Investment Criteria
Investment Criteria
Investment Criteria
Outline
Net present value Benefit cost ratio
The key steps involved in determining whether a project is worthwhile or not are:
Estimate the costs and benefits of the project Assess the riskiness of the project Calculate the cost of capital Compute the criteria of merit and judge whether
INVESTMENT CRITERIA
INVESTMENT CRITERIA
DISCOUNTING CRITERIA
NON-DISCOUNTING CRITERIA
PAYBACK PERIOD
n NPV = t=1
Ct Initial investment (1 + rt )t
Year
0 1 2 3 4 5 Pros
Naveen Enterprises Capital Project Cash flow Discount factor Present value -100.00 1.000 -100.00 34.00 0.870 29.58 32.50 0.756 24.57 31.37 0.658 20.64 30.53 0.572 17.46 79.90 0.497 39.71 Sum = 31.96 Cons
Is an absolute measure and not a relative measure
Reflects the time value of money Considers the cash flow in its entirety Squares with the objective of wealth maximisation
Properties of the NPV Rule NPVs are additive Intermediate cash flows are invested at cost of capital NPV calculation permits time-varying discount rates NPV of a simple project decreases as the discount rate increases.
Centre for Financial Management, Bangalore
Year 0 O G F H D Q S N
present value
Modified NPV
The standard net present value method is based on the assumption that the intermediate cash flows are re-invested at a rate of return equal to the cost of capital. When this assumption is not valid, the re-investment rates applicable to the intermediate cash flows need to be defined for calculating the modified net present value
NPV*
=
(1+ r)n
- I
The benefit cost ratio measures for this project are: 25,000 (1.12) BCR = 100,000 Pros Measures bang per buck Cons Provides no means for aggregation
Centre for Financial Management, Bangalore
40,000 (1.12)2
40,000 (1.12)3
Discount rate
The internal rate of return (IRR) of a project is the discount rate that makes its NPV equal to zero. It is represented by the point of intersection in the above diagram
Net Present Value
Assumes that the discount rate (cost of capital) is known Calculates the net present value, given the discount rate
Calculation of IRR
You have to try a few discount rates till you find the one that makes the NPV zero
Year Cash flow Discounting rate : 20% Discounting rate : 24% Discounting rate : 28%
Discount
factor 0 1 2 3 4 5 -100 34.00 32.50 31.37 30.53 79.90 1.000 0.833 0.694 0.579 0.482 0.402
Present
Value -100.00 28.32 22.56 18.16 14.72 32.12
Discount Present
factor 1.000 0.806 0.650 0.524 0.423 0.341 Value -100.00 27.40 21.13 16.44 12.91 27.25
Discount
factor 1.000 0.781 0.610 0.477 0.373 0.291
Present
Value -100.00 26.55 19.83 14.96 11.39 23.25
NPV = 15.88
NPV = 5.13
NPV = - 4.02
Calculation of IRR
NPV at the smaller rate Smaller Bigger Smaller discount + X discount discount Sum of the absolute values of the rate rate rate NPV at the smaller and the bigger discount rates
25%
400%
NO IRR :
C0 150
C1 -450
C2 375
C0
C1
IRR
P Q
-10,000 -50,000
20,000 75,000
100% 50%
Lending vs Borrowing
C0 A -4000
C1 6000
IRR 50%
4000
-7000
75%
-236
The internal rate of return of this project is the value of r in the expression -300,000 0 417,000 117,000
0 =
(1+r)0 (1+r)1 (1+r)2 (1+r)3 The value of r which satisfies the above expression is 30 percent
Centre for Financial Management, Bangalore
Modified IRR
0
-120
1
-80
2
20
3
60
4
80
5
100
6
120
PV = of TV NPV
189.6
r=15% 115 105.76 r =15% 91.26 r =15% 34.98 r =15% Terminal value (TV) = 467 MIRR = 16.2%
Payback Period
Payback period is the length of time required to recover the initial outlay on the project Naveen Enterprises Capital Project Year Cash flow Cumulative cash flow 0 -100 -100 1 34 - 66 2 32.5 -33.5 3 31.37 - 2.13 4 30.53 28.40 Pros Simple Cons Fails to consider the time value of money Ignores cash flows beyond the payback period
Rough and ready method for dealing with risk Emphasises earlier cash inflows
Average investment
:
Initial investment Average income before interest and taxes
Average investment
Total income after tax but before depreciation Initial investment
:
(Initial investment / 2) x years
Centre for Financial Management, Bangalore
Yes Yes
Yes No
No No
No ?
No ?
Yes
No
No
Yes
Yes
Yes
Yes
Yes
No
No
No
Yes
No
Yes
Perhaps
No
Yes
Yes
85.00
67.50 66.30 58.00 35.10
Technique
Accounting return on investment Payback period Net present value Internal rate of return Profitability index or benefit-cost ratio
None
12.35% 1.76 8.82 7.65 31.17
High
3.53% 30.00 33.20 59.41 11.18
No response
2.94% 1.76 5.29 4.12 15.88
Summary
A wide range of criteria has been suggested to judge the worthwhileness of investment projects. They fall into two broad categories : discounting criteria and non-discounting criteria. The important discounting criteria are : net present value, benefit cost ratio, and internal rate of return. The major non-discounting criteria are : payback period and accounting rate of return. The net present value (NPV) of a project is the sum of the present values of all the cash flows - positive as well as negative - that are expected to occur over the life of the project. The decision rule associated with the NPV criterion is : Accept the project if the NPV is positive and reject the project if the NPV is negative. NPV has certain properties that make it a very attractive decision criterion : NPVs are additive; the NPV rule assumes that the intermediate cash flows of a project are reinvested at a rate of return equal to the cost of capital; NPV calculation permits time varying discount rates
Centre for Financial Management, Bangalore
The standard NPV method is based on the assumption that the intermediate cash flows are re-invested at a rate of return equal to the cost of capital. When this assumption is not valid, the investment rates applicable to the intermediate cash flows need to be defined for calculating the modified net present value. The benefit cost ratio is defined as the present value of benefits (cash inflows) divided by the present value of costs (cash outflows). A project is considered worthwhile if the benefit cost ratio is more than 1 and not worthwhile if the benefit cost ratio is less than 1. The internal rate of return (IRR) of a project is the discount rate which makes its NPV equal to zero. In the NPV calculation we assume that the discount rate is known and determine the NPV. In the IRR calculation, we set the NPV equal to zero and determine the discount Centre for Financial Management, Bangalore rate that satisfies this condition.
The IRR and NPV rules lead to identical decisions provided two conditions are satisfied. First, the cash flows of the project must be conventional, implying that the first cash flow (initial investment) is negative and the subsequent cash flows are positive. Second, the project must be independent meaning that the project can be accepted or rejected without reference to any other project. There are problems in using IRR when the cash flows of the project are not conventional or when two or more projects are being compared to determine which one is the best. In the first case, it is difficult to define 'what is IRR' and in the second case IRR can be misleading. Further, IRR cannot distinguish between lending and borrowing. Finally, IRR is difficult to apply when short-term interest rates differ from long-term interest rates. There are two possible economic interpretations of internal rate of return: (i) The internal rate of return represents the rate of return on the unrecovered investment balance in the project . (ii) The internal rate of return is the rate of return earned on the initial investment made in the project.
Centre for Financial Management, Bangalore
Despite NPV's conceptual superiority, managers seem to prefer IRR over NPV because IRR is intuitively more appealing as it is a percentage measure. Is there a percentage measure that overcomes the shortcomings of the regular IRR? Yes, there is one and it is called the modified IRR or MIRR. It is calculated by solving the following equation : Terminal value of cash inflows Present value of cash outflows = (1 + MIRR)n The payback period is the length of time required to recover the initial cash outlay on the project. According to the payback criterion, the shorter the payback period, the more desirable the project. Firms using this criterion generally specify the maximum acceptable payback period. Payback period is widely used because it is simple, both in concept and application, and it is a rough and ready method for dealing with risk. However, it has serious limitations : it does not consider the time value Centre for Financial Management, Bangalore of
The accounting rate of return, also called the average rate of return,
is defined as Profit after tax Book value of the investment The accounting rate of return has certain virtues : it is simple to calculate; it is based on accounting information which is readily available and familiar to businessmen; it considers benefits over the
The most popular methods for evaluating small sized projects are