1. Two characters: indicates that the bar code has 21 digits. 2. Eight characters: indicates the part number of an ODU.
3. Two characters: indicates the EMS code of a supplier. "10" represents Huawei, "6C" represents RBW, and "4G" represents Comba.
Note: RBW (6C) ODUs and Comba (4G) ODUs are purchased, and XMC (10) ODUs are manufactured by Huawei. 4. Two characters: indicates the production date. The first character represents year and the second character represents month. "A" represents number 10, "B" represents number 11, "C" represents number 12, and so on. For example, "91" represents January, 2009; "AB" represents November, 2010. 5. Six characters: indicates a serial number.
Huawei Confidential
Page 2
Correct 21-digit bar code. If no 21-digit bar code is available, the provider is unable to confirm whether a replacement can be provided. Correct fault information. The correct fault information facilitates fault location. Fault information collection template: Fault Tag
Huawei Confidential
Page 3
For ODUs that fail in the engineering phase For ODUs that fail in the maintenance phase
Cases (Indonesia)
Complete process of how R&D analysis was reserved for Huawei-
Huawei Confidential
Page 4
Process of Handling Faulty Purchased ODUs That Fail in the Engineering Phase (Applicable to the Countries Outside China)
Huawei Confidential
Page 5
Contact person: Alice Tel No.: +6349 549 1560 Ext 373 Fax No.: +6349 549 0753 Email Add: [email protected]
Comba (4G)
Comba Telecom Limited C/O Wavelab 611 East Wing, No. 8 Science Park West Avenue Hong Kong Science Park, Shatin, Hong Kong Tel: +852-2116 6015 Fax: +852-2116 6055 Attn: Miss. Connie Li
Huawei Confidential
If an ODU not intentionally damaged is delivered within one year, the provider promises to provide a replacement for free. If the ODU is
delivered one year before but within two years, the provider repairs
the ODU for free. If the ODU is delivered two years before, the customer needs to pay for the repair.
The field engineers of Huawei must send out a faulty ODU within 70 days (subject to the date of the bill No.) after the provider sends out a replacement. Otherwise, the field engineers need to place a purchase order for the replacement provided by the provider.
Huawei Confidential
Page 7
REMEC Broadband Wireless International Inc (RBW) is a company in the USA. Replacements cannot be directly provided in some regions through a back-to-back process for the reason of USA trade restrictions. For the regions where replacements cannot be directly provided, field engineers of Huawei must state "back-to-back process is not applicable" when completing an SCM form, and the market coordination department directly supplements the field engineers with the replacements.
Huawei Confidential
Page 8
Huawei Confidential
Supplier
Huawei Confidential
Page 10
For ODUs that fail in the engineering phase For ODUs that fail in the maintenance phase
Cases (Indonesia)
Complete process of how R&D analysis was reserved for Huawei-
Huawei Confidential
Page 11
Process of Handling Faulty Purchased (RBW/Comba) ODUs That Fail in the Maintenance Phase
Field repair engineers need to hand faulty ODUs to the field service parts administrator and urge the field
service parts administrator to arrange for the repair as soon as possible. Meanwhile, the field service parts administrator requires the field engineers or the customer to complete a fault tag and a Service Parts Repair Request and pack the faulty ODUs correctly. The figure below shows the repair process of an outsourced microwave product.
Repair of outsourced microwave product (Recommended process II)
No
Repair
Repair request
Bonded warehouse
SPA
Allocate an RP number
Yes
Repair
Requireme nt handling
Deliver the PO
Repair dispatch
Repair order
Cancel the PO
Repair period: It is usually 45 days. Therefore, field engineers must observe the process above when a faulty ODU needs to be repaired.
Huawei Confidential
Page 12
For ODUs that fail in the engineering phase For ODUs that fail in the maintenance phase
Cases (Indonesia)
Complete process of how R&D analysis was reserved for Huawei-
Huawei Confidential
Page 13
2. The project team requests for the SCM Customer Problem Processing Procedure. The link is provided
as follows: http://w3.huawei.com/dominoapp/isc/problemfeedback/scmcustomerproblem.nsf/vwAllCaseList?OpenVie w&Start=1 [Owner]: Project team, Technical Support Dept, GTS Note: Write "R&D analysis required" in the E-flow. Then, the quality management sector at Huawei HQs will contact the R&D contact persons. R&D contact person for XMC ODUs: baibaozhi 00126114/huawei R&D contact person for purchased ODUs: wangzeming 00136337/huawei or yaojun 00176956/huawei 3. Materials Return Request Application E-flow [Owner]: The project team sends faulty units to the local supply chain contact person. Then, the local Delivery and Service Business Dept submits an application and writes down the following information: R&D analysis required; R&D contact person for XMC ODUs: baibaozhi 00126114/huawei; R&D contact person for purchased ODUs: wangzeming 00136337/huawei or yaojun 00176956/huawei [Note]: The regional supply chain sends faulty units to Hong Kong and provides an R&D contact person. The supply chain personnel in Hong Kong send the faulty units to Shenzhen. Then, guobaowei
Cargo Replacement Procedure --- GTS requesting for the Cargo Replacement Procedure
Snapshot: Click:
Huawei Confidential
Page 15
Huawei Confidential
Page 16
Complete a workflow for the faulty ODU to be analyzed. For how to complete the
workflow, see the operation guide in the attachment below. Snapshot: Click:
After completing the workflow, the repair engineer must track the state of the workflow. After the R&D engineer confirms in the workflow that the faulty ODU can be returned for analysis, the repair engineer hands the ODU to be analyzed to the local service parts warehouse, notifies the service parts administrator of performing operations according the return process and the number for the pre-appointment workflow of the ODU. The repair engineer requires the service parts administrator to raise a forward request according to the quantity of workflows of the ODU to be analyzed and the ODU BOM to supplement the field with goods.
Huawei Confidential
Page 17
For ODUs that fail in the engineering phase For ODUs that fail in the maintenance phase
Cases (Indonesia)
Complete process of how R&D analysis was reserved for Huawei-
Huawei Confidential
Page 18
Cargo Replacement Procedure --- GTS requesting for the Cargo Replacement Procedure
Serial No., for example, M2010080631 [Applicant]: Technical Support Dept, GTS (for example, weidai 00134448/huawei at the GTS in Indonesia) [Detailed Approval Log] 01 Basic Application Information 2010-9-1 17:21:24 jipeng 00153940 section 1 submit to section 2(Supervisor Review)bailiqing 00118580 02 supervisor review 2010-9-1 17:24:46 bailiqing 00118580 section 2 submit to section 3jipeng 00153940 03 Issue Resend/Return List 2010-9-1 17:35:40 jipeng 00153940 section 3 submit to section 6(Contract Input)lifangfang 60014740 06 Contract Input 2010-9-2 8:51:05 lifangfang 60014740 section 6 submit to section 7(Contract Coordinator)liqiong WX35453 07 Contract Coordinator Processing 2010-9-2 11:00:58 AM liqiong WX35453 section 7 submit to section 8(Contract Configuration Distribution )liqingping 00154075 08 Contract Coordinator Distribution 2010-9-2 13:44:46 liqingping 00154075 section 8 submit to section 9(Contract Configuration Engineer)zhaofengjun 00156685 09 Contract Configuration Engineer Processing 2010-9-2 15:20:27 zhaofengjun 00156685 section 9 submit to section 10(Intercompany Transaction)jiangyuxia 00119639 10 Intercompany Transaction Processing 2010-9-2 15:31:19 jiangyuxia 00119639 section 10 submit to section 11(Tracking Information)jipeng 00153940 hejinping 00150104
Huawei Confidential
Page 19
Huawei Confidential
Page 20
Huawei Confidential
Page 21
Huawei Confidential
Page 22
Huawei Confidential
Page 23
Including: The GTS hands the faulty ODU to the supply chain and the supply chain submits a workflow for approval and delivers the replacement ODU
Time spent in shipment from Hong Kong to Shenzhen: 1 workday Time spent in in-warehouse in Shenzhen: 1.5 workdays
The reverse logistic service in Shenzhen does not involve the delivery