Pipeline (WPS & WQT)
Sample of Process Flow
Commence
3d
pWPS
21d
WPQT
7d
WPS
14d
Resources
1 Welding Engineer: 360hrs
1 Welder Foreman: 280hrs
1 Fitter Foreman: 280hrs
1 QC Supervisor: 336hrs
1 QC Inspector: 1344hrs
1 Production manager: 40hrs
Total Duration = 45 days
*subject to how many test is required.
WQT
Pipeline (Transportation Study)
Sample of Process Flow
AFC Drawings
Consultant Report
General
Arrangement
Load-out Info
Sea State
Barge Confirmation
Transportation
Study
8d
Analysis/Report
2d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Issued for Approval
Resources
1 Marine Engineer: 80hrs
1 Lead Engineer: 8hrs
1 Drafter: 80hrs
1 Lead Drafter: 8hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 10 days
2
Pipeline (Pipelay Analysis)
Sample of Process Flow
AFC Drawings
Consultant Report
DL Barge Details
Pipelay Analysis
21d
Analysis/Report
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Resources
1 Marine Engineer: 168hrs
1 Lead Engineer:24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 24 days
Issued for Approval
Pipeline (Pipelay Procedure)
Sample of Process Flow
AFC Drawings
Consultant Report
Pipelay Analysis
Pre-lay Survey
Report
pWPS
Barge Confirmation
Resources
2 Field Engineer: 336hrs
1 Lead Engineer: 24hrs
1 Drafter: 80hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 24 days
Pipelay Procedure
21d
Constructability
Review
Analysis/Report
3d
Documentation/
First Rev.
Submission
10d
HAZID
Reviewed by
Company
7d
Issued for Approval
Readiness Review
Pipelay Commence
Structure (On-Bottom Analysis)
Sample of Process Flow
AFC Drawings
Consultant Report
Soil Report
Fabrication WCR
Specification
On-Bottom
Analysis
7d
Jacket Model
21d
Analysis/Report
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
3.5d
Resources
1 Structure Engineer: 248 hrs
1 Lead Engineer: 16hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 31 days
Issued for Approval
Structure (Upending)
Sample of Process Flow
AFC Drawings
Jacket Upending
Consultant Report
5d
Sling Confirmation
Single Block
WCR
Crane Barge
Confirmation
Jacket Main model
Double Block
8d
Analysis
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
Resources
1 Structure Engineer: 128hrs
1 Lead Engineer: 24hrs
1 Drafter: 40hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 16 days
7d
Issued for Approval
Structure (Transportation Study)
Sample of Process Flow
Transportation
Study
AFC Drawings
Consultant Report
General
Arrangement
Fabrication WCR
Jacket/Topside
Piles
15d
10d
Sea State
Analysis/Report
Analysis/Report
Barge Confirmation
Load-out Info
3d
2d Resources
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Issued for Approval
1 Marine Engineer: 144hrs
1 Lead Engineer: 24hrs
1 Drafter: 144hrs
1 Lead Drafter: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 18 days
7
Structure (Conductor Hang-off)
Sample of Process Flow
AFC Drawings
Consultant Report
Conductor Make-up
Hanger Selection
Specification
Conductor Hang-off
Analysis
15d
Report/Analysis
2d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Issued for Approval
Resources
1 Structure Engineer: 136hrs
1 Lead Engineer: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 17 days
Structure (Pile Drivability Study)
Sample of Process Flow
Pile make-up
Hammer Details
Soil report
Sea state Criteria
(underwater Piles)
Piles Drivability
Analysis
7d
Report/Analysis
2d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
3.5d
Resources
1 Structure Engineer: 72hrs
1 Lead Engineer: 16hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 9 days
Issued for Approval
Structure (Pile Upending)
Sample of Process Flow
Pile Make-up
Barge Info
General
Arrangement
Sea state Criteria
Crane Lift Chart
Clamp Details
Piles Upending
15d
Report/Analysis
3d
Documentation/
First Rev.
Submission
10d
Reviewed by
Company
7d
Issued for Approval
Resources
1 Marine Engineer: 144hrs
1 Lead Engineer: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 18 days
10
Structure ( Jacket/Topside Installation
Procedure) Sample of Process Flow
Constructability
Review
AFC Drawing
Rigging Calculation
Final WCR
Consultant Design
Report
14d
Info From
Fabricator
Loadout
Coordination
Manual
Rigging Calculation
Total Duration for first
submission = 31 days
3d
Documentation/
First Rev.
Submission
HAZID
Resources
2 Field Engineer: 448hrs
1 Lead Engineer: 24hrs
1 Drafter: 112hrs
1 Clerk/QA: 16hrs
14d
Installation
Procedure
10d
Reviewed by
Company
7d
Issued for Approval
Readiness Review
Installation
Commence
11