Free Governor Mode of Operation FOR Steam Turbines: (FGMO)
Free Governor Mode of Operation FOR Steam Turbines: (FGMO)
OPERATION
(FGMO)
FOR
STEAM TURBINES
Presented By:
K B Batra
C&I Engineering
ORGANISATION OF PRESENTATION
What is FGMO ?
IEGC guidelines
Facilities available in KWU design sets of BHEL
Problems in implementation of FGMO
Modifications carried in control scheme
Conclusion
DROOP CHARACTERISTICS
Speed(rpm)
3200
3150
3000
3000
5% droop
2800
2600
2400
0
20
40
60
Load %
80
100
REALISATION OF DROOP
CHARACTERISTICS
In hydraulic control mode these are
48
49
51
Dr
oo
p
=
50
- 50 %
Load
52
8%
LOAD
SETPOINT
CORRECTED
LOAD SETPT
+
+
TSE
INFLUENCE
50 Hz
F-ACT.
LOAD
GRADIENT
FREQUENCY
INFLUENCE
500MW
500MW
LOAD
SETPOINT
CORRECTED
LOAD SETPT
+
+
TSE
INFLUENCE
+25 MW
0 MW
LOAD
GRADIENT
FREQUENCY
INFLUENCE
FREQ. = 50Hz
FREQ. = 49.875Hz
LOAD CHANGE = 5% i.e. 25MW
to
implement
STEERING COMMITTE
A high level committee set up by CEA to
examine the issue
View points of Utilities, OEMs, PGCIL and
CERC heard by the committee
After deliberations, certain actions were
suggested to BHEL and NTPC to address
the issues raised by utilities
RECOMMENDATIONS BY COMMITTEE
To develop a control scheme with floating frequency
as the frequency can vary between 49 to 50.5 Hz. The
scheme should also automate the process of
supplementary control i.e. Load change after 5
minutes
The modified control scheme to be tested at
simulator
To suggest suitable changes in the existing control
logic of EHC and CMC for safeguarding the boiler,
turbine, generator from the effect of rapid changes in
frequency
Contd.
OBJECTIVES
Load shall be brought back to the setpoint in a
ramped fashion after five minutes
For frequency < 49.0 and >50.5 Hz , load change to
be as per droop characteristics and limited to +/10%
MODIFIED SCHEME
First scheme developed by BHEL and tested at
Simhadri simulator at Corporate R&D on
17/07/2004
Step and ramp change in load were simulated
Parameter variations were within allowable limits
It met the set objectives. However, certain changes
were suggested
Results were presented to NTPC/ CEA/ PGCIL etc. In
4th and 5th committee meetings. 5th meet was held at
Hardwar
It was suggested by Chairman that the scheme be
tested at Simhadri site by BHEL & NTPC
Fref
Fact
Fdev
LOAD
SETPOINT
+
TSE
INFLUENCE
F-PREV
F-ACT.
(49-50.5)
FREF=49/ 50.5
F-ACT
<49/>50.5
LOAD
GRADIENT
TO CC
+5%
+
-
FREQUENCY
INFLUENCE
F
+
-
TO CC
+10%
LOAD
+ 15 Deg C
variation
+ 10 Deg
C
variation
M.S.
TEMP
H.R.
TEMP
REVISED
FGMO
SCHEME
THROTT
LE
PRESSU
RE
RH METAL
TEMPS
5 kg/sq.cm
variations
Nearing Alarm
Values
CONCLUSION
Modified scheme has been accepted by CEA and
NTPC
Final report of the committee has been released
directing utilities to implement FGMO
Scheme to be implemented by utilities for KWU
design sets
Utilities have to place order on BHEL for this work
As of now, LMZ design sets to be put in FGMO
(without any modification) and controlled manually
LOOP IN AUTO
MS. Pr. > (SET POINT - 2)
S
R
LOOP IN AUTO
8 SEC.
49 HZ
420
392
364
336
308
49.5 HZ
PAISE/UNIT
280
252
224
196
168
50 HZ
140
112
84
56
28
FREQUENCY
FREQUENCY vs UI PRICE
48.5
48.6
48.7
48.8
48.9
49
49.1
49.2
49.3
49.4
49.5
49.6
49.7
49.8
49.9
50
50.1
50.2
50.3
50.4
50.5
50.6
50.7
50.8
50.9
0
51
50.5 HZ