4 Canal Irrigation
4 Canal Irrigation
4 Canal Irrigation
Classification of Canals :
(A) Classification based on the nature of source of supply.
(B) Classification based on financial output.
(C) Classification based on the function of the canal.
(D) Classification based on canal surface boundary.
(E) Classification based on the discharge and its relative
importance in a given network of canals.
(F) Classification based on canal alignment.
Inundation canal
Also called as Temporary
canal.
Draw their supplies form rivers
whenever there is a high stage
in the river. That means carries
water in the rainy season.
They are provided with a canal
head regulator, which may
change according to river
course pattern.
It must be maintain
minimum
rate
of
return(about 6% to 8%).
PROTECTIVE CANAL
Carrier canal
Feeder canal
Feeding two or
more canal
Navigation canal
It provide for
inland
navigation. Small
ships and
steamers can ply.
Power canal
It carrying water
for hydropower
generation. A
power called as
hydel power.
Water supply
canal
Multipurpose
canal
It serves two or
For drinking and
more purpose,
industrial
such as irrigation,
purpose.
water supply etc.
Irrigation canal :
Feeder canal :
Carrier canal :
Navigation canal :
Alluvial canals
Non-alluvial
canals
LINED CANAL
Rigid boundary
canals
UNLINED CANAL
Lined Canal
Unlined Canal
CLASSIFICATION
BASED ON THE
DISCHARGE
Main canal
Branch canal
Major distributary
Minor distributary
Water course
It is branches of the
main canal. Branch
canal are usually feeder
channels for major and
minor distributaries.
Minor distributaries
called minors take off
from branch canals.
Discharge is usually less
than cumecs.
It is a small channel
which ultimately feeds
the water to irrigation
fields depending upon
the size.
CLASSIFICATION
BASED ON
CANAL
ALIGNMENT
Ridge canal
Contour canal
Ridge Canal :
It is also called as watershed canal is aligned along a
watershed.
When a channel is on the watershed, it can command the
areas on both banks and so a large area can be brought
under cultivation.
When the watershed takes a very sharp loop, the canal
should be aligned straight to save considerable idle length.
Contour Canal :
A channel aligned nearly parallel to the contour of the country is
called a contour canal.
It is not possible to align the canal on the watershed as the
watershed on the top of the hill may be very high and the areas
which need irrigation are concentrated in the valley.
The contour channel can irrigate only on one side.
Contour canal is sometimes constructed, with one bank only, and is
known as a single bank canal. However, when both the banks are
provided, it is known as a double bank canal.
Inundation Canals
An Inundation canal is similar to a permanent canal. The
major difference between them is that while in the case of
permanent canal a headwork (such as weir, barrage or a
dam) is constructed, and no such works are needed for an
Inundation canal.
But instead, an open cut in the river bank is provided for
the inundation canal to take off from the river.
The bed level of the cut is kept much above the bed level
of the river.
4.Knowing D and A, calculate the bed width B from geometry of canal section. The side
slope of canal in alluvial soil is assumed to be 0.5 : 1 when the canal has run for some
time.
; Calculate B
5.Calculate the perimeter and the hydraulic mean depth from the relations :
1
1/2
1/2
B
6.Calculate the actual mean velocity of flow (V) from Kutters equation. If this value of
velocity (V) is the same as V0 found in step 2, the assumed depth is correct. If not,
repeat the calculations with a changed value of D till the two velocities are the same.
Hence,
In the above eqtn. Q, m and x are known. Hence D is determined.
5. Knowing
and R, determine the slope S from Kutters flow equation.
The equation can be solved by trial and error method.
Regime silt grade : This indicates the gradation between the small
and the big particles. It should not be taken to mean the average
mean diameter of a particle
Initial regime: One of the condition of attaining regime of a channel is that there should be
freedom for the channel to form its own section. Intial regime is the state of channel that has
formed its section only and yet not secured the longitudinal slope.
Final regime : When a channel is constructed with defective slope , it tries to throw off
incoherent silt on the bed to increase their slopes. To attain the final regime, the channel forms its
section first before the final slope. The channel after attending its section and longitudinal slope
will be said to be in final regime.
Permanent regime : When a channel is protected on the bed and side with some kind of
protecting material, the channel section cannot be scoured up and so there is no possibility of
change of section or longitudinal slope ; the channel will then be said to be in permanent regime .
Regime theory is not applicable to such channels.
* Lacey also states that the silt is kept in suspension due to the force of vertical eddies.
4.
Procedure :
1. Calculate the silt factor :
2. Compute velocity :
3. Determine area :
4. Compute perimeter :
5. Find out bed width B and depth D of the channel section since A and P
are known. The side slope of an irrigation channel is usually : 1.
6. Compute :
Both values of R should be same ; this will provide a numerical check .
7. Find the slope :
2.
3.
Kennedy assumed Kutter's formula for finding the value of mean velocity
where in the value of N is to be assumed arbitrary. Lacey gave his own
formula for the velocity and thus a designer has not to chose anything
arbitrary.
The theory does not given a clear description of physical aspects of the
problem.
2.
3.
4.
5.
Lacey did not take into account the silt left in channel by water that is
lost in absorption which is as much as 12 to 15% of the total discharge
of channel.
K = Bazins coefficient
The value may be taken as 1.2 to 1.4 for earth channels in good
condition and between 1.7 to 1.8 for earth channels in poor condition.
2. Mannings formula :
Where N is Mannings coefficient ; the values of which depends upon
the type of surface of channel.
Design Procedure :
For a channel design, the discharge Q and bed slope S are
generally known. The value of maximum permissible velocity
and side-slopes (r : 1) are chosen on the basis of type of soil
through which the channel has to flow. Generally, Mannings
formula is selected as the flow equation.
Step 1 : Determine the area.
Canal Sections :
Thank You !!