general
office work is being studied with the objective of determining overall
productivity.
3.
The third step in making the study is the identification of the measure
of the output produced or the types of activities performed on the jobs
being studied. This step is especially important if the objective of the
study is to measure productivity with the intent of setting a standard.
4.
Fourth, the time period during which the study will be conducted must
be established. Starting and stopping points for the study must be
defined as well.
5.
This step involves defining the activities that are performed by the
people under study. For example, the definition used in a machine
utilization study, including only the categories of working, idle, and
idle-mechanical breakdown.
6.
7.
8.
9.
Confidence level
At the outset it is necessary to decide what level of
confidence is desired in the final work sampling
results.
The most common interval is 95%
The area under the curve at 2 sigma or two standard
deviations is 95.45 %.
This means that the probability is that 95% of the time
the random observations will represent the facts and 5
percent of the time they will not.
The formula for determining the sample size for a
confidence level of 68 percent or 1 sigma is
S=desired relative accuracy, p=percentage expressed
as a decimal, N=number of random observations
(sample size)
Sp
p (1 p)
N
Example
Suppose we want to determine the percentage of idle
time of the automatic screw machines in a department.
CL=95% error=+,-5 %
We want to know how many random observations will
be needed to give us the desired results.
100 observations were made and preliminary study 25
observations showed the machines to be idle. (25%)
Solution
N=? p=25% S=+,-5%=+,-0.05
p (1 p )
0.05 p 2
N
0.0025 p
4 p (1 p )
p (1 p )
4
N
N
2
0.0025 p
p
0.0025 p
1600(1 0.25)
4800
0.25
Determination of Accuracy
Desired accuracy must be lower than 5%. For example,
if we calculates S is 3.5% then it is sufficient result.
The accuracy or standard error of +,-3.5 percent means
that the results is correct within +,-3.5 percent of ex:30
percent (+,-3.5%*30%=1.05%) or the value was
between 28.95% and 31.05 percent.
The 95% CL means that the probability is that in 95
cases of 100 the above results will represent the facts.
Nomogra
m
method
An easier
way to
determine
sample size
is to read off
the number
of
observation
s
needed
directly
from a
nomogram
such as the
one
reproduced
in figure 91.
We can, however, extend this simple model to try to find out the
cause of the stoppage of the machine:
the
Technique
Locate yourself at the same place each time prior to observing the
operation
Try to intentionally distract yourself from the variable of observation
as you approach the site (think safety)
Limit your time at the site to that actually needed for the
observation
Try to record only the minimum data that you will need to
successfully reconstruct the observation
Verify any discrepancy with the supervisor or foreman
Make notes on the form after the operator can no longer see you
Keep a pleasant attitude