Training Session On Water Treatment
Training Session On Water Treatment
Training Session On Water Treatment
1. 2.
RO PLANT: REVERSE OSMOSIS PLANT. GFD: GALLONS OF WATER FROM RO PLANT PER DAY PER FT SQUARE AREA OF RO MEMBRANE.
3.
FOULANTS: THE ELEMENTS IN WATER THAT IS LIKELY TO CAUSE DAMAGE TO THE TREATMENT EQUIPMENT (RESIN/MEMBRANE).
4.
5.
6. 7.
RAW WATER SOURCES & THEIR PECULIARITIES SOURCE DEEP WELL WATER SHALLOW WELL WATER RIVER LAKE SEA MUNICIPAL EFFLUENT DISSOLVED SUSPENDED ORGANIC IMPURITIES IMPURITIES IMPURITIES HIGH LOW LOW MODERATE LOW MODERATE V. HIGH LOW HIGH LOW HIGH SEASONAL MODERATE MODERATE LOW HIGH MODERATE MODERATE HIGH MODERATE LOW HIGH
CLASSIFICATION OF RAW WATER ANALYSIS IN VARIOUS CATEGORIES NON DISSOLVED IMPURITY DISSOLVED IMPURITY TSS, TURBIDITY, COLLOIDAL SILICA, COLOR, SMELL TDS, CALCIUM, MAGNESIUM, SODIUM, SILICA, CHLORIDES, SULPHATES, NITRATES, ALKALINITY, TOTAL HARDNESS COD, BOD, COLOR, SMELL
CALCIUM, MAGNESIUM
WATER TREATMENT METHODS AVAILABLE & WHICH IMPURITY IT CAN REMOVE. TREATMENT METHOD TUBE SETTLER & CLARIFIERS FILTERS SOFTENER DM PLANTS IMPURITIES REMOVED TSS, TURBIDITY, COLLOIDAL SILICA
TSS, TURBIDITY TOTAL HARDNESS TOTAL HARDNESS, TOTAL DISSOLVED SOLIDS, CALCIUM, MAGNESIUM, SILICA, ALKALINITY, CHLORIDES, SULPHATES TOTAL HARDNESS, TOTAL DISSOLVED SOLIDS, CALCIUM, MAGNESIUM, SILICA, ALKALINITY, CHLORIDES, SULPHATES BOD & COD FREE CHLORINE, COD, BOD, COLOR, SMELL ALKALINITY
RO PLANTS
FILTERS:
HEIGHT OF FILTERS IS USUALLY FIXED AT 1500 MM OR 2000 MM. SOFTENER: REQUIRES SOME CALCULATIONS AS FOLLOWS: FLOW RATE IN M3/HR =F DURATION BETWEEN REGENERATION HRS = T HENCE OUTPUT BETWEEN REGENERATION= F X T REFER TO SOFTENER RESIN GRAPHS TO GET REGENERATION LEVEL = SAY 150 G/L EXCHANGE CAPACITY = SAY @ 50 HENCE QUANTITY OF RESIN REQUIRED IN SOFTENER ( LITRES): = OUTPUT BETWEEN REGENERATION NET EXCHANGE CAPACITY
SELECT THE SOFTENER WITH THE NEAREST RESIN QUANTITY FROM SOFTNER CHART.
10
SIZING DM PLANTS: REQUIRES DETAILED CALCULATIONS. STEPS AS FOLLOWS: DATA: FLOW RATE IN M3/HR DETAILED CATIONIC & ANIONIC ANALYSIS HRS OF OPERATIONS BETWEEN REGENERATION QUALITY OF WATER REQUIRED DESIGN STEPS DECIDE THE SCHEME RESIN QUANTITY CALCULATIONS EQUIPMENT SIZING REGENERATION EQUIPMENT SIZING CHEMICAL CONSUMPTION
11
SIZING RO PLANTS: REQUIRES DETAILED CALCULATIONS. STEPS AS FOLLOWS: DATA COLLECTION: FLOW RATE IN M3/HR DETAILED CATION & ANIONIC ANALYSIS HOURS OF OPERATIONS QUALITY OF WATER REQUIRED DESIGN STEPS: RO PROJECTION FROM SOFTWARE DECIDE ON THE OVERALL SCHEME EQUIPMENT SIZING CHEMICAL CONSUMPTION SIZING CALCULATIONS
12
13
IT IS ESSENTIAL TO UNDERSTAND THE CONSTRUCTIONAL DETAILS & OPERATING STEPS IN ORDER TO SOLVE THE PROBLEM
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
47
48
49
50
51
52
53
54
56
57
58
59
60
61
62
63
64
DM REGENERATION SEQUENCE
OBJECTIVES OF REGENERATION
1 TO REMOVE ACCUMULATED FOREIGN
MATERIALS AND RESIN DUST. 2 TO INJECT ACID OR ALKALI TO CONVERT RESIN IN TO ACTIVATED FORM.
65
STEPS OF REGENERATION
1 BACKWASH.
2 REGENERATION INJECTION. 3 SLOW RINSE. 4 FAST RINSE
66
BACKWASH
RESIN IS FLUIDISED TO 40 TO 50 % BED EXPANSION. - ACCUMULATED DIRT, RESIN FINES
REMOVAL.
- RESIN BED IS HYDRAULICALLY
CLASSIFIED.
67
REGENERATION INJECTION.
- ACID OR ALKALI IS USED SAC : HCL OR H2SO4 WBA : NaOH SBA : NaOH
CONCENTRATION
WEAK RESINS : 0.5 % - 2.5% STRONG RESINS : 3.0 % - 5%
REGENERATION LEVEL
69
REGENERATION QUANTITY
FOR STRONG RESINS. RESIN VOL. (M3) X REGENERATION LEVEL (KG/M3).
X 115
70
71
FAST RINSE
- PURPOSE IS TO REMOVE EXCESS
REGENERANT FROM RESIN BED. SERVICE INLET WATER IS USED. FAST RINSE IS CONTINUED TILL DISIRED OUTLET QUALITY IS
OBTAINED
72
CO FLOW REGENERATION.
SERVICE INLET REGENERANT INLET
SERVICE OUTLET
REGENERANT OUTLET.
73
SERVICE INLET
REGENERANT OUTLET.
74
COFLOW REGENERATION
- LEAKAGE OF IONS IS HIGH
- TREATED WATER QUALITY IS NOT CONSISTENT. THROUGH OUT CYCLE.
75
76
COUNTER REGENERATION
- LEAKAGE OF IONS IS LOW. - TREATED WATER QUALITY IS CONSISTENT THROUGHT THE RUN.
77
ADVANTAGES OF A REVERSE OSMOSIS SYSTEM OVER DM We would like to propose an RO based treatment scheme in place of DM based system. We would like to highlight that the R.O. based treatment system shall be more beneficial in terms of following parameters : 1. Very less operating cost. (Enclosed an annexure on typical operating cost calculations for DM & RO) Less chemical handling and storage. Very less operational needs thus the manual Reverse Osmosis Plant shall suffice in place of an automatic DM Plant. Less civil work. Less area requirements. Reverse Osmosis system can take the marginal variations in feed water quality without affecting the treated water parameters. No need for any neutralisation pit. The RO reject & MB regeneration effluents can be directly taken to guard pond.
2. 3.
4. 5. 6.
7.
79
REVERSE OSMOSIS ( RO )
TOPICS :
- PRINCIPLES OF RO. - PRETREATMENT FOR RO. - OPERATION & MAINTAINANCE. - TROUBLE SHOOTING. - CASE STUDIES & DISCUSSIONS.
PRINCIPLES OF RO
- RO BASICS.
- TYPICAL RO ARANGEMENT - OPERATING ARANGEMENT. - DESIGN PARAMETERS. - SELECTION OF RO MODEL.
Reverse Osmosis
P
DILUTE SOLUTION
CONCENTRATED SOLUTION
P >
TYPICAL RO ARRANGEMENT.
PRETREATMENT
RO
POST TREATMENT
Block Diagram of RO
SALT WATER
OPERATING PARAMETERS
RECOVERY = PERMEATE FLOW = 0.75 OR 75 % FEED FLOW 10 M3/HR FEED PERMEATE 7.5 M3/HR
OPERATING PARAMETERS
RECOVERY = PERMEATE FLOW = 0.75 OR 75 % FEED FLOW PERMEATE 7.5 M3/HR 50 PPM
10 M3/HR
FEED
1000 PPM
SALT PASSAGE
= PERMEATE TDS FEED TDS = 0.05 OR 5 % SALT REJECTION = 100 - SALT PASSAGE = 95 %.
OPERATING PARAMETERS
RECOVERY = PERMEATE FLOW = 0.75 OR 75 % FEED FLOW 10 M3/HR FEED PERMEATE 7.5m3/hr.
OF 50 PPM AT 5 PSI
DESIGN PARAMETERS
FLUX GFD L/M2H
GFD
GFD
=
=
0.59 * L / M 2 H
8-10 FOR WASTE WATER &
SEAWATER.
< 14 FOR SURFACE < 18 FOR WELL WATER < 25 FOR PERMEATE.
DESIGN PARAMETERS
Industrial process water Production of potable water Food processing Waste treatment
Membrane manufactures
Dow Filmtec.,U.S.A. Fluid systems U.S.A. Hydranautics U.S.A. Osmonics inc U.S.A. Trisep USA. Saehan KOREA
O Ring
Mesh Spacer
Permeate Carrier Membrane
Outer Cover
BACKING MATERIAL
Reinforcing Fabric
120 micrometer
Membrane Assembly
In board connector
End cap
o rings
Reverse Osmosis Membranes - Types Cellulose Acetate Thin Film Composite Polysulfones
Benefits of R.O.
High recovery rates. Predictable water quality--regardless of TDS content. Simple operation and control. Limited chemical problems. No daily regeneration hassels. Can be skid mounted,hence less space. Very few components for maintenance. Less operator attention
Source of Water
Surface water
Lake or Pond River
Well Water
Shallow well Deep Well
Treated Effluent
RO System Design
Parameters required for designing :
Temperature (Max, Min & Average) Chlorine Residual Turbidity Suspended solids Color. Silt Density Index pH colliform Count (bacteria) Total Plate Count Calcium Magnesium Pottashium Iron
Manganese Barium Strontium Chlorite Sulfate Nitrate Ammonia Phosphate Fluoride Silica Total Dissolved Solids Hydrogen Sulfate Carbon Di Oxide
Note : Variation in these parameters should be noted and odours, traces of industrial pollutant, clay, sand, rust, or other unusual characteristics should be described.
System Design
The Reverse Osmosis system design process consists of three principal steps. Membrane selection Defining the R.O. configuration and operating conditions. Determining pretreatment requirements
4-2-1 Array
1st Bank
Feed 2000 mg/L 173 gpm
89 mg/L 98 gpm
RO System components
The basic expanded design of a single system includes the following: Raw water feed pump to supply water to the pre treatment Pre treatment system for Turbidity,TSS,Colloidal particles & Organic matter. Cartridge filter to remove micron size particle to control the SDI( Silt density index) of feed water Anti scalant dosing system. High pressure pump&feed control valve to pressurize the feed water. Membranes housed in Pressure tubes. -----continued.,
A reject control valve to control the recovery of the RO system. Askid to mount to all mechanical equipment . Flow indicators to measure permeate and reject flowrates. Pressure gauges for monitoring the differential pressures across the RO feed, reject and intermediate stages. Conductivity & pH meter for measuring the quality of the permeate water. And other necessary instruments for monitoring easy operation and critical parameters. A cleaning system consisting of Tank,CF,Pump and necessary instruments.
- IF IT IS PRESENT- REF : MATTER TO H.O. PEG. IRON & Mn - LESS THAN 0.1
1. BY MnO2 FILTER UP TO 1 PPM. 2. OXIDATION BY AIR, FOLLOWED BY FILTERATION MORE THAN 3 PPM
Pretreatment
Cartridge filter Dosing system
De-chlorination Filteration Pressure tubes Coagulation Clarification
Cartridge filter
RO hydra block
Membrances
Cleaning system
HP pumps
Control pannel
Post treanment
Product water
Waste brine
Operating Parameters
.Feed Pressure Concentration pH Temperature Concentration Flow Pressure Flow Pressure Concentration
Permeate
Concentrate
System Profile
The System Profile is a measurement of the permeate concentration from each individual vessel. Identifies which vessels in an array have high salt passage. A System Profile should be taken at startup, as a baseline record. Record complete system data whenever a System Profile is performed.
PROBING
Probing is done while the system is operating at normal conditions. Insertion is normally done from the end opposite the permeate collection manifold.
PROBING
Feed Con c.
Permeate
CONDUCTIVITY
= MEMBRANE DAMAGE
= MEMBRANE DAMAGE
MEMBRANE DAMAGE
TROUBLESHOOTING OF RO SYSTEM
Too high system recovery : Concentration Polarization Localized Salt Concentration Causes : Operator error Flow meter out of calibration Unnoticed change in Feed water composition
Troubleshooting of RO System
Common causes for high pH
Buildup of bacteria
RO element manufacturing problem Elements moved from their original marked position .
Troubleshooting of RO System
Causes of uniform rejection decline :
Cleaning mistakes
Troubleshooting of RO System
Severe membrane multiple problems: deterioration or
Instrumentation
Instruments used in an RO system pH Conductivity Rota meter. Pressure gauges. ORP Thermometer Level switches Flow switches Pressure switches Electrical control
R. O. PLANT LOGSHEET FORMAT (TYPICAL) DATEO/P R. W. AREA SMBS D. P. ANTI.D. P. G.F./D.M.F. C. F. R. O. BLOCK AREA HRS. NaOCl D. P. I/L FLOW I/L PR. O/L PR. O/L FRC ON/OFF ON/OFF O/L PR. O/L SDI O/L FRC ORP READING FEED PR. REJ. PR. PERMEATE FLOW REJ. FLOW PERMEATE COND. ON/OFF (LPM) (KG/CM2) (KG/CM2) (PPM) (KG/CM2) (PPM) (KG/CM2) (KG/CM2) (LPM) (LPM) (Microsiemens/cm)
SIGN. OF OPERATOR
SIGN. SUPERVISOR
130
D. M PLANT LOGSHEET FORMAT (TYPICAL) O/P HRS. R.W. AREA ALUM D.P. NaOCL D.P.I/L FLOW ON/OFF ON/OFF (M3/HR) DMF ACF I/L PR. O/L PR. I/L PR. O/L PR. O/L FRC (KG/CM2) (KG/CM2) (KG/CM2) (KG/CM2) (PPM) DATE SAC SBA I/L PR. O/L PR. I/L PR. O/L PR. O/LCOND. O/L Ph (KG/CM2) (KG/CM2) (KG/CM2) (KG/CM2) (m/cm2)
SIGN. OPERATOR
SIGN. OF SUPERVISOR
131
132
133
undesirable substances. The interior of a boiler is sometimes covered with an oil film to avoid corrosion during storage or transport. Lubricating grease is used when the tubes are rolled in the shell, cutting oils are used during manufacture, cleaners and rust inhibitors also employed; a special powder is used finally for the PRELIMINARY STAGES assembly of piping. 1. The interior of boilerproducts must be remain checked in order remove The excesses of the all these inside the to boiler. any remains. Moreover, scale, wood, Inaccessible places reached by in using water or air paper, rags and any should kind of be debris remain the boiler. It is under pressure. obvious that the elimination 2. Replace the glass level gauge a temporary gauge for the of these materials is necessary inby order to not infringe on good duration of the operation conditions. treatment. 3. Close the boiler. Fill the boiler with good quality feed water. In order to avoid any thermal shock, the temperature of water should be within a maximum of 10C (22F)
4.
Determine the quantity of water added to the boiler and add a sufficient quantity of Melrose Chemicals, Ltd A-420 or F-685 for the treatment in progress. Refer to the Technical Bulletin of the product used to know its solubility. When the necessary quantity of A-420 or F-685 is added, alkalinity "M" will be 3000 to 4000 ppm. 5. A concentrated solution of the cleaner can be added proportionally to the feed water while filling of the boiler. If there is an economiser in the system, the concentrated solution must be added to there directly. In the case of small boilers or when the conditions allow it, the concentrated solution can be added through a manhole or any other opening located at the top of the boiler. Do not add solids to a boiler. The use of A-420 liquid for an alkaline boil-out eliminates any problem from deposits incurred by the use of solid chemicals. 6. Read and follow closely the instructions of the manufacturer of the boiler concerning the firing stages and the evacuation of the vapours during an alkaline boil-out. 7. In the case of new boilers, the drying of refractory materials can be combined with the alkaline boil-out. Light a fire with wood to dry the boiler lining. Leave the chimney open until vapour appears - then close. If wood cannot be used, use oil. In installations where the oil is pulverized, it is often necessary to use a more easily controllable fuel.
The temperature of the furnace during the preliminary stages of boil-out must be low in order to obtain uniform drying - then can be gradually increased by varying the rate of fuel addition or firing period to maintain the minimum pressure necessary during the boil-out. The suggested maximum pressure is approximately 50% of the limit of pressure for the valve operating with the lowest pressure. This pressure will create sufficient circulation in boilers having a waterwall and a network of complicated internal piping.
8. It is difficult to precisely determine the optimal duration of an alkaline boiling. Experience shows that 1 to 3 days are generally necessary for the internal cleaning of a boiler. One prolonged period is better if drying of refractory materials is also carried out. The state and the appearance of the blowdown water of the boiler are the best indication in knowing if the treatment should be continued or stopped. 9. For the duration of the boiling, all the safety measures must be observed with regard to the superheaters, the economisers, etc. in order to avoid any damage with the equipment. The superheaters and the economisers should be operated in the same way as when the system is operating. Detailed attention should be given to the
at least every 8 hours. The total quantity of water removed from all these points should be roughly a quarter of the level indicated on the gauge, this quantity being also divided between the various drains and the continuous blowdown. First drain the continuous blowdown, then progressing toward the drains on lower level of the boiler. Following this operation, the water level in the boiler should be restored by using water containing the alkaline cleaner, so that the concentration of the cleaner in the boiler is not reduced by these regular purges. 11 At the end of the boiling, cool the boiler gradually, then drain and flush the system by using a water under high pressure. Check the cleanliness of the system and make sure that there are no remaining oils or greases. Experience showed