Bored Pile Procedure :
1. Set up the Location of Bored Pile 2. Insert Casing 3. Drilling 4. Removing Slime 5. KODEN-Test 6. Insert of Steel Cage 7. Insert Tremie Pipe 8. Pouring the Concrete 9. Removing Casing
2. Insert casing
casing must be stand vertical ( by checking verticality of casing when insert casing )
BG - 28
SD - 515
Recorder Unit
Winch Unit
1m Length
3m Length
2m Length
Use mobile crane to hang the hopper Then connect each tremie pipe After that put it into the bored pile hole until bottom
When we pour concrete, we have to bury the tremie pipe into concrete as below :
Diameter of Bored Pile
1000 1800
Strength
fck ( Mpa ) 21 > fck 21 fck 35 fck > 35 Strength of mix ( Mpa ) fck + 7 fck + 8.5 fck + 10
4. Removing slime
5. KODEN Test 6. Inserting Steel Cage 7. Inserting Tremie Pipe 8. Pouring the concrete 9. Remove casing Total Cycle Time
1
1 2 1 2 1.5 18.8