0% found this document useful (0 votes)
257 views51 pages

Project Scheduling

The document discusses project scheduling techniques like PERT and CPM which use networks to represent project activities and their dependencies. It explains how to construct a network diagram, determine the critical path using earliest and latest start/finish times, and calculate float or slack time for non-critical activities. The critical path identifies the minimum time needed to complete the project and activities on this path require close monitoring and control.

Uploaded by

kjs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
257 views51 pages

Project Scheduling

The document discusses project scheduling techniques like PERT and CPM which use networks to represent project activities and their dependencies. It explains how to construct a network diagram, determine the critical path using earliest and latest start/finish times, and calculate float or slack time for non-critical activities. The critical path identifies the minimum time needed to complete the project and activities on this path require close monitoring and control.

Uploaded by

kjs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 51

Chapter 8 Project Scheduling

INTRODUCTION

Schedule converts action plan into operating


time table
Basis for monitoring and controlling project
Scheduling more important in projects than
in production, because unique nature
Sometimes customer specified/approved
requirement-e.g: JKR projects
Based on Work Breakdown Structure (WBS)

Chapter 8

Scheduling, PERT, Cri

NETWORK TECHNIQUES
PERT

CPM

-Program Evaluation and


Review Technique
- developed by the US
Navy with Booz
Hamilton Lockheed
- on the Polaris
Missile/Submarine
program 1958

Critical Path Method


Developed by El
Dupont for Chemical
Plant Shutdown
Project- about
same time as PERT

Both use same calculations, almost similar


Main difference is probabilistic and deterministic in time
estimation
Gantt Chart also used in scheduling

Chapter 8

Scheduling, PERT, Cri

NETWORK

Graphical portrayal of activities and event


Shows dependency relationships between
tasks/activities in a project
Clearly shows tasks that must precede
(precedence) or follow (succeeding) other
tasks in a logical manner
Clear representation of plan a powerful
tool for planning and controlling project

Chapter 8

Scheduling, PERT, Cri

Example of Simple Network


Survey

Chapter 8

Scheduling, PERT, Cri

Example of Network
More Complex

Chapter 8

Scheduling, PERT, Cri

DEFINITION OF TERMS IN A NETWORK

Activity
:
any portions of project (tasks) which required by
project, uses up resource and consumes
time may involve labor,
paper work,
contractual negotiations, machinery operations
Activity on Arrow (AOA) showed as arrow, AON Activity on Node
Event
:
beginning or ending points of one or more
activities, instantaneous point in time, also
called nodes
Network

Combination of all project activities and the events

SUCCESSOR

PRECEEDING
ACTIVITY

EVENT

Chapter 8

Scheduling, PERT, Cri

Emphasis on Logic in Network Construction

Construction of network should be based on logical or


technical dependencies among activities
Example - before activity Approve Drawing can be
started the activity Prepare Drawing must be completed
Common error build network on the basis of time logic
(a feeling for proper sequence ) see example below

WRONG !!!
Chapter 8

CORRECT
Scheduling, PERT, Cri

Example 1- A simple network


Consider the list of four activities for making a simple
product:
Activity

Description

Buy Plastic Body

Design Component

Make Component

Assemble product

Immediate
predecessors
B
A,C

Immediate predecessors for a particular activity are


the activities that, when completed, enable the start of
the activity in question.

Chapter 8

Scheduling, PERT, Cri

Sequence of activities

Can start work on activities A and B anytime,


since neither of these activities depends upon
the completion of prior activities.

Activity C cannot be started until activity B has


been completed

Activity D cannot be started until both


activities A and C have been completed.

The graphical representation (next slide) is


referred to as the PERT/CPM network

Chapter 8

Scheduling, PERT, Cri

10

Network of Four Activities


Arcs indicate project activities
A

2
Nodes correspond to the
beginning and ending of
activities

Chapter 8

Scheduling, PERT, Cri

11

Example 2
Develop the network for a project with following activities
and immediate predecessors:
Activity
Immediate
predecessors
A
B

A, C

Try to do for
G the first five
D,E,F(A,B,C,D,E) activities
Chapter 8

Scheduling, PERT, Cri

12

Network of first five activities


A

B
C

Chapter 8

5
We need to
introduce a
dummy activity

Scheduling, PERT, Cri

13

Network of Seven Activities


A

3
dummy

B
C

E
F

Note how the network correctly identifies D, E, and F as the


immediate predecessors for activity G.
Dummy activities is used to identify precedence
relationships correctly and to eliminate possible confusion of
two or more activities having the same starting and ending
nodes
Dummy activities have no resources (time, labor, machinery,
etc) purpose is to PRESERVE LOGIC of the network

Chapter 8

Scheduling, PERT, Cri

14

EXAMPLES OF THE USE OF DUMMYACTIVITY


Network concurrent activities
a

a
2

Dummy

WRONG!!!

RIGHT

Activity c not
required for e

WRONG !
a

a
b

d
1

c
c

WRONG
!!!

Chapter 8

RIGHT

Scheduling, PERT, Cri

RIGHT

15

WRONG!!!

RIGHT!!!

a precedes d.
a and b precede e,
b and c precede f (a does not precede f)

Chapter 8

Scheduling, PERT, Cri

16

Scheduling with activity time


Activity
(week)
A
B
C
D
E
F
G
H
I

Immediate
predecessors
A
A
A
E
D,F
B,C
G,H

Completion
Time

Total

5
6
4
3
1
4
14
12
2
51

This information indicates that the total time required to

complete activities is 51 weeks. However, we can see from the


network that several of the activities can be conducted
simultaneously (A and B, for example).

Chapter 8

Scheduling, PERT, Cri

17

Earliest start & earliest finish time

We are interested in the longest path through the


network, i.e., the critical path.

Starting at the networks origin (node 1) and using


a starting time of 0, we compute an earliest
start (ES) and earliest finish (EF) time for each
activity in the network.

The expression EF = ES + t can be used to find


the earliest finish time for a given activity.
For example, for activity A, ES = 0 and t = 5; thus
the earliest finish time for activity A is
EF = 0 + 5 = 5

Chapter 8

Scheduling, PERT, Cri

18

Arc with ES & EF time


EF = earliest finish
time

ES = earliest start
time
Activity

Chapter 8

]
5
,
0
[
A
5

t = expected activity
time
Scheduling, PERT, Cri

19

Network with ES & EF time


D[5,8]
3

0]
1
6,
[
F
4

B[0
,6]
6

, 21]
9
[
H
12

5
4]
0,2
G[1 4
1

E[
5,6
]
1

C[5,9]
4

A[
0
5 ,5]

26]
,
4
2
I[
2

3
Earliest start time rule:
The earliest start time for an activity leaving a particular node
is equal to the largest of the earliest finish times for all
activities entering the node.

Chapter 8

Scheduling, PERT, Cri

20

Activity, duration, ES, EF, LS, LF

ES = earliest start
time
Activity
]
9
,
5
[
C
2]
1
,
8
[
4

LS = latest start
time
Chapter 8

EF = earliest finish
time

LF = latest finish
time

Scheduling, PERT, Cri

21

Latest start & latest finish time

To find the critical path we need a backward pass calculation.

Starting at the completion point (node 7) and using a latest


finish time (LF) of 26 for activity I, we trace back through the
network computing a latest start (LS) and latest finish time
for each activity

The expression LS = LF t can be used to calculate latest start


time for each activity. For example, for activity I, LF = 26 and t
= 2, thus the latest start time for activity I is
LS = 26 2 = 24

Chapter 8

Scheduling, PERT, Cri

22

Network with LS & LF time

A[
5[ 0,5]
0,
5]
B[0
6[6 ,6]
, 12
]

C[5,9]
4[8,12]

E[
1[5 5,6]
,6]

0]
1
6, 10]
[
F 6,
4[

21]
,
9
[
H
,24]
2
1
[
12

5
4]
0,2 ]
G[1 10,24
14[

D[5,8]
3[7,10]

26]
,
4
2
I[
26]
,
4
2
2[

3
Latest finish time rule:

The latest finish time for an activity entering a particular node is


equal to the smallest of the latest start times for all activities
leaving the node.

Chapter 8

Scheduling, PERT, Cri

23

Slack or Free Time or Float


Slack is the length of time an activity can be delayed without
affecting the completion date for the entire project.
For example, slack for C = 3 weeks, i.e Activity C can be delayed
up to 3 weeks
3
(start anywhere between weeks 5 and 8). [5,9]

2
ES
5

LS
8

EF
9

C
2]
1
,
8
[
4

EF
12
LF-EF = 12 9 =3
LS-ES = 8 5 = 3

LF-ES-t = 12-5-4 = 3

Chapter 8

Scheduling, PERT, Cri

24

Activity schedule for our example


Activity

A
B
C
D
E
F
G
H
I

Earliest
start (ES)

Latest
start (LS)

0
0
5
5
5
6
10
9
24

0
6
8
7
5
6
10
12
24

Chapter 8

Earliest
finish
(EF)

5
6
9
8
6
10
24
21
26

Latest
finish
(LF)

5
12
12
10
6
10
24
24
26

Scheduling, PERT, Cri

Slack
(LS-ES)

0
6
3
2
0
0
0
3
0

Critical
path

Yes

Yes
Yes
Yes
Yes
25

IMPORTANT QUESTIONS

What is the total time to complete the project?

What are the scheduled start and completion times for each
activity?

ES, EF, LS, LF are given for each activity.

What activities are critical and must be completed as


scheduled in order to keep the project on time?

26 weeks if the individual activities are completed on schedule.

Critical path activities: A, E, F, G, and I.

How long can non-critical activities be delayed before they


cause a delay in the projects completion time

Slack time available for all activities are given.

Chapter 8

Scheduling, PERT, Cri

26

Importance of Float (Slack) and Critical Path


1.

Slack or Float shows how much allowance each activity has,


i.e how long it can be delayed without affecting completion
date of project

2.

Critical path is a sequence of activities from start to finish


with zero slack. Critical activities are activities on the critical
path.

3.

Critical path identifies the minimum time to complete


project

4.

If any activity on the critical path is shortened or extended,


project time will be shortened or extended accordingly

Chapter 8

Scheduling, PERT, Cri

27

Importance of Float (Slack) and Critical Path (cont)


5.

So, a lot of effort should be put in trying to control activities


along this path, so that project can meet due date. If any activity
is lengthened, be aware that project will not meet deadline and
some action needs to be taken.

6.

If can spend resources to speed up some activity, do so only for


critical activities.

7.

Dont waste resources on non-critical activity, it will not shorten


the project time.

8.

If resources can be saved by lengthening some activities, do so


for non-critical activities, up to limit of float.

9.

Total Float belongs to the path

Chapter 8

Scheduling, PERT, Cri

28

PERT For Dealing With Uncertainty

So far, times can be estimated with relative certainty,


confidence

For many situations this is not possible, e.g Research,


development, new products and projects etc.

Use 3 time estimates


m= most likely time estimate, mode.
a = optimistic time estimate,
b = pessimistic time estimate, and
Expected Value (TE) = (a + 4m + b) /6
Variance
(V) = ( ( b a) / 6 ) 2
Std Deviation
() = SQRT (V)

Chapter 8

Scheduling, PERT, Cri

29

Precedences And Project Activity Times


Immediate
Activity Predecessor

Optimistic Most Likely Pessimistic

EXP

Var S.Dev

Time

Time

Time

TE

10

22

22

20

20

20

20

20

10

16

10

14

32

15

25

b,c

20

10

b,c

14

20

14

b,c

12

16

11

5.4

2.32

g,h

16

38

18

28.4 5.33

d,e

14

Chapter 8

Scheduling, PERT, Cri

30

The complete network


2
a
(20,4)

b
(20,0)

e
(10,4)

6
j
(8,4)

f
(14,4)

g
(4,0)

c
(10,4)

Chapter 8

d
(15,25)

h
(11,5.4)

Scheduling, PERT, Cri

i
(18,28.4)

31

Figure 8-13 The complete Network


EF=20
a
(20,4)

b
(20,0)

2
20

35
d
(15,25)
e
(10,4)

j
(8,4)
43

g
(4,0)

c
(10,4)

4
10

Chapter 8

h
(11,5.4)

f
(14,4)

CRIT. TIME = 43

i
(18,28.4)

24

Scheduling, PERT, Cri

32

Critical Path Analysis (PERT)


Activity

LS

ES

Slacks

Critical ?

Yes

20

20

25

20

29

20

21

20

14

10

25

24

35

35

Chapter 8

Scheduling, PERT, Cri

Yes

Yes

33

Assume, PM promised to complete the project in the fifty days.


What are the chances of meeting that deadline?
Calculate Z, where
Z = (D-S) / V

Example,
D = 50; S(Scheduled date) = 20+15+8 =43;
V = (4+25+4) =33
Z = (50 43) / 5.745
= 1.22 standard deviations.

The probability value of Z = 1.22, is 0.888

1.22

Chapter 8

Scheduling, PERT, Cri

34

What deadline are you 95% sure of meeting

Z value associated with 0.95 is 1.645

D = S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days

Thus, there is a 95 percent chance of finishing the project


by 52.45 days.

Chapter 8

Scheduling, PERT, Cri

35

Comparison Between CPM and PERT


CPM
1

PERT

Uses network, calculate float or


slack, identify critical path and
activities, guides to monitor and
controlling project

Same as CPM

Uses one value of activity time

Requires 3 estimates of activity


time
Calculates mean and variance of
time

Used where times can be


estimated with confidence,
familiar activities

Used where times cannot be


estimated with confidence.
Unfamiliar or new activities

Minimizing cost is more important

Meeting time target or estimating


percent completion is more
important

Example: construction projects,


building one off machines, ships,
etc

Example: Involving new activities


or products, research and
development etc

Chapter 8

Scheduling, PERT, Cri

36

BENEFITS OFCPM / PERT NETWORK


Consistent framework for planning, scheduling,
monitoring, and controlling project.

Shows interdependence of all tasks, work


packages, and work units.

Helps proper communications between


departments and functions.

Determines expected project completion date.

Identifies so-called critical activities, which can


delay the project completion time.

Chapter 8

Scheduling, PERT, Cri

37

BENEFITS OFCPM / PERT NETWORK (cont.)

Identified activities with slacks that can be delayed


for specified periods without penalty, or from which
resources may be temporarily borrowed

Determines the dates on which tasks may be started


or must be started if the project is to stay in schedule.

Shows which tasks must be coordinated to avoid


resource or timing conflicts.

Shows which tasks may run in parallel to meet project


completion date

Chapter 8

Scheduling, PERT, Cri

38

Gantt Charts
Since 1917; Useful for showing work vs time in form of bar
charts
e.g.

Can draw directly or from CPM/PERT network

Chapter 8

Scheduling, PERT, Cri

39

Modified PERT/CPM diagram from network


a

Legend

Scheduled
Start
Scheduled
Finish
Actual
Progress
Unavailable
Current Date
Milestone
Scheduled
Milestone
Achieved

3
f

3
b
1

15

20

dummy
h

4
0

10

Chapter 8

25

30
Days

35

40

Scheduling, PERT, Cri

45

40

GANTT CHART

Chapter 8

Scheduling, PERT, Cri

41

Chapter 8

Scheduling, PERT, Cri

42

Chapter 8

Scheduling, PERT, Cri

43

Gantt Charts and CPM/PERT


Networks
Gantt Charts:

Even though a lot of info, easy to read and ,


understand to monitor and follow progress.

Not very good for logical constraints

Should be used to COMPLEMENT networks, not


replace

Chapter 8

Scheduling, PERT, Cri

44

RESOURCE ANALYSIS AND SCHEDULING


Ability to carry out projects depend on the
availability
of resources
Analyze resource implication
-How requirements can be met and changes
needed
Use resources efficiently
Use network to give information about time,
resources
Chapter 8
Scheduling, PERT, Cri
and cost

45

Activity

Activities D, E, F, G and H require fitters.


Construct a bar chart with activities at their EST indicat
person required and total float.
D

22222222

222222
22

2222

4 4 44 444 44444

H
0

10

15

20

Time
Add up across all activities to get the total number of m
required.
Chapter 8

Scheduling, PERT, Cri

46

T otal num ber of m an required

Convert the bar chart to a histogram


14
13
12
11
10
9
8
7
6
5
4
3
2
1
0

10

15

20

Time

Resource analysis before scheduling


Shows: i) Variation from week to week (fitters)
ii) Maximum number of person required (12)
during
week 5-6
Chapter
8
Scheduling,
PERT, Cri
47
Examine
resource
implication.

Example
If only 8 fitters are available at any period during the pr
New bar chart:
22222222

Activity

222222

22

2222

4 4 44 444 44444

H
0

Chapter 8

10

Time

15

Scheduling, PERT, Cri

20

48

Additional Restriction no fitters available until the end


week 5.
Revised Schedule:
22222222

Activity

222222

22

F
G

2222

4 4 44 444 44444
0

Chapter 8

10

Time

15

Scheduling, PERT, Cri

20

49

Resource constraints relates to:


1. Variations in resource requirements
2. Resource availability
Smaller variations:
1. Easier control of the job
2. Better utilization of resources
Big variations:
1. Frequent moving of manpower
2. Require close control
3. Affect efficiency
Chapter 8

Scheduling, PERT, Cri

50

T otal num ber of m an required


0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Time

Histogram showing large resource variations


Chapter 8

Scheduling, PERT, Cri

51

You might also like