Suspension Bridges: Dora Mayfield CEVE 499
Suspension Bridges: Dora Mayfield CEVE 499
Suspension Bridges: Dora Mayfield CEVE 499
1.TWO TOWERS 2. THE CATENARY SYSTEM 3.A GROUND ANCHOR 4.A LEVEL TRUSS STIFFENED DECK 5.A DESIGN TO SUPPORT HEAVY LOADS
The Towers/Anchorages
The towers are the struts for the suspension bridge. They receive all of the compressive forces. These members have to be thick enough resist buckling, flexure, and oscillation. They have to withstand minor changes as a result of live loads and temperature changes. The main job of the towers is to withstand the forces that are exerted on it by the cables. The anchorages pull the side spans to the ground and fixes them in place.
The anchors must be able to hold down the cable with its weight or by transferring the tension in the ropes to the ground.
The Cables
All of the tension forces in the bridge is transferred to the main cable through the suspenders. The cables have to support the deck and live loads without having to overstress any member. The cables need to allow vibration and be resistant to corrosion.
The Deck
The deck needs to be ridge to prevent any dipping as live loads pass, yet it needs to be as light as possible. The deck is a major factor in calculating the dead load and tension in the main cable.
Structural Principles
A main cable of a suspension bridge resembles a parabola. The hangers, or suspenders, are placed at equal intervals from each other.
To calculate the height of each hanger, we can measure the two end heights, the center height, and get an equation for a parabola.
The moment of the weight of the anchor must be greater than that coming from the tension in the cable.
In other words, you want your anchor to be heavy enough to hold down the cables, regardless of what type of anchor you decided to use.
The Forces
The forces on the cables of a suspension bridge are all tension. The horizontal forces for each member are equal, and the vertical forces increase in the direction of the towers.
Finding Force
Calculating the force is a result of the length of the bridge and the weight of the deck. The tension at each end of the bridge carries half the weight of the bridge. The tension in the main cable is also a result of the height of the tower. (The higher you tower, the less tension at the top,but there will be a greater chance of buckling.)
Cable Materials
For a small projects, single rope or single strand wires can be used.
Implementation
Where the towers are founded on underwater piers, caissons are sunk and any soft bottom is excavated for a foundation. If bedrock cannot be reached, pilings are driven to bedrock or hard soil, or a large concrete pad may be constructed. The foundation piers are then extended to above water level. Where the towers are founded on dry land, deep foundations or pilings are used. From the tower foundation, towers of multiple columns are erected using concrete, stonework, or steel structures. At some elevation there must be a passage for the deck, with the columns extending high above this level. Smooth open cable paths called saddles are anchored atop the towers. These allow for slight movements of the cable as the loads change during construction. The top of these saddles may be closed with an additional part after completion of the bridge. Anchorages are constructed to resist the tension of the cables. These will have multiple protruding open eyebolts. A temporary suspended walkway supported by wire rope follows the curve of the cables to be constructed, mathematically described as a catenary arc. Another set of wire ropes are suspended above the walkway and are used to support a traveler that has wheels riding atop these cables. There will be one set of wire ropes and a traveler for each cable to be "spun" Pulling cables attached to winches are capable of pulling the traveler from one anchorage to the other, traveling in arcs to the tops of the two towers.
High strength wire, typically less than 1cm in diameter, is pulled in a loop by pulleys on the traveler, with one end affixed at an anchorage. When the traveler reaches the opposite anchorage the loop is placed over an anchor eyebolt. The traveler is returned to the start point to pick up another loop or it is used to carry a new loop from this side. As loops are placed, corrosion proofing may be applied. In this way a complete sub-cable is created linking the eye-bolt (or a set of eye bolts) from one anchorage to the other. The sub-cables will have a hexagonal cross section and are held together with temporary bindings. Multiple adjacent sub-cables are placed adjacent to each other. While these are on a hexagonal grid, the general form for the larger cable is circular. The entire cable is then compressed by a traveling hydraulic press into a closely packed cylinder and tightly wrapped with additional wire to form the final circular cross section. Saddles to carry the suspender cables are clamped to the main cables, each with an apropriate shape to conform to the slope of the main cables. Each saddle is an equal horizontal distance from the next, with spacing appropriate to the design of the deck. Suspender cables engineered and cut to precise lengths and carrying swedged ends are looped over the saddles. In some bridges, where the towers are close to or on the shore, the suspender cables may be applied only to the central span. Special lifting hosts attached to the suspenders or from the main cables are used to lift prefabricated sections of bridge deck to the proper level, provided that the local conditions allow the sections to be carried below the bridge by barge or other means, otherwise a traveling cantilever my be used to extend the deck one section at a time. During the construction the finished portions of the deck will appear to pitch upward rather sharply, as there is no downward force in the center of the span. Upon completion of the deck the added load will pull the main cables into an arc mathematically described as a parabola, while the arc of the deck will be as the designer intended - usually a gentle upward arc for added clearance if over a shipping channel, or flat in other cases such as a span over a canyon, With completion of the primary structure various details such as lighting, handrails, finish painting and paving are added.
http://www.sahale.com/
Completion of Tower 1 Implementation of hangers by Tower abutment after skyline concrete placement Preparing to place tower leg The completed bridge
Hanger Attachment (screws to adjust tension) Handrail suspender bar Implementation of deck
Advantages/Disadvantages
Cost All tension forces are in cables/ All compression forces are in towers Balancing the tensions during and after construction Rigidity Construction of cables
Sources
D B Steinman, A Practical Treatise on Suspension Bridges: Their Design, Construction, and Erection New York, London, J. Wiley & Sons; Chapman & Hall, 1929. Zalewski, Waclaw ; Allen,Edward, Shaping Structures: Statics New York : Wiley, 1998. http://www.inventionfactory.com/history/RHAbridg/sbtd/ http://www.brantacan.co.uk/index.htm http://www.pbs.org/wgbh/nova/bridge/meetusp.html http://www.icomos.org/studies/bridges.htm#13