Function Point Analysis (FPA) is a method to estimate the time and cost of developing or maintaining software by measuring certain attributes of the system. These attributes include inputs, outputs, files, inquiries and interfaces, which are each assigned complexity weights and counted. The counts are adjusted based on factors like performance needs and reuse. The adjusted function points can then indicate the estimated time and labor cost to complete the project. FPA allows productivity comparisons across languages, platforms, methods and teams. However, it does have some limitations for complex systems and difficulty applying to all project types.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
181 views9 pages
Function Point Analysis
Function Point Analysis (FPA) is a method to estimate the time and cost of developing or maintaining software by measuring certain attributes of the system. These attributes include inputs, outputs, files, inquiries and interfaces, which are each assigned complexity weights and counted. The counts are adjusted based on factors like performance needs and reuse. The adjusted function points can then indicate the estimated time and labor cost to complete the project. FPA allows productivity comparisons across languages, platforms, methods and teams. However, it does have some limitations for complex systems and difficulty applying to all project types.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 9
Function Point Analysis
What is Function Point Analysis (FPA)?
It is designed to estimate and measure the time, and thereby the cost, of developing new software applications and maintaining existing software applications. It is also useful in comparing and highlighting opportunities for productivity improvements in software development. It was developed by A.J. Albrecht of the IBM Corporation in the early 1980s. The main other approach used for measuring the size, and therefore the time required, of software project is lines of code (LOC) which has a number of inherent problems.
Function Point Analysis
How is Function Point Analysis done? Working from the project design specifications, the following system functions are measured (counted): Inputs Outputs Files Inquires Interfaces
Function Point Analysis
These function-point counts are then weighed (multiplied) by their degree of complexity: Simple Average Complex Inputs 2 4 6 Outputs 3 5 7 Files 5 10 15 Inquires 2 4 6 Interfaces 4 7 10
Function Point Analysis
A simple example: inputs 3 simple X 2 = 6 4 average X 4 = 16 1 complex X 6 = 6 outputs 6 average X 5 = 30 2 complex X 7 = 14 files 5 complex X 15 = 75 inquiries 8 average X 4 = 32 interfaces 3 average X 7 = 21 4 complex X 10 = 40 Unadjusted function points 240
Function Point Analysis
In addition to these individually weighted function points, there are factors that affect the project and/or system as a whole. There are a number (~35) of these factors that affect the size of the project effort, and each is ranked from 0- no influence to 5- essential. The following are some examples of these factors: Is high performance critical? Is the internal processing complex? Is the system to be used in multiple sites and/or by multiple organizations? Is the code designed to be reusable? Is the processing to be distributed? and so forth . . .
Function Point Analysis
Continuing our example . . . Complex internal processing Code to be reusable = 2 High performance = 4 Multiple sites = 3 Distributed processing = 5 Project adjustment factor
= 3
= 17
Adjustment calculation: Adjusted FP = Unadjusted FP X [0.65 + (adjustment factor X 0.01)] = 240 X [0.65 + ( 17 X 0.01)] = 240 X [0.82] = 197 Adjusted function points
Function Point Analysis
But how long will the project take and how much will it cost? As previously measured, programmers in our organization average 18 function points per month. Thus . . . 197 FP divided by 18 = 11 man-months If the average programmer is paid $5,200 per month (including benefits), then the [labor] cost of the project will be . . . 11 man-months X $5,200 = $57,200
Function Point Analysis
Because function point analysis is independent of language used, development platform, etc. it can be used to identify the productivity benefits of . . . One programming language over another One development platform over another One development methodology over another One programming department over another Before-and-after gains in investing in programmer training And so forth . . .
Function Point Analysis
But there are problems and criticisms: Function point counts are affected by project size Difficult to apply to massively distributed systems or to systems with very complex internal processing Difficult to define logical files from physical files The validity of the weights that Albrecht established and the consistency of their application has been challenged Different companies will calculate function points slightly different, making intercompany comparisons questionable