Price AdjustmentsPrice Adjustment
Price AdjustmentsPrice Adjustment
Price AdjustmentsPrice Adjustment
By
Engr. M. Mazhar-ul-Islam
Convener PEC Act & Byelaws Committee
Meaning Adjustment of Contract Price for increase or decrease of prices of adjustable materials / services.
It is compensation and not extra benefit to Contractor.
Results of non-adjustments: Project delay, disputes, cancellation of contracts resulting more cost for the Employer. Exclusions: Variation Orders Claims Subsequent Legislation Measurement of Quantities
Standard Bidding Documents for Civil Works: Clause 70.1 of PCC. Standard Bidding Documents for E&M Works: Clause 47.1 of PCC. Standard Form of Bidding Documents (Smaller Contractor): Preamble. Standard Contract for Consultancy (Time Based): Clause 6.2(a) SC. Standard Procedure & Formula for Price Adjustments.
Below Rs 30 million contract (below C-5 Ceiling)not covered for Price Adjustment.
Weightage 3 0.350
Applicable Index 4
(ii)
(iii) (iv) (v) (vi) (vii) (viii)
Local Labor
Cement in bags Reinforcing Steel High Speed Diesel (HSD) Bricks Bitumen
PICC
PICC PICC PICC PICC PICC
Total
1.000
9
Employers using this price adjustment provisions may add or delete any elements as deemed appropriate to the project.
10
Indices for (ii) to (vii) are taken from FBS. The base cost indices or prices shall be those applying 28 days prior to the latest day for submission of bids. Current indices or prices shall be those applying 28 days prior to the last day of the billing period.
11
Any fluctuation in the indices or prices of materials other than those given above shall not be subject to adjustment of the Contract Price.
12
Fixed portion shown here is for typical road project, Employer to determine the weightage of Fixed Portion considering only those cost elements having cost impact of seven (7) revised to five (5) percent or more on his specific project.
13
Pn = A + b Ln + c Mn + d En + Lo Mo Eo
14
Pn is Price Adjustment Factor A is constant, representing the nonadjustable portion b, c, d, etc. are coefficients / weightages representing
Ln, Mn, En, etc. are the current cost indices of cost elements for month n Lo, Mo, Eo, etc. are base cost indices corresponding to
Source of indices shall be those listed in Appendix-C as approved by Engineer. As the basis of Price adjustment, Contractor shall have submitted the tabulation of Weightages & Source of Indices if different than Appendix C.
16
Base cost indices or prices shall be those prevailing on the day 28 days prior to the latest date of bid submission. Current indices or prices shall be those prevailing on the day 28 days prior to the last day of the period to which a particular monthly statement is related.
17
If at any time, current indices are not available, provisional indices are determined by the Engineer will
18
Clause 43 GC: Time for Completion within Schedule or extended Schedule pursuant to Clause 44 GC.
Clause 44 GC: Extension of Time for Completion not for fault of Contractor. Clause 48GC: Taking over Certificate by the Engineer.
19
20
The Weightages of each of the cost factors shall be adjusted at any stage of the project, if it is found unreasonable, unbalanced or inapplicable in review of the Engineer.
Weightages change for Instruction under clause 51(v.o.). Such adjustments shall have to be agreed in such v.o.
21
22
Applicable to Time Based assignment Contract only. Generally increase in cost for services. Exclusions:
Increase in ceiling Cost of Additional work
Payment to be adjusted under Clause 6.2(a) SC. Applicable for both Foreign & Local currency adjustments.
23
Option 1
Billing rates for each person shall be adjusted in each July. First adjustment in July following submission of final proposal. Revision Elements:
Annual increment Increase due to promotion Salary revision to Clause 5.3 SC or otherwise
24
Option 2
Using the formula: RI = RIo x II/IIo Where: RI is the adjusted billing rate RIo is the billing rate payable II is the combined consumer Price Index (CPI) General for Govt. employees IIo is CPI in July of the year Consultant submitted its proposal
25
Rf is adjusted remuneration Rfo is the remuneration payable If is the official salary index in foreign country for the first month for which adjustment is suppose to have effect Ifo is the official salary index for the monthly date of contract
26
THANK YOU
27