CPM 20
CPM 20
PM 1 Im in charge of the construction of a retail development in the centre of a large town. There are 26 retail units and a super market in the complex. My main responsibilities are to co-ordinate the work of the various contractors to ensure that the project is completed to specification, within budget and on time. PM 2 I am directing a team of research scientists. We are running trials on a new analgesic drug on behalf of a pharmaceutical company. It is my responsibility to design the experiments and make sure that proper scientific and legal procedures are followed, so that our results can be subjected to independent statistical analysis. PM 3- The international aid agency which employs me is sending me to New Delhi to organize the introduction of multimedia resources at a teachers training college. My role is quite complex. I have to make sure that appropriate resources are purchased- and in some cases developed within the college. I also have to encourage the acceptance of these resources by lecturers and students within the college. 3
darla/smbs/vit
PROJECT
A project is a series of activities directed to accomplishment of a desired objective.
application of a collection of tools and techniques to direct the use of diverse resources towards the accomplishment of a unique, complex, one time task within time, cost and quality constraints origins lie in World War II, when the military authorities used the techniques of operational research to plan the optimum use of resources
Its
One
of these techniques was the use of networks to represent a system of related activities
5
Project Definition and Scope Technical Design Financing Contracting Implementation Performance Monitoring
method of breaking down a project into individual elements ( components, subcomponents, activities and tasks) in a hierarchical structure which can be scheduled and financed It defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project It is foundation of project planning It is developed before identification of dependencies and estimation of activity durations It can be used to identity the tasks in the CPM and PERT
8
10
Gantt Chart
Graph or bar chart with a bar for each project activity that shows passage of time
11
HISTORY OF CPM/PERT
Critical
El Du Pont de Nemours & Co. (1957) for construction of new chemical plant and maintenance shut-down Deterministic task times Repetitive nature of jobs
Project
U S Navy (1958) for the POLARIS missile program Multiple task time estimates (probabilistic nature) Activity-on-arrow network construction Non-repetitive jobs (R & D work)
12
VIDEO
13
PROJECT NETWORK
Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects Use of nodes and arrows Arrows An arrow leads from tail to head directionally Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work Nodes A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish Dummy Activity Indicates only precedence relationships Does not require any time of effort
14
CONT
Activity-on-node (AON)
nodes represent activities, and arrows show precedence relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points in time
PRECEEDING ACTIVITY SUCCESSOR
EVENT
15
3
2 0
3
Design house and obtain financing
1
Order and receive materials
4
Select paint
6
1
Select carpet
7
darla/smbs/vit
2 2 Start 1 3 3 1
Order and receive materials
4 3
Finish work
7 1 5 1
Select paint
6 1
Select carpet
16
B
A must finish before either B or C can start C
A
C B A B A both A and B must finish before C can start
C
D
B
Dummy
A must finish before B can start both A and C must finish before D can start 17
CONCURRENT ACTIVITIES
3
Lay foundation
Dummy 2 0
Lay foundation
3 2
1
Order material
Order material
18
NETWORK EXAMPLE
Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ?
19
For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time".
20
21
CPM CALCULATION
Path
A connected sequence of activities leading from the starting event to the ending event
Critical Path
Critical Activities
22
FORWARD PASS
Earliest
Start Time (ES) earliest time an activity can start ES = maximum EF of immediate predecessors finish time (EF) earliest time an activity can finish earliest start time plus activity time
EF= ES + t
Earliest
23
BACKWARD PASS
darla/smbs/vit
24
CPM ANALYSIS
Draw the CPM network Analyze the paths through the network Determine the float for each activity Compute the activitys float float = LS - ES = LF - EF Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project Find the critical path, is that the sequence of activities and events where there is no slack i.e.. Zero slack Longest path through a network Find the project duration is minimum project completion time
25
CPM EXAMPLE:
CPM Network f, 15 a, 6 g, 17 i, 6 h, 9
b, 8
d, 13 c, 5 e, 9
26
j, 12
CPM EXAMPLE
ES
and EF Times
f, 15 g, 17 i, 6
a, 6 0 6
h, 9
b, 8
0 8 c, 5 0 5 e, 9
27
d, 13
j, 12
CPM EXAMPLE
ES
and EF Times
a, 6 0 6
f, 15 6 21 g, 17 6 23 i, 6
h, 9
b, 8
0 8 c, 5 0 5 d, 13 8 21 e, 9 5 14
28
j, 12
CPM EXAMPLE
ES
and EF Times
a, 6 0 6
f, 15 6 21 g, 17 6 23 i, 6 23 29
h, 9 21 30
b, 8
0 8 c, 5 0 5 d, 13 8 21 e, 9 5 14 j, 12 21 33 Projects EF = 33
29
CPM EXAMPLE
LS
and LF Times
a, 6 0 6
f, 15 6 21 g, 17 6 23 i, 6 23 29 27 33
h, 9 21 30 24 33
b, 8 0 8
c, 5 0 5
d, 13 8 21 e, 9 5 14
j, 12 21 33 21 33
30
CPM EXAMPLE
LS
and LF Times
a, 6 0 6 4 10 b, 8 0 8 0 8 c, 5 0 5 7 12
f, 15 6 21 18 24 g, 17 6 23 10 27 d, 13 8 21 8 21 e, 9 5 14 12 21
i, 6 23 29 27 33
h, 9 21 30 24 33
j, 12 21 33 21 33
31
CPM EXAMPLE
Float
a, 6 3 0 6 3 9 b, 8 0 0 8 0 8 c, 5 7 0 5 7 12
f, 15 3 6 21 9 24 g, 17 4 6 23 10 27 d, 13 0 8 21 8 21 e, 9 7 5 14 12 21
i, 6 23 29 4 27 33
h, 9 3 21 30 24 33
j, 12 0 21 33 21 33
32
CPM EXAMPLE
Critical
Path
f, 15 g, 17 i, 6
a, 6
h, 9
b, 8
d, 13 c, 5 e, 9
33
j, 12
VIDEO
34
darla/smbs/vit
PERT
PERT is based on the assumption that an activitys duration follows a probability distribution instead of being a single value Three time estimates are required to compute the parameters of an activitys duration distribution: pessimistic time (tp ) - the time the activity would take if things did not go well most likely time (tm ) - the consensus best estimate of the activitys duration optimistic time (to ) - the time the activity would take if things did go well
te =
tp + 4 tm + t o
6
2
Variance: Vt =2 =
tp - to
6
35
PERT ANALYSIS
Draw the network. Analyze the paths through the network and find the critical path. The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum Probability computations can now be made using the normal distribution table.
36
PROBABILITY COMPUTATION
Determine probability that project is completed within specified time x- Z=
37
PERT EXAMPLE
Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -4 6 8 B -1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 38 K G,I 3 5 7
C B F G
39
PERT EXAMPLE
Activity
A B C D E F G H I J K
Expected Time
6 4 3 5 1 4 2 6 5 3 5
Variance
4/9 4/9 0 1/9 1/36 1/9 4/9 1/9 1 1/9 4/9
40
PERT EXAMPLE
Activity
A B C D E F G H I J K
ES
0 0 6 6 6 9 9
EF
6 4 11 7 13 11 13 13 19 23
LS
0 5 9 15 12 9 16 19 18 22 18
LF
6 9 6 20 13 13 18 14 13 20 23
Slack
0 *critical 5 9 0* 9 6 0* 7 20 1 18 0* 23 1 0*
41
18
PROJECT COST
Project managers may have the option or requirement to crash the project, or accelerate the completion of the project. This is accomplished by reducing the length of the critical path(s). The length of the critical path is reduced by reducing the duration of the activities on the critical path. If each activity requires the expenditure of an amount of money to reduce its duration by one unit of time, then the project manager selects the least cost critical activity, reduces it by one time unit, and traces that change through the remainder of the network. As a result of a reduction in an activitys time, a new critical path may be created. When there is more than one critical path, each of the critical paths must be reduced. If the length of the project needs to be reduced further, the process is repeated.
43
PROJECT CRASHING
Crashing reducing project time by expending additional resources Crash time an amount of time an activity is reduced Crash cost cost of reducing activity time Goal reduce project duration at minimum cost
44
ACTIVITY CRASHING
Crash cost
Crashing activity Slope = crash cost per unit time Normal Activity
Normal cost
Normal time
Crash time Activity time 45
TIME-COST RELATIONSHIP
Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs
Time-Cost Tradeoff
Min total cost = optimal project time Total project cost Indirect cost
Direct cost
46
time
2 8 1
12
4
12
7 4 3 4
5 4
6 4
47
Normal cost Rs 3000 2000 4000 50000 500 500 1500 75000
Crash time 7 5 3 9 1 1 3
Crash cost Rs 5000 3500 7000 71000 1100 1100 22000 110700
slope
400 500 3000 7000 200 200 7000
48
R500
2 8 1
12
R7000 4
12
Project duration = 36
R700 7 4 6 4 R200
From..
R400
3 4 R3000
5 4 R200
R500 2 8 1
7
R7000 4
12
R700 7 4
To.. Project
R400
duration = 31
Additional cost = R2000
3 4 R3000
5 4 R200
6 4 R200
49
BENEFITS OF CPM/PERT
Useful at many stages of project management Mathematically simple Give critical path and slack time Provide project documentation Useful in monitoring costs
LIMITATIONS TO CPM/PERT
Clearly defined, independent and stable activities Specified precedence relationships Over emphasis on critical paths Deterministic CPM model Activity time estimates are subjective and depend on judgment PERT assumes a beta distribution for these time estimates, but the actual distribution may be different PERT consistently underestimates the expected project completion time due to alternate paths becoming critical
To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias
51
Project (Microsoft Corp.) MacProject (Claris Corp.) PowerProject (ASTA Development Inc.) Primavera Project Planner (Primavera) Project Scheduler (Scitor Corp.) Project Workbench (ABT Corp.)
52
darla/smbs/vit
54