Final AMHS Project
Final AMHS Project
Final AMHS Project
Good Evening
ENGINEERING MANAGEMENT
Project Name : AMHS INSTALATION Team Members:
Ponnusamy Rajkumar (P1147117) Parameshwarn Prabhu ( P1147188) Nataraj Ranjithkumar (P1147360)
ENGINEERING MANAGEMENT
AUTOMATIC MATERIAL HANDING SYSTEM (AMHS)
Introduction
In Todays fast growing world People like have every thing compact within their hands Semiconductors plays the major role with new technologies and innovations So we as a semiconductor manufacturer need to update in advance technological progress to survive in the market
Initially we were convention fab manufacturing 200mm wafers and decide to move to 300mm hi-tech
Project Synopsis
Initially with 200mm production capability of 4.3B, after we move 300mm increased our capacity by 16% to reach 5B because 300mm can yield more chips at low cost. This project is to install AMHS in semiconductor fab due to difficult in handling, transportation between department and storage of 300mm wafer
MISSION
To install AMHS for easy handling transportation and storage in Three Months period Challenges
With out effecting current production Space Machines
Project Objects
A) Build in Team B) Plan & Schedule C) Find Place and Clear Place D) Vendor E) Laying Electrical Ducts & Control Panels F) AMHS Erection F) Testing G) Sample Run H) Handover to Production
Organize a Team
Responsibility Matrix
H
I J
5
7 3
G
H I
AON (Activity-On-Node)
0 4 3 A 4 3 7 3 7 5 8 B 4 12 10 18 C 12 4 22 8
41 10 51 F 45 4 55
34 38
7 E 4
41 45
18 16 34 D 22 4 38
51 20 71 G 55 4 75
71
75
5 H 4
76
76
80
80
7 I 4
83
83
87
87
3 J 4
86
90
Duration in Days
86
3 5 10 16 7 10 20 5 7 3
Start Date
5-Mar-12
5-Mar-12 8-Mar-12 15-Mar-12 29-Mar-12 23-Apr-12 3-May-12 18-May-12 15-Jun-12 22-Jun-12 3-Jul-12
End Date
5-Jul-12
7-Mar-12 14-Mar-12 28-Mar-12 20-Apr-12 2-May-12 17-May-12 14-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12
Costing
Find place and clear New machine Installation Contractor Materials Buffer $10k $300K $140K $100K $200K $50K
SWOT ANALYSIS
Strength Good Teamwork Collogues with good Experience R&D No complaints form customer
Power duct
Control Panels
Control
Project Achievement
Lot Handling Before
After
Project Achievement
Transportation between departments Before
After
Project Achievement
Storage Before
After
Project Closing
The close-out responsibilities of each team member Details of the tasks to avoid missing out Follow-up on the outstanding matters Check on the quality of the various jobs Perform final inspection with the team or contractors involved.
Conclusion
We successfully converted to hi-tech fab with good team work and strength to achieve our goal with in 90 days and within budget AMHS reduced productivity human error and increased
With new investments 300 mm fab with hi-tech capacity expected to increase by 20% 2013 Globally recognized