This document discusses methods for evaluating the required generating capacity of a power system to ensure adequate supply. It covers static and operating capacity requirements, generation system adequacy evaluation models, capacity outage probability tables, expected load loss calculations, and loss of load expectation as a risk index. The key points are:
- Static capacity looks at long-term overall system needs while operating capacity evaluates short-term actual capacity required to meet load.
- Models combine generation and load data to calculate outage probabilities and expected energy curtailment.
- Capacity outage tables show availability levels and probabilities at different capacity states.
- Loss of load expectation is the expected number of days that load exceeds available capacity in a given period.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
550 views85 pages
Generation System Adequacy Evaluation
This document discusses methods for evaluating the required generating capacity of a power system to ensure adequate supply. It covers static and operating capacity requirements, generation system adequacy evaluation models, capacity outage probability tables, expected load loss calculations, and loss of load expectation as a risk index. The key points are:
- Static capacity looks at long-term overall system needs while operating capacity evaluates short-term actual capacity required to meet load.
- Models combine generation and load data to calculate outage probabilities and expected energy curtailment.
- Capacity outage tables show availability levels and probabilities at different capacity states.
- Loss of load expectation is the expected number of days that load exceeds available capacity in a given period.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 85
Objective : to determine the required amount of system
generating capacity to ensure an adequate supply.
1. Static Capacity Requirement : Long-term evaluation of the overall system requirement. Practice : Percentage Reserve method. Issue : comparison Probabilistic approaches. 2. Operating Capacity Requirement Short term evaluation of the actual capacity required to meet a given load. Fundamental difference: Time period
Generation System Adequacy Evaluation Generation System Adequacy Evaluation
The Generation and Load models are combined to form Risk model Binomial Distribution P(H) + P(T) = [P(H) + P(T)] 1 P(H).P(H) + 2P(H).P(T) + P(T).P(T) = P 2 (H) + 2P.(H)P(T) + P 2 (T) = [P(H) + P(T)] 2
P 3 (H) + 3P 2 (H)P(T) + 3P(H)P 2 (T) + P 3 (T) = [P(H) + P(T)] 3 Ex. Consider a system with 4 components. The components are identical with a success probability of 0.9 and a failure probability of 0.1 Obtain the various states in which the components can exist. Since there are 4 components and each one of them is either available OR unavailable, the total number of states is All components working 1 component failed 2 components failed 3 components failed All components failed
(S+F) 4 = S 4 +4S 3 F+6S 2 F 2 +4SF 3 +F 4
System state Individual Probability All components working 0.94 = 0.6561 1 component failed 4X0.93X0.1 = 0.2961 2 components failed 6X0.92X0.12 = 0.0486 3 components failed 4X0.9X0.13 =0.0036 All components failed 0.14 = 0.0001 1.0000 If at least three components are required for success then Success Probability OR Reliability R R = 0.6561 + 0.2916 = 0.9477 Failure probability of the system Q Q = 0.0486 + 0.0036 + 0.0001 = 0.0523 = 1 R Capacity Outage Probability Table An array of capacity levels and the associated probabilities of existence. Ex. A small generating plant is o be designed to satisfy a constant 10 MW load. Four alternatives are under consideration as shown below. Obtain the capacity outage probability table. Assume that the probability of a unit failing is the same for all the units and is equal to 0.02 Alternative Capacity A 1 X 10 MW B 2 X 10 MW C 3 X 5 MW D 4 X 10/3 MW FOR = 0.02 Availability = 0.98 Binomial function = (S + F) 2
Case Units out Capacity Individual Probability Out available A 1 X 10 MW 0 0 10 0.98 1 0.02 B 2 X 10 MW 0 0 20 0.9604 1 10 10 0.0392 2 20 0 0.0004 C 3 X 5 MW 0 0 15 0.941192 1 5 10 0.057624 2 10 5 0.001176 3 15 0 0.000008 D 4 X 10/3 MW 0 0 40/3 0.92236816 1 10/3 10 0.07529536 2 20/3 20/3 0.00230496 3 10 10/3 0.00003136 4 40/3 0 0.00000016
Expected Load Loss
Case Capacity Out (MW) Probability
Load loss (MW)
Expected Load Loss (MW) A 1 X 10 MW 0 0.98 0 --- 10 0.02 10 0.2 0.2 MW B 2 X 10 MW 0 0.9604 0 --- 10 0.0392 0 --- 20 0.0004 10 0.004 0.004 MW C 3 X 5 MW 0 0.941192 0 ---- 5 0.057524 0 ----- 10 0.001176 5 0.00588 15 0.000008 10 0.00008 0.00596 MW D 4 X 10/3 MW 0 0.92236816 0 ------ 10/3 0.07529536 0 ------ 20/3 0.00230496 10/3 0.00768320 10 0.00003136 20/3 0.00020907 40/3 0.00000016 10 0.00000160 0.0078938 7 MW Let the cost per 10 MW unit be 1 unit. The investment cost for the alternatives is Investment cost of plant
Expected Load curtailment
System Expected Load Loss (MW) Investment cost p.u. 1 X 10 MW 0.2 1.0 2 X 10 MW 0.004 2.0 3 X 5 MW 0.00596 1.5 4 X 10/3 MW 0.00789387 1.33 System Probability of loss of load Expected load curtailment hr/yr 1 X 10 MW 0.02 175.2 2 X 10 MW 0.0004 3.504 3 X 5 MW 0.001184 10.37814 4 X 10/3 MW 0.00233648 20.46756 Effect of unavailability
System 1X10 MW 2X10 MW 3X5 MW 4X10/3 MW Unavailabili ty % Expected Load loss, MW 2 0.2 0.004 0.00596 0.00789387 4 0.4 0.016 0.02368 0.03112407 6 0.6 0.036 0.05292 0.06909417 Ex. A system consists of three 20 MW units with a FOR of 4%. Obtain the capacity outage probability table. (COPT). If a 4 th unit of 40 MW with an FOR of 4%, is added to the system, obtain the COPT on a 100 MW installed capacity. Table A
Table B
Sl. No Capacity Available Capacity out Probability 1 60 0 0.884736 2 40 20 0.110592 3 20 40 0.004608 4 0 60 0.000064 Sl No Capacity available Capacity out Probability 1 40 0 0.96 2 0 40 0.04 Table C
State Capacity available Capacity out How obtained Probability a 100 0 1(a),1(b) 0.8493465 b 60 40 1(A), 2(B) 0.0353894 c 80 20 2(A), 1(B) 0.1061683 d 40 60 2(A), 2(B) 0.0044236 e 60 40 3(A), 1(B) 0.0044236 f 20 80 3(A),2(B) 0.0001843 g 40 60 4(A),1(B) 0.0000614 h 0 100 4(A), 2(B) 0.0000025 Table D
State Capacity availabl e Capoacit y out How obtain ed Probability (state) Cumulativ e probability i 100 0 a 0.8493465 1.00 ii 80 20 c 0.10616863 0.1506534 iii 60 40 b+e 0.039813 0.0444851 iv 40 60 d+g 0.004485 0.004672 v 20 80 f 0.0001843 0.0001868 vi 0 100 h 0.0000025 0.0000025 Ex. A system consists of two 3 MW units with a FOR of 2%. Obtain the capacity outage probability table. (COPT). If a 3 rd unit of 5 MW with an FOR of 2%, is added to the system, obtain the COPT. Also obtain the COPT in the increments of 5 MW Table 1. COPT for two units
Table 2. COPT with 5 MW unit in service
Capacity Out Probability 0 0.9604 3 0.0392 6 0.0004 Capacity Out Probability 0+0 = 0 MW (0.9604) X (0.98) = 0.941192 3 + 0 = 3 MW (0.0392) X (0.98) = 0.038416 6 + 0 = 6 MW (0.0004) X (0.98) = 0.000392
= 0.980000 Table 3. COPT with 5 MW out of service
Table 4. COPT with all the units Capacity Out Probability 0+5 = 5MW (0.9604) X (0.02) = 0.019208 3 + 5 = 8 MW (0.0392) X (0.02) = 0.000784 6 + 5 = 11 MW (0.0004) X (0.02) = 0.000008 = 0.020000 Capacity Out Probability Cumulative Probability 0 0.941192 1.000000 3 0.038416 0.058808 5 0.019208 0.020392 6 0.000392 0.001184 8 0.000784 0.000792 11 0.000008 0.000008 Table 5. Rounded table
Capacity Out Probability 0 0.9565584 5 0.0428848 10 0.0005552 15 0.0000016 Comparison of percentage reserve margin and largest unit reserve criteria system 1, 24 x 10 MW units each having a FOR of 0.01 system 2. 12 x 20 MW units each having a FOR of 0.01 system 3, 12 x 20 MW units each having a FOR of 0.03 system 4,22 x 10 MW units each having a FOR of 0.01
Loss of Load Indices The generation system model is convolved with an appropriate load model to produce a system risk index. The risk indices depends upon the nature of load model. Sample types of load models Daily peak load variation curve. Each day is represented by its daily peak load. Individual peak loads arranged in descending manner forming a cumulative model daily peak load variation curve.
Load duration curve. Individual hourly loads are used. Area under the curve represents the energy required in the given period. Loss of Load Expectation (LOLE) The expected number of days in the specified period in which the daily peak load will exceed the available capacity. Capacity Outage loss of generation which may or may not result in a loss of load. This depends on the generating capacity reserve margin. Loss of load occur only when the capability of the generating capacity remaining in service is exceeded by the system load. The applicable system capacity outage probability table is combined with the system load characteristics to give an expected risk of loss of load.
Where C i = available capacity on day I L I = forecast peak load on day I P i (C i L i ) = probability of loss of load on day i. ( obtained from the capacity outage cumulative probability table)
Ex. A system consists of two units of 25 MW each and one unit of 50 MW with a FOR 0.02. Obtain LOLE with the load data given in table 1 below. Capacity Out Cumulative Probability 0 1.000000 25 0.058808 50 0.020392 75 0.000792 100 0.000008 Table 2 LOLE from daily peak load variation curve.
Q k - magnitude of kth outage in the system COPT t k number of time units in the study interval that an outage of magnitude Q k would result in a loss of load. The load model is a represented by a continuous curve for 365 days.
P k cumulative outage probability for capacity state Q k Ex. Consider a system containing five 40 MW units each with a FOR of 0.01. the COPT for the system is given in the table 3. The system load model is represented by the daily peak load variation curve shown in the figure. Obtain LOLE if the forecast peak load is 160 MW 100 % means 365 days on the x - axis and 160 MW on the y - axis.
LOLE using individual probability The LOLE is 0.0412413 % of the time base unit. With 365 days year, the LOLE will be 0.150410 days. LOLE using Cumulative Probability Capacity out Capacity In Cumulative Probability Time interval T k LOLE 0 200 1.000000 0 ---------- 40 160 0.049009 0 ---------- 80 120 0.000980 41.7 0.0408660 120 80 0.000009 41.7 0.0003753 0.0412413 % Table 4. The LOLE obtained is identical to the value obtained with the value obtained with individual probability. Examples A power system contains the following generating capacity. 3 X 40 MW hydro units FOR = 0.005 1 X 50 MW thermal units FOR = 0.02 1 X 60 MW thermal unit FOR = 0.02 The annual daily peak load variation curve is given by a straight line from the 100 % to the 40% point. Calculate the loss of load expectation for the following peak load values. a. 150 MW b. 160 MW c. 170 MW d. 180 MW e. 190 MW f. 200 MW. Table 5. Variation in risk as a function of peak load Sensitivity Studies Fig 1. Variation in risk with system peak load, drawn on a semi log sheet Table 6 . Effect of FOR and System Peak Load The system used is very small hence the effect of generating unit unavailability is quite pronounced. The effect for a big system with large units having high FORs is shown in the fig. 2 The total installed capacity of the system is 10100 MW The largest units have 300 MW and 500 MW capacity with FOR varying from 4 % to 13%. The risk profile is almost a straight line. This is because, a large system with a wide range of unit sizes has a more continuous COPT resulting in a smoother risk profile.
Fig 2. LOLE as a function of FOR The system peak load carrying capability (PLCC) The PLCC at a risk level of 0.1 day/year is 9006 MW for FOR of 0.04. Table 7 shows the change in PLCC for FOR values from 0.04 to 0.13. the decrease in PLCC is 815 MW.
FOR % PLCC (MW) Difference (MW) Cumulative difference MW 4 9006 ------ ------ 5 8895 111 111 6 8793 102 213 7 8693 100 313 8 8602 91 404 9 8513 89 493 10 8427 86 579 11 8345 82 661 12 8267 78 739 13 8191 76 815 Table 7 . Changes in PLCC If the forecast peak load is 9000 MW and the FOR of the large units are 0.13, an additional capacity of approximately 1000 MW has to be installed. The investment has to be therefore increased to meet the new demand. This clearly shows the consequences of the unit unavailability in terms of additional capacity.
Capacity Expansion Analysis Time required for designing, construct and commissioning a large power station takes normally 5 10 years. Consider a plant with five 40 MW units whose COPT is shown in table 8
Table 8 It is decided to add additional 50 MW units with FOR 0.01, to meet a projected load growth of 10 %. The question- In what years must the units be committed in order to meet the accepted system risk level? Table 9 shows the change in risk level for with the sequential addition of 50 MW units. Table 9. The change in risk level with sequential addition of 50 MW units System Peak Load (MW) LOLE (days/year) 200 MW 250 MW 300 MW 350 MW 100 0.001210 ---- ---- ---- 120 0.002005 ---- ---- ---- 140 0.08686 0.001301 ---- ---- 160 0.1506 0.002625 ---- ---- 180 3.447 0.06858 ---- ---- 200 6.083 0.1505 0.002996 ---- 220 ---- 2.058 0.03615 ---- 240 ---- 4.853 0.1361 0.002980 250 ---- 6.083 0.1800 0.004034 260 ---- ---- 0.6610 0.01175 280 ---- ---- 3.566 0.1075 300 ---- ---- 6.082 0.2904 320 ---- ---- ---- 2.248 340 ---- ---- ---- 4.880 350 ---- ---- ---- 6.083 Year number Forecast peak load (MW) 1 160 2 176 3 193.6 4 213.0 5 234.3 6 257.5 7 283.1 8 311.4 Table 10. Load growth at 10 % Fig 3. Variation in risk with unit additions. If it is accepted that an installed capacity of 200 MW is adequate for a system peak load of 160 MW, the risk criterion is 0.15 days/year. Choosing this risk criterion, the timing of unit additions can be obtained. The actual choice of the risk value is a management decision. In the present case, 50 MW additions can be made in the years 2,4 and 6 The expansion is shown in the table 11. Table 11. Generation expansion results Year Unit added (MW) System capacity (MW) Peak Load (MW) LOLE (days/year) 1 ----- 200 160 0.15 2 ----- 200 176 2.9 50 250 176 0.058 3 ----- 250 193.6 0.11 4 ----- 250 213 0.73 50 300 213 0.011 5 ----- 300 234.3 0.11 6 ----- 300 257.4 0.55 50 350 257.4 0.009 7 ----- 350 283.1 0.125 8 ----- 350 311.4 0.96 Perturbation Effects Large units have relatively low cost per KW installed. Large units have better heat rates than the smaller units. However, the impact on the system reliability by adding a large unit should be considered when carrying out economic evaluation of alternate sizes. This effect is considered in Increased Peak Load Carrying Capacity due to unit additions. (IPLCC)
The IPLCC values with each 50 MW unit at a system risk level of 0.1 is shown in table 12.
Table 12. IPLCC for five unit system. System Capacity (MW) Available peak load (MW) Increase in PLCC (MW) Individual Cumulative 200 144 0 0 250 186 42 42 300 232 46 88 350 279 47 135 Consider a large system with 20 10 MW units. The total installed capacity = 200 MW With the criterion of loss of largest unit , this system can carry a 190 peak load. The initial load carrying capability is different than the 5 unit system The addition of each 50 MW unit has a different IPLCC Initial PLCC penalty
Table 13. IPLCC for 20 unit system. System Capacity (MW) Available peak load (MW)
Increase in PLCC (MW)
Individual Cumulative 200 184 0 0 250 202 18 18 300 250 48 66 350 298 48 114 Scheduled Outages If the units are removed from the service for periodic inspection/maintenance, the capacity available during this period is not the same as that during the other period. Hence a single COPT is not applicable. The year is divided into several periods and the LOLE is calculated for each period. The annual risk index is obtained as
Modified capacity model is obtained by creating new COPT for each capacity condition.
If a new unit is added to the system, the same can be added to the capacity model also. If the actual in-service date of the new unit is uncertain, it can be represented by a probability distribution function and LOLE is obtained as
Alternate method
Another alternate method
Most realistic approach is to obtain the COPT by considering the units actually available in a given period. Other methods give a higher risk value which increases with increased maintenance capacity.
Maintenance Scheduling.
While scheduling the maintenance, the important point to be considered is that, the reliability of a system becomes poorer if a unit with low FOR is removed from service. Approaches for maintenance scheduling: 1. To reduce the total installed capacity by the expected capacity loss rather than by the actual unit capacity and then schedule maintenance on a constant reserve base. 2. Determine the decrease of PLCC at the appropriate risk level for each individual unit on maintenance and then using these values, schedule is prepared on a constant reserve basis.
Evaluation methods on period basis. Annual risk index can be obtained by using any of the three methods 1. Monthly (or period) basis considering maintenance 2. Annual basis neglecting maintenance 3. Worst period basis. Monthly approach : Constant capacity for the period is assumed. Appropriate COPT is combined with the load model. The annual risk is the sum of the 12 monthly risks. If the capacity on maintenance is not constant during the month, the month is divided into several intervals during which the capacity is constant. The COPT, modified by removing the units on maintenance for each separate interval, is combined with monthly peak and load characteristic using the interval as its time base.
Annual approach neglecting maintenance: The annual forecast peak load and the system load characteristics are combined with the system COPT. Basic assumption: a constant capacity exists for the entire period. Justification: The year can be divided into a peak load season and a light load season. The planned maintenance can be scheduled entirely during the light load season. The contribution of light load season to the annual risk is quite low and hence a constant capacity can be assumed. Worst Period Basis: The load level in a particular season or month may be so high that the same may dominate the annual figure. The risk value for that month is calculated. The annual risk level is obtained by multiplying this risk value by 12. Usually the worst period is December. 12 December Basis. Load Forecast Uncertainty Assumption that the actual peak load will differ from the forecast peak load with zero probability, is extremely unlikely to happen in the actual practice, as the forecast is actually predicted on past experience. Method 1: This uncertainty can be described by a probability distribution, whose parameters can be determined from past experience, future load modeling. The load forecast probability is divided into several class intervals. LOLE is computed for each load by multiplying the class interval and the probability of the load existing. The uncertainty is well described by a normal distribution. The distribution mean is the forecast peak load. The distribution is divided into a discrete number of class intervals. The load representing the class interval mid point is taken as the probability for that class interval.
Ex. A system consists of twelve 5 MW units, each with a FOR of 0.01. the forecast peak load is 50 MW. The COPT can be obtained
The uncertainty is normally distributed using a seven step approximation.
Period = 1 month = 30 days = 720 hours. Standard deviation is 2% of the forecast peak load = 1 MW. Monthly load-duration curve is represented by a straight line .
The LOLE is obtained as Probability of load X LOLE (hours/month for the load)
In general LOLE is affected by Generation unit unavailability (FOR) Load Forecast uncertainty. Hence the calculated value is only approximate. The actual distribution of LOLE can be obtained by Monte Carlo simulation
Loss of Energy Indices The area under the load duration curve represents the energy utilized during the specified period and can be used to determine the expected energy not supplied due to insufficient installed capacity.
The normalized LOEE is obtained as
Where E is the total energy under load duration curve. The energy index of Reliability EIR is EIR = 1 LOEE pu
Consider the LDC for a period of 100 hours and the generating unit capacity shown in the table The total energy in the period is 4575 MWh. If there were no units, the Expected Energy Not Supplied (EENS) is 4575 MWH. If the system contained only unit 1, the EENS is obtained as EENS with units 1 & 2 EENS with units 1,2 & 3 The expected energy produced by unit 3 is 401.7 64.08 = 337.6 MWh
Summary of EENS The expected energy not supplied is therefore 64.08 MWh. The energy index of reliability EIR is obtained as EIR = 1 (64.08/4575) = 0.985993 A generating contains three 25 MW generating units each with a 4 % FOR and one 30 MW unit with 5 % FOR. If the peak load for a 100 day period is 75 MW, what is the LOLE and EIR for this period? Assume that appropriate load characteristics is a straight line from the 100 % point to 60 % point.