Final AMHS Project

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 33

Singapore Polytechnic

Good Evening

ENGINEERING MANAGEMENT
Project Name : AMHS INSTALATION Team Members:
Ponnusamy Rajkumar (P1147117) Parameshwarn Prabhu ( P1147188) Nataraj Ranjithkumar (P1147360)

ENGINEERING MANAGEMENT
AUTOMATIC MATERIAL HANDING SYSTEM (AMHS)

INSTALLATION OF AMHS IN SEMICONDUCTOR INDUSTRY TO INCREASE PRODUCTIVITY

Introduction
In Todays fast growing world People like have every thing compact within their hands Semiconductors plays the major role with new technologies and innovations So we as a semiconductor manufacturer need to update in advance technological progress to survive in the market

Initially we were convention fab manufacturing 200mm wafers and decide to move to 300mm hi-tech

Project Synopsis
Initially with 200mm production capability of 4.3B, after we move 300mm increased our capacity by 16% to reach 5B because 300mm can yield more chips at low cost. This project is to install AMHS in semiconductor fab due to difficult in handling, transportation between department and storage of 300mm wafer

This project budget is $800k


With in 90days

MISSION
To install AMHS for easy handling transportation and storage in Three Months period Challenges
With out effecting current production Space Machines

Introduction for Manufacturing process in Semiconductor


Semiconductor Manufacturing is further divided into two major steps
Front End (45-60days to complete) Back End ( 15 days)

Manufacturing steps at front end


Clean up

Project Objects
A) Build in Team B) Plan & Schedule C) Find Place and Clear Place D) Vendor E) Laying Electrical Ducts & Control Panels F) AMHS Erection F) Testing G) Sample Run H) Handover to Production

Organize a Team

Roles of each Team Member


Sponsor: Ensure the project team has sufficient resource to work, also ensure the project is successful. Project Leader : Oversee and Lead the project activity is carried out within target completion, budget and manage the team members. Project Manager : To manage people and process and monitor Project Engineer : In-charge for assessing work requirement contractor Purchase Engineer : Source for vendor and raise PO Drawing Engineer : Prepare drawing Software Engineer : To install software and to in cooperate to existing Mechanical Engineer : Directly involve in machine installation, initial run and testing Process Engineer : Run evaluation and confirm machine quality and performance Production Engineer : Manpower allocation, actual run of initial and mass production Quality Engineer : Confirm product initial quality of product

Responsibility Matrix

Plan & Schedule


ACTIVITY A B C D E F G TASK PLAN FIND AND CLEAR PLACE SOURCE FOR VENDOR PLACE ORDER AND SHIPMENT FOUNDATION FOR AMHS ERECTION OF POWER DUCTS & DATA CONTROL PANNELS AMHS INSTALLATION DURATION IN (DAYS) 3 5 10 16 7 10 20 A B B&C D E E&F PREDECESSOR

H
I J

TESTING AND COMMISIONING


SAMPLE RUN RELEASE TO PRODUCTION

5
7 3

G
H I

AON (Activity-On-Node)
0 4 3 A 4 3 7 3 7 5 8 B 4 12 10 18 C 12 4 22 8

41 10 51 F 45 4 55

34 38

7 E 4

41 45

18 16 34 D 22 4 38

51 20 71 G 55 4 75

71

75

5 H 4

76

76

80

80

7 I 4

83

83

87

87

3 J 4

86

90

Microsoft Excel Project Schedule


Task
AMHS INSTALLATION
Plan Find & Clear Place Source Vendor Order and Shipment Foundation for AMHS Erection of Electrical, Data & Control Panels AMHS Installation Testing and Commissioning Sample Run Release to Production

Duration in Days
86
3 5 10 16 7 10 20 5 7 3

Start Date
5-Mar-12
5-Mar-12 8-Mar-12 15-Mar-12 29-Mar-12 23-Apr-12 3-May-12 18-May-12 15-Jun-12 22-Jun-12 3-Jul-12

End Date
5-Jul-12
7-Mar-12 14-Mar-12 28-Mar-12 20-Apr-12 2-May-12 17-May-12 14-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12

Work breakdown structure(WBS)

Costing
Find place and clear New machine Installation Contractor Materials Buffer $10k $300K $140K $100K $200K $50K

SWOT ANALYSIS

Strength Good Teamwork Collogues with good Experience R&D No complaints form customer

Weakness Lack of Machines Lack of quality staffs Not Globally recognized

Opportunities New Leadership UP grading skills To expand company

Treats Resignation of staffs Natural disaster Lose orders Economical crisis

Layout : Machine Location


AMHS Installed

Layout : Over head tracks and storage

Foundation For AMHS

Power ducts and Control Panels

Power duct

Control Panels

Tracks and Travelling units

Over head travelling tracks

Over head Travelling vehicle

Over head Storage Racks along tracks


Storage Location

Control

Integrated AMHS control system

AMHS Control Units

AMHS Storage and Processing Unit

Project Achievement
Lot Handling Before

After

Project Achievement
Transportation between departments Before

After

Project Achievement
Storage Before

After

Project Closing
The close-out responsibilities of each team member Details of the tasks to avoid missing out Follow-up on the outstanding matters Check on the quality of the various jobs Perform final inspection with the team or contractors involved.

Conclusion
We successfully converted to hi-tech fab with good team work and strength to achieve our goal with in 90 days and within budget AMHS reduced productivity human error and increased

With new investments 300 mm fab with hi-tech capacity expected to increase by 20% 2013 Globally recognized

THANK YOU