The document describes the proposed configuration for upgrading the control system of four gas turbines (GT1-GT4) by replacing the existing DOS-based operator interface stations with new Windows-based human-machine interface (HMI) stations. One HMI would connect to each GT for redundancy. Commissioning activities would include backing up files from the old stations, replacing hardware in the stations with HMI components, establishing communication between the HMIs and GTs, and checking that configuration data and screen logic match the old stations.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online from Scribd
The document describes the proposed configuration for upgrading the control system of four gas turbines (GT1-GT4) by replacing the existing DOS-based operator interface stations with new Windows-based human-machine interface (HMI) stations. One HMI would connect to each GT for redundancy. Commissioning activities would include backing up files from the old stations, replacing hardware in the stations with HMI components, establishing communication between the HMIs and GTs, and checking that configuration data and screen logic match the old stations.
Original Description:
A brief overview of Mark-V Gas Turbine Control System
The document describes the proposed configuration for upgrading the control system of four gas turbines (GT1-GT4) by replacing the existing DOS-based operator interface stations with new Windows-based human-machine interface (HMI) stations. One HMI would connect to each GT for redundancy. Commissioning activities would include backing up files from the old stations, replacing hardware in the stations with HMI components, establishing communication between the HMIs and GTs, and checking that configuration data and screen logic match the old stations.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online from Scribd
The document describes the proposed configuration for upgrading the control system of four gas turbines (GT1-GT4) by replacing the existing DOS-based operator interface stations with new Windows-based human-machine interface (HMI) stations. One HMI would connect to each GT for redundancy. Commissioning activities would include backing up files from the old stations, replacing hardware in the stations with HMI components, establishing communication between the HMIs and GTs, and checking that configuration data and screen logic match the old stations.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online from Scribd
Download as ppt, pdf, or txt
You are on page 1of 5
MARK V CONTROLS
OPERATOR INTERFACE STATION
• Issue commands to start / stop the unit
• Manage and log alarms • Monitor unit operation • Configue or modify control, protection, monitoring, logging PRESENT CONFIGURATION • 3 <I> INTERFACE OPERATOR STATIONS FOR 4 GT’S • <I> STATIONS ON DOS BASED PC’s
GT3 GT2 GT1
GT4
<I> <I> <I>
PROPOSED CONFIGURATION • One HMI connected to each machine –HMI-Windows based PC • Interconnection for redundancy
GT4 GT3 GT2 GT1
HMI HMI HMI HMI
COMMISSIONING ACTIVITIES
• * Back up files from 'I' station project software
* Power down station and replace With HMI CPU * Replace SDCC card * Replace PROM set * Connect arcnet cable to HMI and power up * Establish communication with MK V * Check CSP,Constants and alarm points integrity with