Primavera EVMS
Primavera EVMS
Primavera EVMS
IPECC Consultants
Project Management, Training & Contract
1
Workforce
Earned Value Analysis
What Is It ?
Why Do I Need It ?
How Do I Do It?
Today’s Situation
Shuja Ali:[email protected] 3
There’s Room For Improvement
Shuja Ali:[email protected] 4
How to answer the
question: “Have we done what
we said we’d do?”
% complete
estimating % of
Budget spent % of
work done % of
time elapsed
subjective, incomplete
draws false
conclusions
Shuja Ali:[email protected] 5
Enter Earned Value
Analysis
“Earned Value Analysis” is:
• an industry standard way to:
• measure a project’s progress,
• forecast its completion date and final cost,
and
• provide schedule and budget variances
along the way.
Shuja Ali:[email protected] 6
What’s more Important?
Shuja Ali:[email protected] 7
EVA Integrates All Three
Shuja Ali:[email protected] 8
Earned Value needed
because...
Shuja Ali:[email protected] 9
Earned Value needed
because...
Shuja Ali:[email protected] 10
And One More
Reason
Why You Need EVA
?
Shuja Ali:[email protected] 11
So, Is This Stuff New ?
It’s been around since the sixties.
Shuja Ali:[email protected] 12
Examples of informal Earned Value
Analysis
•Cost comparisons
Budget vs. Actual
Shuja Ali:[email protected] 13
How’s this project doing?
120000
100000
80000
Projected
60000
Actual
40000
20000
0
Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03
Shuja Ali:[email protected] 14
But First! - We gotta get
organized
Obviously in small
bites.
Shuja Ali:[email protected] 16
Proper WBS Design
Shuja Ali:[email protected] 17
A sample Work Breakdown
Structure
Serve Pizzas to Customers
Shuja Ali:[email protected] 18
WBS Units are “Work Packages”
Shuja Ali:[email protected] 19
Control Account Plans
Shuja Ali:[email protected] 22
Earned Value Definitions
Shuja Ali:[email protected] 23
BCWS - Budgeted Cost of Work
Scheduled
120000
100000
80000
60000 BCWS
40000
20000
Nov-03
Jul-03
Jan-03
Jun-03
Mar-03
Apr-03
Oct-03
Feb-03
May-03
Aug-03
Sep-03
Dec-03
Shuja Ali:[email protected] 24
Earned Value Definitions
(cont.)
Shuja Ali:[email protected] 25
ACWP - Actual Cost of Work Performed
120000
100000
80000
56000 BCWP
60000
ACWP
49000
40000
20000
Nov-03
Jun-03
Jul-03
Jan-03
Feb-03
Mar-03
Apr-03
May-03
Aug-03
Sep-03
Oct-03
Dec-03
Shuja Ali:[email protected] 26
Earned Value Definitions
(cont.)
Shuja Ali:[email protected] 27
BCWP - Budgeted Cost of Work
Performed
120000
100000
80000
55000 BCWP
60000
49000 BCWS
40000
20000
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Dec-03
Feb-03
Mar-03
Apr-03
May-03
Aug-03
Sep-03
Shuja Ali:[email protected] 28
The Whole Story
120000
100000
80000
56000 BCWS
60000 BCWP
55000
49000 ACWP
40000
20000
Nov-03
Jul-03
Jan-03
Jun-03
Feb-03
Mar-03
May-03
Aug-03
Sep-03
Dec-03
Apr-03
Oct-03
Shuja Ali:[email protected] 29
Some Derived Metrics
behind schedule
budget.
Shuja Ali:[email protected] 30
Schedule Variance & Cost Variance
Shuja Ali:[email protected] 31
Some More Derived Metrics
Shuja Ali:[email protected] 32
Performance Metrics
SPI: BCWP/BCWS
49,000/55,000 = 0.891
CPI: BCWP/ACWP
49,000/56000 = 0.875
Shuja Ali:[email protected] 33
Making Projections
Once a project is 10% complete, the
overrun at completion will not be less
than the current overrun.
20000
Nov-03
Jan-03
Jun-03
Jul-03
Oct-03
Dec-03
Feb-03
Mar-03
Apr-03
May-03
Aug-03
Sep-03
Shuja Ali:[email protected] 35
Estimate to Complete
140000
120000 116,571
100000 102000
BCWS
80000
Today BCWP
60000
ACWP
40000
20000
0
03
03
04
3
4
3
03
3
-0
-0
l-0
-0
v-
n-
n-
p-
ar
ar
ay
Ju
No
Ja
Ja
Se
M
M
M
Shuja Ali:[email protected] 36
A New Criteria
Shuja Ali:[email protected] 37
Value of Earned Value
Schedule Status
Reporting
Cost Status Reporting
Forecasting
Shuja Ali:[email protected] 38
But How Do I Do All This Stuff
?
Quantifying/measuring work
progress can be difficult.
Shuja Ali:[email protected] 47
Summary
EVA & EVMS will help reduce guesswork in:
Measuring performance
forecasting
Need to get beyond misleading measures of
progress.
Reasons to use EVA and EVMS:
Good project management practice
OMB requirement
Incorporate into contracts
Shuja Ali:[email protected] 48
Earned Value Analysis
Questions/Discussion
Shuja Ali:[email protected] 49