Primavera EVMS

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 49

Earned Value Analysis

Presented by: Shuja Ali

IPECC Consultants
Project Management, Training & Contract
1
Workforce
Earned Value Analysis

What Is It ?

Why Do I Need It ?

How Do I Do It?
Today’s Situation

Need for accurate and consistent status


information
Numerous complex (and interrelated)
projects
 Projects with many WBS activities
 Virtual offices
 Diverse technology platforms

Shuja Ali:[email protected] 3
There’s Room For Improvement

70% of projects are:


•Over budget
•Behind schedule

52% of all projects finish at


189% of their initial budget

And some, after huge


investments of time and
money, are simply never
comple

Shuja Ali:[email protected] 4
How to answer the
question: “Have we done what
we said we’d do?”

% complete
estimating % of
Budget spent % of
work done % of
time elapsed
 subjective, incomplete
 draws false
conclusions

Shuja Ali:[email protected] 5
Enter Earned Value
Analysis
“Earned Value Analysis” is:
• an industry standard way to:
• measure a project’s progress,
• forecast its completion date and final cost,
and
• provide schedule and budget variances
along the way.

By integrating three measurements, it provides


consistent, numerical indicators with which you
can evaluate and compare projects.

Shuja Ali:[email protected] 6
What’s more Important?

Knowing where you


are on schedule?

Knowing where you


are on budget?

Knowing where you


are on work
accomplished?

Shuja Ali:[email protected] 7
EVA Integrates All Three

It compares the PLANNED amount of


work with what has actually been
COMPLETED, to determine if COST ,
SCHEDULE, and WORK ACCOMPLISHED
are progressing as planned.

Work is “Earned” or credited as it is


completed.

Shuja Ali:[email protected] 8
Earned Value needed
because...

Different measures of progress for


different types of tasks

Need to “roll up” progress of many


tasks into an overall project status

Need for a uniform unit of measure


(dollars or work-hours).

Shuja Ali:[email protected] 9
Earned Value needed
because...

Provides an “Early Warning” signal for


prompt corrective action.

 Bad news does not age well.

 Still time to recover

 Timely request for additional funds

Shuja Ali:[email protected] 10
And One More
Reason
Why You Need EVA

?
Shuja Ali:[email protected] 11
So, Is This Stuff New ?
It’s been around since the sixties.

“Cost/Schedule Control Systems


Criteria”
(C/SCSC)

Shuja Ali:[email protected] 12
Examples of informal Earned Value
Analysis

It’s done informally without realizing it.


•30% time used,
•30% $$ spent
•So, if 30% of the work is done, I must be
OK ??

•Shop floor estimates

•Cost comparisons
Budget vs. Actual

Shuja Ali:[email protected] 13
How’s this project doing?

120000

100000

80000

Projected
60000
Actual

40000

20000

0
Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03

Shuja Ali:[email protected] 14
But First! - We gotta get
organized

EVA works best when work is


‘compartmentalized’.

Compartmentalization is best achieved with


a well-planned Work Breakdown Structure.

So, how do I create a WBS for a really


complex project?
Shuja Ali:[email protected] 15
How am I gonna eat this
elephant?

Obviously in small
bites.

Shuja Ali:[email protected] 16
Proper WBS Design

One WBS per program


• Deliverable-oriented
• Work not in the WBS is out-of-scope
• Each descending level represents more
detail
Full (and accurate) definition is key
• Defined deliverable(s)
• Timeframe for delivery of product
• Total cost (direct and indirect) to deliver
product

Shuja Ali:[email protected] 17
A sample Work Breakdown
Structure
Serve Pizzas to Customers

Provide the Cook the Serve (Others)


Place Food Customers

Make the Cook the Build the Pizza


Dough Sauce

Shuja Ali:[email protected] 18
WBS Units are “Work Packages”

Lowest level WBS elements

Have an accompanying narrative

Have three measurable components


• Scope of work to be accomplished
• Total (direct and indirect) cost
• Timeframe for completion

Shuja Ali:[email protected] 19
Control Account Plans

A CAP is essentially a Work Package with some


added features:
 Assignment of responsibility
• Organization
• Individual
 Division (if necessary) into lower-level Work
Packages.
 Metrics for measuring EV performance
• Milestones
• % complete
• Other

 The sum of the CAPs constitutes the Performance


Measurement Shuja
Baseline
Ali:[email protected] 20
Enough With the WBS Stuff
Already !

We came here to talk about Earned


Value.
Shuja Ali:[email protected] 21
Some New Terms

BCWS - Budgeted Cost of Work


Scheduled

ACWP - Actual Cost of Work


Performed

BCWP - Budgeted Cost of Work


Performed

Shuja Ali:[email protected] 22
Earned Value Definitions

BCWS: “Budgeted Cost of Work


Scheduled”

Planned cost of the total amount of work


scheduled to be performed by the milestone
date.

Shuja Ali:[email protected] 23
BCWS - Budgeted Cost of Work
Scheduled

120000

100000

80000

60000 BCWS

40000

20000

Nov-03
Jul-03
Jan-03

Jun-03
Mar-03
Apr-03

Oct-03
Feb-03

May-03

Aug-03
Sep-03

Dec-03

Shuja Ali:[email protected] 24
Earned Value Definitions
(cont.)

ACWP: “Actual Cost of Work


Performed”

Cost incurred to accomplish the work that has


been done to date.

Shuja Ali:[email protected] 25
ACWP - Actual Cost of Work Performed

120000

100000

80000
56000 BCWP
60000
ACWP
49000
40000

20000

Nov-03
Jun-03
Jul-03
Jan-03
Feb-03
Mar-03
Apr-03
May-03

Aug-03
Sep-03

Oct-03

Dec-03

Shuja Ali:[email protected] 26
Earned Value Definitions
(cont.)

BCWP: Budgeted Cost of Work Performed

The planned (not actual) cost to complete the


work that has been done.

Shuja Ali:[email protected] 27
BCWP - Budgeted Cost of Work
Performed

120000

100000

80000
55000 BCWP
60000
49000 BCWS
40000

20000

Nov-03
Jul-03
Jan-03

Jun-03

Oct-03

Dec-03
Feb-03
Mar-03

Apr-03

May-03

Aug-03
Sep-03

Shuja Ali:[email protected] 28
The Whole Story

120000

100000

80000
56000 BCWS
60000 BCWP
55000
49000 ACWP
40000

20000

Nov-03
Jul-03
Jan-03

Jun-03
Feb-03
Mar-03

May-03

Aug-03
Sep-03

Dec-03
Apr-03

Oct-03

Shuja Ali:[email protected] 29
Some Derived Metrics

SV: Schedule Variance (BCWP-BCWS)


 A comparison of amount of work performed
during a given period of time to what was
scheduled to be performed.
 A negative variance means the project is

behind schedule

CV: Cost Variance (BCWP-ACWP)


 A comparison of the budgeted cost of work
performed with actual cost.
 A negative variance means the project is over

budget.
Shuja Ali:[email protected] 30
Schedule Variance & Cost Variance

Schedule Variance = BCWP-BCWS


$49,000
- 55,000
SV = - $ 6,000

Cost Variance = BCWP-ACWP


$49,000
56,000
CV = - $7,000

Shuja Ali:[email protected] 31
Some More Derived Metrics

SPI: Schedule Performance Index


SPI=BCWP/BCWS SPI<1
means project is behind schedule
CPI: Cost Performance Index
CPI= BCWP/ACWP CPI<1
means project is over budget

CSI: Cost Schedule Index (CSI=CPI x SPI)


The further CSI is from 1.0, the less likely project
recovery becomes.

Shuja Ali:[email protected] 32
Performance Metrics

SPI: BCWP/BCWS
49,000/55,000 = 0.891

CPI: BCWP/ACWP
49,000/56000 = 0.875

CSI: SPI x CPI


.891 x .875 = 0.780

Shuja Ali:[email protected] 33
Making Projections
Once a project is 10% complete, the
overrun at completion will not be less
than the current overrun.

Once a project is 20% complete,


the CPI does not vary from its current
value by more
than 10%.

The CPI and SPI are statistically accurate


indicators of final cost results.

Source: Defense Acquisition University


Shuja Ali:[email protected] 34
Making Projections
120000
103865
100000 102000
90882
80000
BCWS
60000 Today BCWP
ACWP
40000

20000

Nov-03
Jan-03

Jun-03

Jul-03

Oct-03

Dec-03
Feb-03
Mar-03
Apr-03
May-03

Aug-03
Sep-03

Shuja Ali:[email protected] 35
Estimate to Complete
140000
120000 116,571
100000 102000
BCWS
80000
Today BCWP
60000
ACWP
40000
20000
0
03
03

04
3

4
3

03
3
-0

-0
l-0
-0

v-
n-

n-
p-
ar

ar
ay

Ju

No
Ja

Ja
Se
M

M
M

Shuja Ali:[email protected] 36
A New Criteria

Activities “earn value” as they are completed.


The value earned is the WBS budgeted cost of
the activity completed to date.

Shuja Ali:[email protected] 37
Value of Earned Value

Schedule Status
Reporting
Cost Status Reporting
Forecasting

Shuja Ali:[email protected] 38
But How Do I Do All This Stuff
?

With an Earned Value Management System


Shuja Ali:[email protected] 39
Shuja Ali:[email protected] 40
Shuja Ali:[email protected] 41
Shuja Ali:[email protected] 42
Shuja Ali:[email protected] 43
Shuja Ali:[email protected] 44
Shuja Ali:[email protected] 45
Requirements of Earned
Value

Proper WBS Design


Baseline Budget Control Accounts
Baseline Schedule
Work measurement by Control
Account
 work-hours, dollars, units, etc.
Good Project Management
Practices
Shuja Ali:[email protected] 46
Shortcomings of Earned Value

Quantifying/measuring work
progress can be difficult.

Time required for data


measurement, input, and
manipulation can be considerable.

Shuja Ali:[email protected] 47
Summary
EVA & EVMS will help reduce guesswork in:
 Measuring performance
 forecasting
Need to get beyond misleading measures of
progress.
Reasons to use EVA and EVMS:
 Good project management practice
 OMB requirement
Incorporate into contracts

Shuja Ali:[email protected] 48
Earned Value Analysis

Questions/Discussion

Shuja Ali:[email protected] 49

You might also like