Lean Tools and Their Implementation
Lean Tools and Their Implementation
Guided by: Prof. Gajanan Patange Project by: Bharat Chaudhary (09ME021)
Content
Introduction to lean manufacturing Objective of Project Wastes in Lean Manufacturing Lean tools
Kanban
SMED ( Single minute exchange of dies) Kaizen
Content
Case studies 1) Navkala Plastic Molding pvt ltd, Ahmedabad 2) Real Casting pvt ltd, Ahmedabad 3) G.S brass Enterprise, Jamnagar ( Under process) Propose Implantations Conclusion
It is a whole new way of thinking, to serve the customers with high quality Products, low cost and short delivery times. Lean is a philosophy that seeks to eliminate waste in all aspects of a firms production activities: human relations, vendor relations, technology, and the management of materials and inventory.
associated
with
manufacturing
equally applicable to both service and administration processes. Currently it is also being adopted by manufacturing and meat processing sectors. the food
Objective of Project
Lean implementation is focused on getting the right things, to the right place, at the right time, in the right quantity to achieve perfect work flow while minimizing waste and being flexible and able to change. The objective of this Thesis is to carry out a study, proposal and analysis of improvements about Manufacturing in Plastic injection molding, Casting and Brass products machining Industries. By getting these improvements; it would have some benefits, adding more production and easiness work and also an improvement in terms of quality.
Muda (or non value-added work): Muda is discovered after the process is in place and is dealt with reactively. It is seen through variation in output. Muri (or overburden): It is focused on the preparation and planning of the process, or what work can be avoided by design.
Mura (or unevenness): It focuses on implementation and the elimination of fluctuation at the scheduling or operations level, such as quality and volume
Muda wastes
1)
2) Transportation: To move products that is not actually required to perform the processing.
3)
4) Inventory: All components, work-in-progress and finished product not being processed. 5) Motion: People or equipment moving or walking more than is required to perform the processing 6) 7) Over-Processing: Due to poor tool or product design creating activity. Defects: The effort involved in inspecting for and fixing defects.
Muri wastes
Work Flow: Logical directions to be taken. Takt time: Maximum time allowed producing in order to meet demand. When everyone knows the standard condition, and the standardized work sequences, the results observed are:
Employee morale is heightened Higher quality is achieved Productivity is improved Costs are reduced.
Mura wastes
It is based on little or no inventory, by supplying the production process with the right part, at the right time, in the right amount, and first-in, first out component flow.
Just in Time systems create a pull system in which each sub-process withdraws its needs from the preceding sub-processes, and ultimately from an outside supplier.
Value Stream Mapping is a method of creating a "One page picture" of all the processes that occur in a company, from the time a customer places an order for a product, until the customer has received that product in their facility. The goal is to depict material and information flows across and throughout all Value-Adding Processes required to produce and ship the product to the customer. Value Stream Maps document all of the processes used to produce and ship a product, both Value-Adding and Non-Value-Adding (Waste) processes.
Steps in VSM
Plan the activity, Walk the process and collect the process and step data, Produce and analyze the current-state value stream map, Produce a future-state map,
2)5S +Safety
TPM (Total Productive Maintenance) is an excellent method for meeting the demands and for continuous flow manufacturing on equipment. TPM does the following:
It increases OEE (Overall Equipment Effectiveness) using improvement activities. It establishes an autonomous maintenance program performed by equipment operators. It establishes a planned maintenance system. It requires training to improve operation and maintenance skill It institutes a system for MP (maintenance prevention) design and early equipment management.
Types of Losses
Break Downs
Setup and Adjustment
Losses
Startup Rejects
Many people treat it just another Program of the month without paying any focus and also doubt about the effectiveness.
Not sufficient resources (people, money, time, etc.) and assistance provided
4) KANBAN
The premise of Kanban is to create Visual Indicators to allow the operators to be the ones who determine how much of a product to run when to stop or change over. Kanban rules also tell the operators What Steps to take when they have problems and whom to go when Problems occurs. Benefits:
It provides a rapid and efficient way of converting a manufacturing process from running the current product to running the next product. This rapid changeover is key to reducing production lot sizes and thereby improving flow.
Steps:
Separate internal from external setup operations Convert internal to external setup Standardize function, not shape Use functional clamps or eliminate fasteners altogether Use intermediate jigs Adopt parallel operations (see image on next slide) Eliminate adjustments Mechanization
Kaizen is a combination of two words, kai and Zen. Kai means to change or modify and Zen means to Improve or make better. Kaizen Principles:
Focus on improvements Blame the process and not the person Create work teams Develop self-discipline, a sense of personal responsibility and accountability. Enable Employees (i.e. Set employees for success)
Kaizen Process
Case Study:1
Company Profile: Name: Navkala plastics Number of Working People: 40 Turn Over: 10crores Product: Plastic caps, bowls, containers, bottles, etc.
Flow diagram
Identification of problem
Problem no
1 2
Problems
Too much die changing time Die life is less
3
4 5 6 7 8 9 10 11 12
70
20 90 60 50 30 60 90 50 90 70
13
Pareto chart
Why-Why Analysis
Main cause: - Too much Die changing time Why 1 - All the external operations were also performed after stopping the machine Why 2 -There was only one operator per machine with no helper, and die was heavy Main cause: Die life was less
Main cause: Production rate varied continuously Why1- Time wastage between removals of product from mold. Why2- Machine stops as door opens.
Main cause: Improper space utilization Why1- Whole floor was covered by products, wastes, packing materials and other things Why2- No proper layout and Upper part of factory was not used Why3- Lack of 5S Principle implementation
5S analysis sheet
Proposals:
Sorting
Extra wooden roof at the top can accommodate all unused item, increasing floor space Use only needed materials, equipment, tooling & supplies when needed. Eliminate excess / obsolete equipment & inventory Improve space utilization by eliminating space taken up by unneeded items and organizing needed items
Set in Order
Locate missing tools, documents, instructions, keys and inventory
Put everything in a useable place Make every item visible, reachable & available when needed
Shine in Order
Remove dirt, oil, scraps and garbage Assign cleaning responsibilities - team effort
Standardization
Maintain and control continual improvement Ensure systematic organization, sorting, and scrubbing clean are synchronized
TPM Implementation
3) Start up rejects
Above graph shows after starting the machine rejects are very high Solution: For every die parameters like pressure, temperature, dwell time, feeding rate, etc are different. Instead of using try and error method every time whille using the die, some standardised parameters should be used. The parameters which are found ok should be stored and directly should be implemented next time.
4) Production rejects
There were many rejects due to some machine error, due to improper cooling, plastic getting stick to the die and runner scraps.
Solution Some rejects are always there but by proper cooling of die sticking problem can be minimized . Die should be made such that runners scrap is less Nozzle should be blockage free so mass flow rate is constant
Case study:-2
Company Profile:
Flow chart
Problems:
1) Too much wastes 2) Sand reclamation system was not there 3) Improper space Utilization 4) Too much inventory 5) Environmental Pollution
Pollution due to
Pattern Making
VOC (volatile organic compound) from glues, epoxies, and paints. Waste water: Little or no wastewater generated ,but there is no plan for water utilization.
Mold and Core Preparation and Pouring Waste mold and core sand potentially containing metals and residual chemical binders Charging and Melting Air Emissions: Products of combustion, oil vapors, particulates, metallic oxide fumes
Shakeout, Cooling and Sand Handling Dust and metallic particulates; VOC and organic compounds from the sand disposal as there was no treatment system. Air emission
Concentration in mg/kg Sr. No. Waste
Cu
Zn
Pb
Ni
F1 79 169 306
F2 71 138 297
F3 67 149 319
F1 172 263 49
F2 180 255 52
F3 158 248 57
From
Ladle MOEF Standard
141
130
150
340
312
302
30
26
23
239
227
244
300
1000
100
50
Result
The foundries generate lot of Solid waste like sand waste, dust, and slag waste, waste from ladle which is harmful for human health. There is no arrangement for beneficial reuse, disposal, treatment and handling. Regarding air emission, foundry is emitting pollutants from different department namely Furnace operation, Preparation of cores and molds, Casting, Shakeout and reclamation. There are drastic deviations in all department compare to MOEF Standard. There is low air emission where induction furnace is installed but they are not running with highest efficiency.
5S- It involves proper arrangement of all the equipments at right place, proper layout of the factory, proper cleaning, etc. If proper arrangement are there then everything can be found out easily found when required reducing unnecessary buying of inventory
Why 5S
Proposals:
Extra roofs, where unwanted material can be stored so floor space can be utilized properly.
All the Pattern, Cope and Drag which are not in use should be marked and stored in separate section.
Every section should be separate pattern making, poring, grinding, etc. Better cleanliness of Equipment's like Muller machine, Grinders, Containers which are used for pulling raisin from tanks. Make every item visible, reachable & available when needed Ensure systematic organization, sorting, and scrubbing clean are synchronized Use safety equipments like safety shoes, Helmets, Hand gloves, etc.
Conclusion
There is an infinite number of ways of implement Lean Manufacturing in these Industries in future, both the management and the workers have to work together for successful implementation. Most of lean tools are not costly and can be implemented easily, after attainment of its use. Indian small and medium scale industries can get large advantage of it.