4E1 Management For Engineers: Project Management - Lecture 3 Leo Harmon
4E1 Management For Engineers: Project Management - Lecture 3 Leo Harmon
4E1 Management For Engineers: Project Management - Lecture 3 Leo Harmon
Objective of Lecture
From WBS to Network
Differences between them
Network to Gantt
Worked examples from Gray Larson
Concept of Critical Path
Concepts of Float/Slack and lag
Additional learning material
Chapter 6 Gray & Larson
4E1 Project Management Lecture 3
WBS to Network
WBS
Independently specified - task, resources, costs
No analysis of sequence
Network
Sequence of tasks
Interdependency & scheduling
Network Rules
Flow is Left to Right
An activity cannot begin until the preceding tasks
are completed
Arrows indicate precedence and flow (can cross
over each other)
Each activity should have a unique ID
Looping is NOT ALLOWED
Conditional statements are NOT ALLOWED
Project should have a common start and end
node
4E1 Project Management Lecture 3
In Class Exercise 1
From the Following WBS draw network
Solution to Task 1
Project Networks
Project networks have some specific characteristics:
Arrows/links
starting node
completion node
link between each pair of
nodes (why?)
May be
Free float
10
1.Forward pass
Traverse network from start,
calculating earliest possible
completion time of each task.
This will give you a total time
for the project.
2.Backward pass
Working backwards from end,
calculate latest completion
time needed to complete each
activitys preceding task.
3.Identify critical path
Nodes where the forward
earliest completion time
equals the backward latest
completion lie on the critical
path.
11
Forward Pass
How soon can an activity
start?
Earliest Start (ES)
ES
ID
EF
Description
Duration
12
EF
ES
EF
1
5
1
1
ES
EF
Description
Description
Description
Duratio
n
Duratio
n
Duratio
n
ES
EF
Description
Duratio
n
4E1 Project Management Lecture 3
13
Durations
Task A: Project Kick off
Task B: Dig Foundations
Task C: Order concrete
Task D: Pour Concrete
0
ES
1
5
1
1
D
Kickoff
Dig foundations
Pour Concrete
EF
Description
Order
Concrete
Duration
14
15
16
Backward Pass
How Late can an activity
start?
ES
ID
EF
Description
LS
Duration LF
17
Backward Pass
Task A: Project Kick off
Task B: Dig Foundations
Task C: Order concrete
Task D: Pour Concrete
0
ES
EF
SL
Description
LS
Duration
LF
Pour Concrete
Dig foundations
Kickoff
0
1
5
1
1
Order
Concrete
5
18
19
20
ES
ID
EF
SL
Description
LS
Duration LF
21
Slack
Task A: Project Kick off
Task B: Dig Foundations
Task C: Order concrete
Task D: Pour Concrete
Kickoff
ES
EF
SL
Description
LS
Duration
LF
1
5
1
1
Dig foundations
Pour Concrete
Order
Concrete
22
23
Solution to Koll
24
Complications
Complications can arise
when computing the
critical path:
Different precedence
relations
Multiple projects
Resource constraints
Tradeoffs
Overtime
Additional resources
Extension of duration
Cost
Resource sharing
Availability constraints
Politics
4E1 Project Management Lecture 3
25
Critical Path
Put best people on CP
Put most effort into Risk Assessment on CP
When short of time - focus on the CP and
Practice MBWA
Know where you can lend resources safely
Know where extra effort will pay big dividends
26
Finish to start
Start to start
Start to finish
Finish to finish
4E1 Project Management Lecture 3
27
Lag
Delay between the end of task and start of the
next
Transport
Approvals and signoff
Etc.
28
29
Critical Path
Probably the most important tool in project
management
Sensitivity Analysis
Multiple Critical Paths
then assign resources
30